Wage Determination MI20260090-17091-bld

Livingston, MI · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination MI20260090-17091-bld covers 61 trade classifications for building construction in Livingston, MI. Total packages (base + fringe) range from $14.75/hr to $103.89/hr, with the highest going to CREDIT. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: MI20260090-17091-bld
Revision: 1
Type: building
County: Livingston
State: MI
Effective: May 17, 2026
Trades covered: 61
Highest rate: $103.89/hr
Official source: SAM.gov reference MI20260090View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $41.28 $25.25 $66.53 $0.00 $0.00 $0.00 $0.00
400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CH $47.28 $25.25 $72.53 $0.00 $0.00 $0.00 $0.00
ASBESTOS WORKER/HEAT & FROST INSULATOR $40.00 $23.65 $63.65 $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.50 $36.74 $80.24 $0.00 $0.00 $0.00 $0.00
BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHIN $40.71 $28.21 $68.92 $0.00 $0.00 $0.00 $0.00
BRICKLAYER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLIDA $36.10 $26.22 $62.32 $0.00 $0.00 $0.00 $0.00
CARPENTER: FLOOR LAYER - CARPET, RESILIENT & VINYL FLOORING $36.21 $21.06 $57.27 $0.00 $0.00 $0.00 $0.00
CARPENTER: FLOOR LAYER - CARPET, RESILIENT, & VINYL FLOORING $36.76 $21.11 $57.87 $0.00 $0.00 $0.00 $0.00
CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING $42.44 $31.43 $73.87 $0.00 $0.00 $0.00 $0.00
CARPENTER: INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING $36.21 $21.06 $57.27 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $25.58 $12.88 $38.46 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $24.64 $12.88 $37.52 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $32.23 $22.11 $54.34 $0.00 $0.00 $0.00 $0.00
CREDIT $65.45 $38.44 $103.89 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING FOR AND INSTALLATION OF ALARMS $28.14 $8.89 $37.03 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING $38.79 $19.87 $58.66 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ALARM INSTALLATION & LOW VOLTAGE WIRING $31.20 $10.97 $42.17 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: LOW VOLTAGE WIRING & ALARM INSTALLATION $36.89 $14.16 $51.05 $0.00 $0.00 $0.00 $0.00
GLAZIER PAID HOLIDAYS: NEW YEAR'S DAY, DECORATION DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED THAT THE EMPLOYEE HAS W $42.00 $25.55 $67.55 $0.00 $0.00 $0.00 $0.00
INSTALLER - OVERHEAD DOOR $27.98 $0.00 $27.98 $0.00 $0.00 $0.00 $0.00
IRONWORKER STRUCTURAL $30.02 $27.43 $57.45 $0.00 $0.00 $0.00 $0.00
IRONWORKER, ORNAMENTAL $18.48 $7.93 $26.41 $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $36.55 $33.37 $69.92 $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL $36.55 $35.93 $72.48 $0.00 $0.00 $0.00 $0.00
LABORER: ASBESTOS ABATEMENT $39.08 $15.92 $55.00 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $17.64 $4.95 $22.59 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL; GRADE CHECKER; SANDBLASTER $38.11 $15.45 $53.56 $0.00 $0.00 $0.00 $0.00
LABORER: GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE; PIPELAYER; SANDBLASTER (EAST OF OAK GROVE RD. & NORTH OF M-59) $38.00 $18.25 $56.25 $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER $29.93 $9.10 $39.03 $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE & IRRIGATION: GROUP 2 LANDSCAPE LABORER: SMALL POWER TOOL OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDE $27.71 $9.10 $36.81 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK; MASON TENDER - CEMENT/CONCRETE $38.33 $15.45 $53.78 $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $38.47 $15.45 $53.92 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $42.92 $39.13 $82.05 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE O $43.93 $25.25 $69.18 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.5 $39.57 $25.25 $64.82 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $39.57 $25.25 $64.82 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE $33.71 $25.25 $58.96 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE $31.23 $25.25 $56.48 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH AND ROLLER $32.85 $20.41 $53.26 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $28.75 $18.68 $47.43 $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $32.85 $20.41 $53.26 $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $28.32 $16.88 $45.20 $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY $26.86 $17.66 $44.52 $0.00 $0.00 $0.00 $0.00
PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION $51.30 $25.87 $77.17 $0.00 $0.00 $0.00 $0.00
PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION $40.30 $38.80 $79.10 $0.00 $0.00 $0.00 $0.00
PIPEFITTER: EXCLUDING HVAC PIPE INSTALLATION; INCLUDING HVAC SYSTEM INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY $46.29 $25.43 $71.72 $0.00 $0.00 $0.00 $0.00
PLASTERER $25.39 $12.53 $37.92 $0.00 $0.00 $0.00 $0.00
PLASTERER $23.73 $12.88 $36.61 $0.00 $0.00 $0.00 $0.00
PLASTERER $30.63 $14.07 $44.70 $0.00 $0.00 $0.00 $0.00
PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION $43.34 $32.92 $76.26 $0.00 $0.00 $0.00 $0.00
PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION $51.30 $25.87 $77.17 $0.00 $0.00 $0.00 $0.00
PLUMBER: INCLUDING HVAC PIPE INSTALLATION; EXCLUDING HVAC SYSTEM INSTALLATION FOOTNOTE: PAID HOLIDAYS: MEMORIAL DAY, INDEPENDENCE DAY AND LABOR DAY, I $46.29 $25.43 $71.72 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER $42.74 $21.53 $64.27 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 $42.74 $21.53 $64.27 $0.00 $0.00 $0.00 $0.00
ROOFER $42.67 $21.62 $64.29 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $41.34 $27.39 $68.73 $0.00 $0.00 $0.00 $0.00
TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WIT $33.50 $23.52 $57.02 $0.00 $0.00 $0.00 $0.00
TILE FINISHER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOL $33.50 $23.52 $57.02 $0.00 $0.00 $0.00 $0.00
TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN DAYS BEFORE SAID HOLIDAY WITHI $40.53 $23.62 $64.15 $0.00 $0.00 $0.00 $0.00
TILE SETTER FOOTNOTE: PAID HOLIDAY: FOURTH OF JULY, IF THE WORKER WAS EMPLOYED BY THE CONTRACTOR IN ANY PERIOD OF SEVEN WORKING DAYS BEFORE SAID HOLID $40.53 $23.62 $64.15 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: TRACTOR HAUL TRUCK $13.57 $1.18 $14.75 $0.00 $0.00 $0.00 $0.00
View all WDs for Livingston → Revision history →