Wage Determination IL20260016-16774-hwy

Lawrence, IL · highway · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination IL20260016-16774-hwy covers 96 trade classifications for highway construction in Lawrence, IL. Total packages (base + fringe) range from $40.65/hr to $93.84/hr, with the highest going to LINE CONSTRUCTION: LINEMAN (RANDOLPH COUNTY). Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: IL20260016-16774-hwy
Revision: 1
Type: highway
County: Lawrence
State: IL
Effective: May 17, 2026
Trades covered: 96
Highest rate: $93.84/hr
Official source: SAM.gov reference IL20260016View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BLACK TOP PLANT OILER INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING AND RIVER WORK $43.45 $34.95 $78.40 $0.00 $0.00 $0.00 $0.00
CARPENTER $33.54 $27.97 $61.51 $0.00 $0.00 $0.00 $0.00
CARPENTER $39.02 $18.90 $57.92 $0.00 $0.00 $0.00 $0.00
CARPENTER $41.36 $18.90 $60.26 $0.00 $0.00 $0.00 $0.00
CARPENTER DIVERS $39.02 $18.90 $57.92 $0.00 $0.00 $0.00 $0.00
CARPENTER DIVERS $38.52 $18.90 $57.42 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $29.11 $16.09 $45.20 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $29.22 $16.31 $45.53 $0.00 $0.00 $0.00 $0.00
DRIVER OPERATOR, PULLS & SCRAPERS, POWER PAC & CONTROLS, PUG MILL, PULVERIZER OR TILLERS, PUSH CATS, QUAD TRAC, ROTOMILLS, ROTATING CAB FORKLIFTS, RUB $40.13 $32.00 $72.13 $0.00 $0.00 $0.00 $0.00
ELECTRICAL LOW VOLTAGE WIRING INSTALLER, BUILDING (ALEXANDER, BOND, CLAY, CLINTON, EDWARDS, EFFINGHAM, FAYETTE, FRANKLIN, GALLATIN, HAMILTON, HARDIN $38.44 $19.37 $57.81 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $46.14 $21.67 $67.81 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $45.00 $26.70 $71.70 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (ALEXANDER, CLAY, EDWARDS, EFFINGHAM, FAYETTE, FRANKLIN, GALLATIN, HAMILTON, HARDIN, JACKSON, JEFFERSON, JOHNSON, MARION, MASSAC, PERRY, P $52.14 $29.14 $81.28 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (EFFINGHAM, AND FAYETTE COUNTIES) $41.00 $20.68 $61.68 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (RANDOLPH COUNTY) $52.41 $30.27 $82.68 $0.00 $0.00 $0.00 $0.00
IRONWORKER (ALEXANDER, FRANKLIN, GALLATIN, HARDIN, JACKSON, JOHNSON, MASSAC, PERRY, POPE, PULASKI, SALINE, UNION, AND WILLIAMSON COUNTIES) $37.66 $32.10 $69.76 $0.00 $0.00 $0.00 $0.00
IRONWORKER (CLAY, CRAWFORD, EFFINGHAM COUNTY, JASPER, LAWRENCE, AND RICHLAND COUNTIES) $38.00 $26.39 $64.39 $0.00 $0.00 $0.00 $0.00
IRONWORKER (CLAY, EDWARDS, FRANKLIN, GALLATIN, HAMILTON, JEFFERSON, LAWRENCE, MARION, RICHLAND, SALINE, WABASH, WAYNE, AND WHITE COUNTIES) $35.34 $26.40 $61.74 $0.00 $0.00 $0.00 $0.00
IRONWORKER (EFFINGHAM AND FAYETTE COUNTIES) $37.60 $32.94 $70.54 $0.00 $0.00 $0.00 $0.00
IRONWORKER (FAYETTE, JACKSON, JEFFERSON, MARION, PERRY, AND RANDOLPH COUNTIES) $41.65 $31.18 $72.83 $0.00 $0.00 $0.00 $0.00
LABORER $32.75 $27.64 $60.39 $0.00 $0.00 $0.00 $0.00
LABORERS, GROUP 2 ASBESTOS ABATEMENT WORKER AND HAZARDOUS WASTE WORKER; LEAD BASE PAINT WORKER $34.64 $30.59 $65.23 $0.00 $0.00 $0.00 $0.00
LABORERS, GROUP 3 DYNAMITE MAN $35.64 $30.59 $66.23 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: CABLE SPLICER; LINEMAN WELDER (RANDOLPH COUNTY) $63.79 $26.89 $90.68 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN (RANDOLPH COUNTY) $42.10 $18.84 $60.94 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN - CLASS A (ALEXANDER, CLAY, CRAWFORD, EDWARDS, EFFINGHAM, FRANKLIN, FAYETTE, GALLATIN, HAMILTON, HARDIN, JACKSON, JASPER $38.18 $19.92 $58.10 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN - EQUIPMENT OPERATOR CLASS II (ALEXANDER, CLAY, CRAWFORD, EDWARDS, EFFINGHAM, FRANKLIN, FAYETTE, GALLATIN, HAMILTON, HARD $46.49 $22.33 $68.82 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN EQUIPMENT OPERATOR (RANDOLPH COUNTY) $56.38 $25.23 $81.61 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (RANDOLPH COUNTY) $46.03 $20.60 $66.63 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN/EQUIPMENT OPERATOR (FAYETTE COUNTY) $52.63 $24.35 $76.98 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN/TRUCK DRIVER (FAYETTE COUNTY) $39.92 $20.22 $60.14 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: HEAVY - EQUIPMENT OPERATOR CLASS I (ALEXANDER, CLAY, CRAWFORD, EDWARDS, EFFINGHAM, FRANKLIN, FAYETTE, GALLATIN, HAMILTON, HARDIN, J $52.13 $23.97 $76.10 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN (ALEXANDER, CLAY, CRAWFORD, EDWARDS, EFFINGHAM, FRANKLIN, FAYETTE, GALLATIN, HAMILTON, HARDIN, JACKSON, JASPER, JEFFERSON $65.52 $27.85 $93.37 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN (RANDOLPH COUNTY) $64.83 $29.01 $93.84 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN AND SUBSTATION TECHNICIAN (FAYETTE COUNTY) $58.58 $26.29 $84.87 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, CLASS B: OILERS CLASSIFIED AS ASSISTANT OPERATORS, AIR TRACK DRILL/COMPRESSOR, ALL MACHINES USED TO SWEEP, CLEAN, BROOM OR $38.23 $32.00 $70.23 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: RIVER Class 1: All Off Road Material Hauling Equipment, All Terrain Crane, All Power Boat Operators, Articulated Dump, Asph $40.23 $32.00 $72.23 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT: RIVER Class 2: Assistant Operators required on All terrain cherry picker w/over 40 ton lifting capacity, Crane, Deckhand on $36.78 $32.00 $68.78 $0.00 $0.00 $0.00 $0.00
PAINTER: BLASTING, SPRAYING & PRESSURE WASHING EPOXY OR TOXIC-LEAD-BASED PAINT WORK-$1.00 PREMIMUM BRUSH & ROLLER WORK OVER 30FT ABOVE GROUND OR FLOOR $28.30 $20.07 $48.37 $0.00 $0.00 $0.00 $0.00
PAINTER: BRIDGE EPOXY OR TOXIC-LEAD-BASED PAINT WORK-$1.00 PREMIMUM $32.45 $17.12 $49.57 $0.00 $0.00 $0.00 $0.00
PAINTER: BRIDGES & DAMS - BLAST & SPRAY SPRAY, SANDBLASTING AND WATER BLAST UNITS WITH 3500 PSI RECEIVE A $.50 PER HOUR PREMIMUM. ALL WORK FORTY FEET $31.00 $15.40 $46.40 $0.00 $0.00 $0.00 $0.00
PAINTER: BRIDGES & DAMS - BRUSH & ROLL SPRAY, SANDBLASTING AND WATER BLAST UNITS WITH 3500 PSI RECEIVE A $.50 PER HOUR PREMIMUM. ALL WORK FORTY FEET A $30.00 $15.40 $45.40 $0.00 $0.00 $0.00 $0.00
PAINTER: BRIDGES, DAMS $35.51 $18.78 $54.29 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH & ROLLER AND WALL COVERING DRYWALL PREPARING EPOXY OR TOXIC-LEAD-BASED PAINT WORK-$1.00 PREMIMUM BRUSH & ROLLER WORK OVER 30FT ABOVE GR $27.30 $20.07 $47.37 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND PAPERHANGER FOOTNOTE A: ALL STRUCTURES OVER 40FT? $0.75/ HOUR ABOVE BASE WAGE ALL STRUCTURES OVER 75FT? $1.50 HOUR ABOVE BA $27.60 $17.63 $45.23 $0.00 $0.00 $0.00 $0.00
PAINTER: INDUSTRIAL - BLAST & SPRAY SPRAY, SANDBLASTING AND WATER BLAST UNITS WITH 3500 PSI RECEIVE A $.50 PER HOUR PREMIMUM. ALL WORK FORTY FEET AND $26.25 $15.40 $41.65 $0.00 $0.00 $0.00 $0.00
PAINTER: INDUSTRIAL - BRUSH & ROLL SPRAY, SANDBLASTING AND WATER BLAST UNITS WITH 3500 PSI RECEIVE A $.50 PER HOUR PREMIMUM. ALL WORK FORTY FEET AND A $25.25 $15.40 $40.65 $0.00 $0.00 $0.00 $0.00
