ABOVE THE 75'-0"" LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
|
$55.88 |
$23.77 |
$79.65 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS REMOVAL LABORER SCOPE OF WORK: INCLUDES SITE MOBILIZATION, INITIAL SITE CLEANUP, SITE PREPARATION, REMOVAL OF ASBESTOS-CONTAINING MATERIAL AN
|
$46.48 |
$25.93 |
$72.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER
|
$23.52 |
$13.37 |
$36.89 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS WORKERS/INSULATOR
|
$56.32 |
$26.52 |
$82.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BOILERMAKER
|
$51.98 |
$42.11 |
$94.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICK TENDER
|
$42.60 |
$22.13 |
$64.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER; MARBLE SETTER
|
$45.53 |
$20.29 |
$65.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: CARPENTER, CABINET INSTALLER, INSULATION INSTALLER, HARDWOOD FLOOR WORKER AND ACOUSTICAL INSTALLER FOOTNOTE: WORK OF FORMING IN THE CONSTRU
|
$52.24 |
$26.18 |
$78.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: MILLWRIGHT FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS U
|
$52.24 |
$26.68 |
$78.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: PILEDRIVERMEN/DERRICK BARGEMAN, BRIDGE OR DOCK CARPENTER, HEAVY FRAMER, ROCK BARGEMAN OR SCOWMAN, ROCKSLINGER, SHINGLER FOOTNOTE: WORK OF F
|
$52.37 |
$26.18 |
$78.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: PNEUMATIC NAILER, POWER STAPLER FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HO
|
$52.37 |
$26.18 |
$78.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: SAWFILER FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USE
|
$52.34 |
$26.18 |
$78.52 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: SCAFFOLD BUILDER FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGIN
|
$45.37 |
$25.43 |
$70.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: TABLE POWER SAW OPERATOR FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTA
|
$52.34 |
$26.18 |
$78.52 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASON/CONCRETE FINISHER
|
$47.70 |
$27.07 |
$74.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
|
$51.39 |
$23.77 |
$75.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
|
$54.93 |
$23.77 |
$78.70 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR. OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 25- CONCRETE PUMP OPERATOR-TRUCK MOUNTED; RUBBER-TIRE
|
$67.91 |
$33.20 |
$101.11 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$48.13 |
$17.49 |
$65.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER (ASSISTANT TENDER)
|
$52.37 |
$3.27 |
$55.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER (STANDBY)
|
$56.37 |
$3.27 |
$59.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER (TENDER)
|
$55.37 |
$3.27 |
$58.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER (WET)
|
$112.74 |
$3.27 |
$116.01 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL
|
$21.45 |
$11.27 |
$32.72 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL
|
$52.24 |
$26.18 |
$78.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL FINISHER/TAPER
|
$49.33 |
$26.82 |
$76.15 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELEVATOR MECHANIC FOOTNOTE: A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEA
|
$69.43 |
$38.44 |
$107.87 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
EQUIPMENT OPERATOR, TOWER CRANE REPAIRMAN; TRACTOR LOADER OPERATOR; WOODS MIXER OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIP
|
$66.41 |
$33.20 |
$99.61 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
FIRE STOP TECHNICIAN
|
$39.94 |
$20.65 |
$60.59 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
FT. FROM THE GROUND FLOOR OR SUPPORTING STRUCTURE: DOUBLE THE REGULAR STRAIGHT-TIME RATE OF PAY. SAFETY NETS, IF USED, WILL NOT INVALIDATE THIS
|
$54.61 |
$25.16 |
$79.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
GLAZIER FOOTNOTE: ADDITIONAL $1.25 PER HOUR FOR WORK IN A CONDOR, FROM THE THIRD FLOOR AND UP ADDITIONAL $1.25 PER HOUR FOR WORK ON THE OUTSIDE OF THE
|
$53.05 |
$30.64 |
$83.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEEL
|
$67.18 |
$33.20 |
$100.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER.$ 50.70 35.15 IRONWORKER
|
$45.78 |
$26.51 |
$72.29 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 1: CLEANING AND HANDLING OF PANEL FORMS; CONCRETE SCREEDING FOR ROUGH STRIKE-OFF; CONCRETE, WATER CURING; DEMOLITION LABORER, THE CLEANI
|
$46.48 |
$25.95 |
$72.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 2: ASPHALT SHOVELER; CEMENT DUMPER; CESSPOOL DIGGER AND INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE HANDLING OF THE CHU
|
$47.03 |
$25.95 |
$72.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 3: BUGGYMOBILE PERSON; CONCRETE CUTTING TORCH; CONCRETE PILE CUTTER; DRILLER, JACKHAMMER, 2-1/2 FT. DRILL STEEL OR LONGER; DRI-PAK-IT MA