PAINTER: JOURNEYMAN $33.21 $18.78 $51.99 $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN $33.54 $27.97 $61.51 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 03 AIR COMPRESSORS, WATER PUMPS, REGARDLESS OF SIZE, WATER-BLASTERS, WELDING MACHINE, MIXERS, CONVEYOR, SIPHON OR JET $41.59 $39.10 $80.69 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 11 MASTER MECHANIC $49.20 $39.10 $88.30 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 11 MASTER MECHANIC INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING AND R $44.45 $34.95 $79.40 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 12 LICENSED BOAT PILOT $50.20 $39.10 $89.30 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 12 LICENSED BOAT PILOT INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING A $45.45 $34.95 $80.40 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 01 CRANES, DRAGLINES, SHOVELS, SKIMMER SCOOPS, CLAMSHELLS OR DERRICK BOATS, PILE DRIVERS, CRANE-TYPE BACKHOES, ASPHALT $47.20 $39.10 $86.30 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 02 ASSISTANT OPERATORS FAYETTE, JEFFERSON, MARION, PERRY, AND RANDOLPH COUNTIES $46.07 $39.10 $85.17 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 02 ASSISTANT OPERATORS INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING $41.32 $34.95 $76.27 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 03 AIR COMPRESSOR ONE; WATER PUMP REGARDLESS OF SIZE ONE; WELDING MACHINE ONE; 1-BAG MIXER ONE; CONVEYOR ONE; SIPHON O $36.84 $34.95 $71.79 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 04 FIREMAN ON WHIRLIES AND HEAVY EQUIPMENT OILERS, TRUCK CRANES, DREDGES, MONIGANS, LARGE CRANES - CONCRETE PLANT OILE $41.65 $39.10 $80.75 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 05 OILERS FAYETTE, JEFFERSON, MARION, PERRY, AND RANDOLPH COUNTIES $41.65 $39.10 $80.75 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 05 OILERS INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING AND RIVER WOR $44.45 $34.95 $79.40 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 06 OPERATORS ON EQUIPMENT WITH BOOMS, INCLUDING JIBS, 100 FT AND OVER, BUT LESS THAN 150 FT $49.75 $39.10 $88.85 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 06 OPERATORS ON EQUIPMENT WITH BOOMS, INCLUDING JIBS, 100 FT AND OVER, BUT LESS THAN 150 FT INCLUDING BUILDING CONSTRU $45.00 $34.95 $79.95 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 07 OPERATORS ON EQUIPMENT WITH BOOMS, INCLUDING JIBS, 150 FT AND OVER, BUT LESS THAN 200 FT INCLUDING BUILDING CONSTRU $45.30 $34.95 $80.25 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 08 OPERATORS ON EQUIPMENT WITH BOOMNS, INCLUDING JIBS, 200 FT AND OVER; TOWER CRANES, AND WHIRLEY CRANES INCLUDING BUI $45.60 $34.95 $80.55 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 09 CERTIFIED CRANE OPERATORS, BELOW 17.5 TONS, WHEN REQUESTED BY THE CONTRACTOR OR REQUIRED BY THE OWNER $48.20 $39.10 $87.30 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 09 CERTIFIED CRANE OPERATORS, BELOW 17.5 TONS, WHEN REQUESTED BY THE CONTRACTOR OR REQUIRED BY THE OWNER. INCLUDING BU $46.25 $34.95 $81.20 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 1 POWER CRANES, DRAGLINES, DERRICKS, SHOVELS, GRADALLS, MECHANICS, TRACTOR HIGHLIFT, TOURNADOZER, CONCRETE MIXERS WITH $45.15 $26.00 $71.15 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 10: Certified crane Operators 17.5 tons and above, when requested by the Contractor or required by the Owner $46.75 $34.95 $81.70 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 7: Operators on equipment with Booms, including Jibs, 150 ft and over, but less than 200 ft $45.30 $34.95 $80.25 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 8: Operators on equipment with Boomns, including Jibs, 200 ft and over; Tower Cranes, and Whirley Cranes $45.60 $34.95 $80.55 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORGROUP 1: Cranes, Draglines, Shovels, Skimmer Scoops, Clamshells or Derrick Boats, Pile Drivers, Crane-Type Backhoes, Asphalt P $42.45 $34.95 $77.40 $0.00 $0.00 $0.00 $0.00
STRUCTURES OVER 100FT? $2.50/ HOUR ABOVE BASE WAGE..$ 29.60 17.63 PAINTER: DRYWALL FINISHERS AND PLASTERERS FOOTNOTE A: ALL STRUCTURES OVER 40FT? $0.7 $27.85 $17.63 $45.48 $0.00 $0.00 $0.00 $0.00
STRUCTURES OVER 75FT? $1.50 HOUR ABOVE BASE WAGE ALL STRUCTURES OVER 100FT? $2.50/ HOUR ABOVE BASE WAGE $28.60 $17.63 $46.23 $0.00 $0.00 $0.00 $0.00
THE CONTRACTOR OR REQUIRED BY THE OWNER INCLUDING BUILDING CONSTRUCTION ON HEAVY INDUSTRIAL SITES & HEAVY CONSTRUCTION EXCEPT DREDGING AND RIVER WORK $46.75 $34.95 $81.70 $0.00 $0.00 $0.00 $0.00
TRACT JACK, POWER BROOM, SELF-PROPELLED FROM TAMPER, TRAC-AIR, MIXERS - LESS THAN 21 CU.FT., MORTAR MIXER W/SKI OR PUMP, MUD JACKS, ONE WELL POINT PUM $30.83 $32.00 $62.83 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 1: DRIVERS ON 2 AXLE TRUCKSHAULING LESS THAN 9 TON; AIR COMPRESSOR AND WELDING MACHINES AND BROOMS, INCLUDING THOSE PULLED BY SEPA $38.55 $16.11 $54.66 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 1: DRIVERS ON 2 AXLES HAULING LESS THAN 9 TONS; AIR COMPRESSOR & WELDING MACHINES AND BROOMS, INCLUDING THOSE PULLED BY SEPARATE U $45.35 $25.72 $71.07 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 1: DRIVERS ON 2 AXLES HAULING LESS THAN 9 TONS; AIR COMPRESSOR & WELDING MACHINES AND BROOMS, INCLUDING THOSE PULLED BY SEPARATE U $43.28 $27.56 $70.84 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 2: 2 OR 3 AXLE TRUCKS HAULING MORE THAN 9 TON BUT HAULING LESS THAN 16 TON; A-FRAME WINCH TRUCKS; HYDROLIFT TRUCKS; VACTOR TRUCKS $38.97 $16.11 $55.08 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A-frame winch trucks; hydrolift trucks; Vactor Trucks or s $45.88 $25.42 $71.30 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A-frame winch trucks; hydrolift trucks; Vactor Trucks or s $45.93 $25.72 $71.65 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 2: 2 or 3 axles hualing more than 9 tons but hauling less than 16 tons; A-frame winch trucks; hydrolift trucks; Vactor Trucks or s $43.86 $27.56 $71.42 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5-Axles or more combination units; drivers on water pulls; articulated dump trucks; me $46.15 $25.42 $71.57 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5-Axles or more combination units; drivers on water pulls; articulated dump trucks; me $46.25 $25.72 $71.97 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 3: 2, 3 or 4 Axles hauling 16 tons or more; 5-Axles or more combination units; drivers on water pulls; articulated dump trucks; me $44.15 $27.56 $71.71 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 3: 2, 3, or 4 axle trucks hauling 16 ton or more; Drivers on water pulls; Articulated Dump Trucks; Mechanics and working foreperso $39.18 $16.11 $55.29 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 4: LOW BOY AND OIL DISTRIBUTORS $46.54 $25.42 $71.96 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 4: LOW BOY AND OIL DISTRIBUTORS $46.60 $25.72 $72.32 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 4: LOW BOY AND OIL DISTRIBUTORS $44.53 $27.56 $72.09 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 4: LOW BOY; OIL DISTRIBUTORS FOOTNOTE: A. $46.20 PER DAY $39.44 $16.11 $55.55 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK $47.64 $25.42 $73.06 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK $47.71 $25.72 $73.43 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK $45.61 $27.56 $73.17 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, GROUP 5: DRIVERS WHO REQUIRE SPECIAL PROTECTIVE CLOTHING WHILE EMPLOYED ON HAZARDOUS WASTE WORK. FOOTNOTE: A. $46.20 PER DAY $39.44 $16.11 $55.55 $0.00 $0.00 $0.00 $0.00
UNDER, ROLLERS ON AGGREGATE AND SEAL COAT SURFACES, FORK LIFTS (WHEN USED FOR LANDSCAPING WORK, CONCRETE AND BLACKTOP CURB MACHINE, FARM TRACTOR WITH $30.05 $26.00 $56.05 $0.00 $0.00 $0.00 $0.00
View all WDs for Lawrence → Revision history →