|
$47.58 |
$25.95 |
$73.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 4: ASPHALT RAKER, LUTE PERSON, IRONER, ASPHALT DUMP PERSON, AND ASPHALT SPREADER BOXES; CONCRETE CORE CUTTER, GRINDER OR SANDER; CONCRET
|
$49.13 |
$25.95 |
$75.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 5: BLASTER POWDER, ALL WORK OF LOADING HOLES, PLACING AND BLASTING OF ALL POWDER AND EXPLOSIVES OF WHATEVER TYPE, REGARDLESS OF METHOD U
|
$49.48 |
$25.95 |
$75.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER, TUNNEL: GROUP 1: BATCH PLANT LABORER; CHANGEHOUSE PERSON; DUMP PERSON; DUMP PERSON; SWAMPER; TUNNEL MATERIALS HANDLING PERSON; NIPPER; POT TE
|
$53.60 |
$25.74 |
$79.34 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER, TUNNEL: GROUP 2 BULL GANG MUCKER, TRACK PERSON; CHUCKTENDER, CABLETENDER; CONCRETE CREW, INCLUDING RODDER AND SPREADER; LOADING AND UNLOADING
|
$53.92 |
$25.74 |
$79.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER, TUNNEL: GROUP 3 BLASTER, DRILLER, POWDER PERSON; CHEMICAL GROUT JET PERSON; CHERRY PICKER PERSON; GROUT GUN PERSON; GROUT MIXER PERSON; GROUT
|
$54.38 |
$25.74 |
$80.12 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER, TUNNEL: GROUP 4: DIAMOND DRILLER; SANDBLASTER; SHAFT AND RAISE WORK
|
$55.07 |
$25.74 |
$80.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: PLASTER CLEAN-UP LABORER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORON
|
$46.17 |
$25.97 |
$72.14 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: PLASTER TENDER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL
|
$48.72 |
$25.97 |
$74.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: DRILLING CREW LABORER
|
$47.94 |
$20.86 |
$68.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: ELECTRONIC TRACKING LOCATOR
|
$51.96 |
$20.86 |
$72.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: HORIZONTAL DIRECTIONAL DRILL OPERATOR
|
$49.96 |
$20.86 |
$70.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: VEHICLE OPERATOR/HAULER
|
$48.11 |
$20.86 |
$68.97 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 1 PROTECTIVE COATING, PAVEMENT SEALING, INCLUDING REPAIR AND FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE IN
|
$49.30 |
$23.97 |
$73.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 2 TRAFFIC SURFACE ABRASIVE BLASTER; POT TENDER - REMOVAL OF ALL TRAFFIC LINES AND MARKINGS BY ANY METHOD AND PR
|
$50.60 |
$23.97 |
$74.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 3 TRAFFIC DELINEATING DEVICE APPLICATOR: LAYOUT AND APPLICATION OF PAVEMENT MARKERS, DELINEATING SIGNS, RUMBLE
|
$52.61 |
$23.97 |
$76.58 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 4 STRIPER: LAYOUT AND APPLICATION OF TRAFFIC STRIPES AND MARKINGS; HOT THERMO PLASTIC; TAPE TRAFFIC STRIPES AND
|
$54.35 |
$23.97 |
$78.32 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: EQUIPMENT SPECIALIST (OPERATES CRAWLER TRACTORS, COMMERCIAL MOTOR VEHICLES, BACKHOES, TRENCHERS, CRANES, OVERHEAD & UNDERGROUND DIS
|
$53.30 |
$22.26 |
$75.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: GROUNDMAN HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DA
|
$40.76 |
$21.76 |
$62.52 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: LINEMAN; CABLE SPLICER HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVI
|
$70.16 |
$24.71 |
$94.87 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MARBLE FINISHER
|
$43.38 |
$15.36 |
$58.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MODULAR FURNITURE INSTALLER
|
$25.00 |
$13.06 |
$38.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR, POWER EQUIPMENT: BARGE MATE
|
$61.34 |
$40.95 |
$102.29 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR, POWER EQUIPMENT: DECKMATE..$ 61.82 40.95 OPERATOR, POWER EQUIPMENT: DREDGE DOZER
|
$61.93 |
$40.95 |
$102.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR, POWER EQUIPMENT: FIREMAN-OILER, DECKHAND, BARGEMAN, LEVEEHAND
|
$60.73 |
$40.95 |
$101.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR, POWER EQUIPMENT: WINCH OPERATOR
|
$61.27 |
$40.95 |
$102.22 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 12- AUTO GRADER OPERATOR; AUTOMATIC SLIP FORM OPERATOR; DRILLING MACHINE OPERATOR, BUCKET OR AUGER TY
|
$66.58 |
$33.20 |
$99.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 13- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM PREMIUM PA
|
$66.68 |
$33.20 |
$99.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 14- CANAL LINER OPERATOR; CANAL TRIMMER OPERATOR; REMOTE- CONTROL EARTH-MOVING EQUIPMENT OPERATOR; WH
|
$66.71 |
$33.20 |
$99.91 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 15- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM; RUBBER-T
|
$66.79 |
$33.20 |
$99.99 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 16- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM; RUBBER-T
|
$66.91 |
$33.20 |
$100.11 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 17- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM; TANDEM T
|
$67.08 |
$33.20 |
$100.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 19- ROTEX CONCRETE BELT OPERATOR; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM
|
$67.29 |
$33.20 |
$100.49 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 2- ASPHALT-RUBBER PLANT OPERATOR;COIL TUBING RIG OPERATOR, CONCRETE MIXER OPERATOR-SKIP TYPE; CONVEYO
|
$64.18 |
$33.20 |
$97.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 2-0 RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM; RUBBER-TIRED EARTH-MOVING EQUI
|
$67.41 |
$33.20 |
$100.61 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 21- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM PREMIUM PAY: $10.00 PER HOUR SH
|
$67.58 |
$33.20 |
$100.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 22- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTE
|
$67.68 |
$33.20 |
$100.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 23- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTE
|
$67.79 |
$33.20 |
$100.99 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 3- ASPHALT-RUBBER BLEND OPERATOR; BOBCAT OR SIMILAR TYPE; EQUIPMENT GREASER; FORD FERGUSON; HELICOPTE
|
$64.67 |
$33.20 |
$97.87 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 4- ASPHALT PLANT FIREMAN; BACKHOE OPERATOR; BORING MACHINE OPERATOR; BOXMAN OR MIXERMAN; CHIP SPREADI
|
$65.96 |
$33.20 |
$99.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 6- ARTICULATING MATERIAL HAULER; ASPHALT PLANT ENGINEER; BATCH PLANT OPERATOR; BIT SHARPENER; CONCRET
|
$66.18 |
$33.20 |
$99.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 1- Engineer oiler; Fork lift operator PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON A
|
$64.75 |
$33.20 |
$97.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 10- Crane operator; Derrick barge operator; Hoist operator, stiff legs, Guy derrick o
|
$67.75 |
$33.20 |
$100.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 11- Crane operator; Derrick barge operator; Hoist operator, stiff legs, Guy derrick o
|
$68.75 |
$33.20 |
$101.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 12- Crane operator; Derrick barge operator; Hoist operator, stiff legs, Guy derrick o
|
$69.75 |
$33.20 |
$102.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 13 Crane operator; Derrick barge operator; Helicopter pilot; Hoist operator, stiff le
|
$70.75 |
$33.20 |
$103.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 2- Truck crane oiler PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMEN
|
$65.53 |
$33.20 |
$98.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 3- A-frame or winch truck operator; Ross carrier operator PREMIUM PAY: $10.00 PER HOU
|
$65.82 |
$33.20 |
$99.02 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 4- Bridge-type unloader and turntable operator; Helicopter hoist operator PREMIUM PAY
|
$65.96 |
$33.20 |
$99.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 5 HYDRAULIC BOOM TRUCK; STINGER CRANE; TUGGER HOIST OPERATOR PREMIUM PAY: $10.00 PER
|
$66.18 |
$33.20 |
$99.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 6 Bridge crane operator; Cretor crane operator; Hoist operator; Lift mobile operator
|
$66.29 |
$33.20 |
$99.49 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 7 PEDESTAL CRANE OPERATOR; SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR; TOWER CRANE
|
$66.41 |
$33.20 |
$99.61 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 8 Crane operator; Crawler transporter operator; Derrick barge operator; Hoist operato
|
$66.58 |
$33.20 |
$99.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 9 Crane operator; Derrick barge operator; Highline cableway operator; Hoist operator
|
$66.75 |
$33.20 |
$99.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 1- Skiploader PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the fol
|
$65.25 |
$33.20 |
$98.45 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 2- Power-driven jumbo form setter operator PREMIUM PAY: $10.00 per hour shall be paid on all Power Equip
|
$66.03 |
$33.20 |
$99.23 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 3- Dinkey locomotive or motorperson PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Op
|
$66.32 |
$33.20 |
$99.52 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 4- Bit sharpener; Equipment greaser; Slip form pump operator; Tugger hoist operator; Tunnel locomotive o
|
$66.46 |
$33.20 |
$99.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 5- Backhoe operator; Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shiel
|
$66.68 |
$33.20 |
$99.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 6- Heavy Duty Repairman PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work
|
$66.79 |
$33.20 |
$99.99 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 7- Tunnel mole boring machine operator PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment
|
$66.91 |
$33.20 |
$100.11 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OR COMPRESSOR PLANT OPERATOR; PUMP OPERATOR; SIGNALMAN; SWITCHMAN PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON T
|
$63.40 |
$33.20 |
$96.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS, INCLUDING LEAD ABATEMENT: ALL OTHER WORK
|
$36.44 |
$18.58 |
$55.02 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS: INCLUDING LEAD ABATEMENT: JOURNEYMAN PAINTER
|
$36.44 |
$18.58 |
$55.02 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLASTERER VANDENBURG AFB: $3.00 ADDITIONAL PER HOUR
|
$47.37 |
$19.64 |
$67.01 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER
|
$48.84 |
$23.58 |
$72.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER
|
$44.75 |
$26.20 |
$70.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER/PIPEFITTER
|
$44.29 |
$24.16 |
$68.45 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER/PIPEFITTER
|
$61.73 |
$26.81 |
$88.54 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER/PIPEFITTER
|
$59.85 |
$25.83 |
$85.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER/PIPEFITTER VANDENBURG AIR FORCE BASE
|
$66.23 |
$26.81 |
$93.04 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE COR
|
$42.12 |
$35.69 |
$77.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFER FOOTNOTE: PITCH PREMIUM: WORK ON WHICH EMPLOYEES ARE EXPOSED TO PITCH FUMES OR REQUIRED TO HANDLE PITCH, PITCH BASE OR PITCH IMPREGNATED PRODUC
|
$52.63 |
$20.73 |
$73.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPDENDENCE DAY, LABOR DAY, VETERAN
|
$45.48 |
$30.05 |
$75.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SOFT FLOOR LAYER
|
$45.15 |
$19.43 |
$64.58 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SPRINKLER FITTER
|
$49.69 |
$29.72 |
$79.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO FINISHER
|
$42.11 |
$14.67 |
$56.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO WORKER/SETTER
|
$49.62 |
$15.26 |
$64.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE FINISHER
|
$37.96 |
$13.77 |
$51.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE LAYER
|
$48.29 |
$19.18 |
$67.47 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 1 TRUCK DRIVER WORK ON ALL MILITARY BASES: PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE
|
$41.59 |
$35.69 |
$77.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 10 DUMP TRUCK - 50 YDS. OR MORE WATER LEVEL; WATER PULL - SINGLE ENGINE WITH ATTACHMENT WORK ON ALL MILITARY BASES: PREMIUM PAY: $3
|
$43.12 |
$35.69 |
$78.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 11 WATER PULL - TWIN ENGINE; WATER PULL - TWIN ENGINE WITH ATTACHMENTS; WINCH TRUCK DRIVER - $1.25 ADDITIONAL WHEN OPERATING WINCH
|
$43.62 |
$35.69 |
$79.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 12 BOOM TRUCK 17K AND ABOVE WORK ON ALL MILITARY BASES: PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS
|
$44.05 |
$35.69 |
$79.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 2 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 2 AXLES; TRAFFIC CONTROL PILOT CAR EXCLUDING MOVING HEAVY EQUIPMENT PERMIT LOAD; T
|
$41.74 |
$35.69 |
$77.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 3 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 3 AXLES; BOOT PERSON; CEMENT MASON DISTRIBUTION TRUCK; FUEL TRUCK DRIVER; WATER TR
|
$41.87 |
$35.69 |
$77.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 5 WATER TRUCK, 3 OR MORE AXLES; TRUCK GREASER AND TIRE PERSON; PIPELINE AND UTILITY WORKING TRUCK DRIVER, INCLUDING WINCH TRUCK AND
|
$42.09 |
$35.69 |
$77.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 7
|
$42.37 |
$35.69 |
$78.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 8 DUMP TRUCK, 25 YDS. TO 49 YDS. WATER LEVEL; TRUCK REPAIR PERSON; WATER PULL - SINGLE ENGINE; WELDER WORK ON ALL MILITARY BASES: P
|
$42.62 |
$35.69 |
$78.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 9 TRUCK REPAIR PERSON/WELDER; LOW BED DRIVER, 9 AXLES OR OVER WORK ON ALL MILITARY BASES: PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [
|
$42.82 |
$35.69 |
$78.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TYPES; CABLE BUNDLING MACHINE OPERATOR; CABLE TRENCHING MACHINE OPERATOR CAST-IN-PLACE PIPE LAYING MACHINE OPERATOR; COMBINATION MIXER AND COMPRESSOR
|
$66.29 |
$33.20 |
$99.49 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
WATER LEVEL WORK ON ALL MILITARY BASES: PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTR
|
$42.06 |
$35.69 |
$77.75 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |