$3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, GEORGE AFB, MARINE CORP
|
$42.12 |
$35.69 |
$77.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS REMOVAL LABORER SCOPE OF WORK: INCLUDES SITE MOBILIZATION, INITIAL SITE CLEANUP, SITE PREPARATION, REMOVAL OF ASBESTOS CONTAINING MATERIAL AN
|
$46.48 |
$25.93 |
$72.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER
|
$23.52 |
$13.37 |
$36.89 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ASBESTOS WORKERS/INSULATOR
|
$56.32 |
$26.52 |
$82.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICK TENDER
|
$42.60 |
$22.13 |
$64.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER; MARBLE SETTER
|
$58.81 |
$19.14 |
$77.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER; MARBLE SETTER *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, N
|
$50.07 |
$20.29 |
$70.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CABLE SPLICER ALL WORK WITHIN 32 ROAD MILES OR LESS FROM THE NEAREST BASE POINT ALL WORK MORE THAN 32 ROAD MILES FROM NEAREST BASE POINT: ADD $5.00 TO
|
$58.40 |
$31.72 |
$90.12 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: CABINET INSTALLER
|
$40.46 |
$16.28 |
$56.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: FENCE BUILDER
|
$39.91 |
$15.37 |
$55.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: FRAMER & FINISH CARPENTER
|
$40.75 |
$16.28 |
$57.03 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: INSULATION INSTALLER
|
$25.66 |
$15.96 |
$41.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: ROOF LOADER OF SHINGLES
|
$30.08 |
$16.28 |
$46.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: SHINGLER
|
$39.90 |
$16.28 |
$56.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER: SUBTERRANEAN GARAGE CONCRETE CONSTRUCTION AND CARPENTERS PERFORMING ON GRADE SLAB CONCRETE CONSTRUCTION
|
$39.38 |
$16.28 |
$55.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASON/CONCRETE FINISHER
|
$47.70 |
$27.07 |
$74.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNCIATION SYSTEM: TECHNICIAN COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$33.09 |
$15.89 |
$48.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$46.47 |
$18.47 |
$64.94 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$48.13 |
$17.49 |
$65.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$45.23 |
$20.47 |
$65.70 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS AND SYSTEMS WORK SCOPE OF WORK: INSTALLATION, TESTING, SERVICE AND MAINTENANCE OF SYSTEMS UTILIZING TH
|
$46.47 |
$19.22 |
$65.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: INSTALLER SCOPE OF WORK: Installation, testing, service and maintenance of systems utilizing the transmission and/or transferen
|
$49.73 |
$17.54 |
$67.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM: TECHNICIAN SCOPE OF WORK: Installation, testing, service and maintenance of systems utilizing the transmission and/or transfere
|
$30.89 |
$11.66 |
$42.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRAGLINE, CLAMSHELL OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LA
|
$48.48 |
$25.25 |
$73.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL FINISHER/TAPER IMPERIAL
|
$32.27 |
$14.70 |
$46.97 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL: DRYWALL INSTALLER/LATHER: ALL OTHER WORK
|
$51.60 |
$16.28 |
$67.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL: DRYWALL INSTALLER/LATHER: WORK ON WOOD-FRAMED SINGLE FAMILY HOMES, AND WOOD-FRAMED APARTMENT BUILDINGS UP TO AND INCLUDING 4 STORIES
|
$32.14 |
$16.28 |
$48.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL: STOCKER/SCRAPPER: ALL OTHER WORK
|
$22.16 |
$8.62 |
$30.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DRYWALL: STOCKER/SCRAPPER: WORK ON WOOD-FRAMED SINGLE FAMILY HOMES, AND WOOD-FRAMED APARTMENT BUILDINGS UP TO AND INCLUDING 4 STORIES
|
$22.16 |
$8.62 |
$30.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$57.26 |
$32.83 |
$90.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$36.66 |
$11.26 |
$47.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$37.63 |
$9.57 |
$47.20 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$55.50 |
$24.42 |
$79.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN ALL WORK WITHIN 32 ROAD MILES OR LESS FROM THE NEAREST BASE POINT ALL WORK MORE THAN 32 ROAD MILES FROM NEAREST BASE POINT: ADD $5.00 TO T
|
$53.09 |
$31.56 |
$84.65 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN: 1 TO 3 STORIES
|
$40.50 |
$8.18 |
$48.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN: DOES NOT INCLUDE FIRE ALARM, HOLD-UP ALARM, BURGLAR ALARM AND SURVEILLANCE SYSTEMS LOS ANGELES
|
$37.63 |
$8.41 |
$46.04 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIANS WORK AT VANDENBERG AFB: $3.75 ADDITIONAL PER HOUR
|
$41.00 |
$4.73 |
$45.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE F
|
$48.81 |
$25.25 |
$74.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
FIRE STOP TECHNICIAN
|
$39.94 |
$20.65 |
$60.59 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
GLAZIER
|
$52.90 |
$22.16 |
$75.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
GLAZIER
|
$49.22 |
$30.47 |
$79.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
GLAZIER FOOTNOTE: ADDITIONAL $1.25 PER HOUR FOR WORK IN A CONDO, FROM THE THIRD FLOOR AND UP. ADDITIONAL $1.25 PER HOUR FOR WORK ON THE OUTSIDE OF THE
|
$53.05 |
$30.64 |
$83.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY
|
$84.05 |
$38.44 |
$122.49 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER PREMIUM PAY: $9.00 additional per hour at the following locations: China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland
|
$50.70 |
$35.15 |
$85.85 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER PREMIUM PAY: $9.00 additional per hour at the following locations: China Lake Naval Test Station, Chocolate Mountains Naval Reserve-Niland
|
$45.78 |
$26.51 |
$72.29 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 1 CLEANING AND HANDLING OF PANEL FORMS; CONCRETE SCREEDING FOR ROUGH STRIKE-OFF; CONCRETE, WATER CURING; DEMOLITION LABORER, THE CLEANIN
|
$35.24 |
$20.09 |
$55.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 1 CLEANING AND HANDLING OF PANEL FORMS; CONCRETE SCREEDING FOR ROUGH STRIKE-OFF; CONCRETE, WATER CURING; DEMOLITION LABORER, THE CLEANIN
|
$39.23 |
$23.30 |
$62.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 2 ASBESTOS ABATEMENT; ASPHALT SHOVELER; CEMENT DUMPER; CESSPOOL DIGGER AND INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE
|
$35.79 |
$20.09 |
$55.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 2 ASBESTOS ABATEMENT; ASPHALT SHOVELER; CEMENT DUMPER; CESSPOOL DIGGER AND INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE
|
$39.78 |
$23.30 |
$63.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 2 ASBESTOS ABATEMENT; ASPHALT SHOVELER; CEMENT DUMPER; CESSPOOL DIGGER AND INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE
|
$35.24 |
$20.09 |
$55.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 3 BUGGYMOBILE PERSON; CONCRETE CUTTING TORCH; CONCRETE PILE CUTTER; DRILLER, JACKHAMMER, 2-1/2 FT. DRILL STEEL OR LONGER; DRI-PAK-IT MAC
|
$36.34 |
$20.09 |
$56.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 3 BUGGYMOBILE PERSON; CONCRETE CUTTING TORCH; CONCRETE PILE CUTTER; DRILLER, JACKHAMMER, 2-1/2 FT. DRILL STEEL OR LONGER; DRI-PAK-IT MAC
|
$40.33 |
$23.30 |
$63.63 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 4 ANY WORKER EXPOSED TO RAW SEWAGE; ASPHALT RAKER, LUTE PERSON, IRONER, ASPHALT DUMP PERSON AND ASPHALT SPREADER BOXES; CONCRETE CORE CU
|
$37.89 |
$20.09 |
$57.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 4 ANY WORKER EXPOSED TO RAW SEWAGE; ASPHALT RAKER, LUTE PERSON, IRONER, ASPHALT DUMP PERSON AND ASPHALT SPREADER BOXES; CONCRETE CORE CU
|
$41.88 |
$23.30 |
$65.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 5 BLASTER POWDER, ALL WORK OF LOADING HOLES, PLACING AND BLASTING OF ALL POWDER AND EXPLOSIVES OF WHATEVER TYPE, REGARDLESS OF METHOD US
|
$38.24 |
$20.09 |
$58.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 5 BLASTER POWDER, ALL WORK OF LOADING HOLES, PLACING AND BLASTING OF ALL POWDER AND EXPLOSIVES OF WHATEVER TYPE, REGARDLESS OF METHOD US
|
$42.23 |
$23.30 |
$65.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: ALL OTHER WORK RESIDENTIAL, 3 STORIES AND UNDER
|
$46.00 |
$22.70 |
$68.70 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: CLEANUP, FENCING, LANDSCAPING RESIDENTIAL, 3 STORIES AND UNDER
|
$45.00 |
$22.70 |
$67.70 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: DRILLING CREW LABORER
|
$47.94 |
$20.86 |
$68.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: ELECTRONIC TRACKING LOCATOR
|
$51.96 |
$20.86 |
$72.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: HORIZONTAL DIRECTIONAL DRILL OPERATOR
|
$49.96 |
$20.86 |
$70.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: VEHICLE OPERATOR/HAULER
|
$48.11 |
$20.86 |
$68.97 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: PLASTER CLEAN-UP LABORER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORO
|
$36.92 |
$23.32 |
$60.24 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: PLASTER TENDER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL. WORK AT MILITARY BASES - $3.00 ADDITIONAL PER HOUR: CORONADO NAVAL
|
$39.47 |
$23.32 |
$62.79 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 1 PROTECTIVE COATING, PAVEMENT SEALING, INCLUDING REPAIR AND FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE IN
|
$49.30 |
$23.97 |
$73.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 2 TRAFFIC SURFACE ABRASIVE BLASTER; POT TENDER - REMOVAL OF ALL TRAFFIC LINES AND MARKINGS BY ANY METHOD AND PR
|
$50.60 |
$23.97 |
$74.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 3 TRAFFIC DELINEATING DEVICE APPLICATOR: LAYOUT AND APPLICATION OF PAVEMENT MARKERS, DELINEATING SIGNS, RUMBLE
|
$52.61 |
$23.97 |
$76.58 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS:, STRIPING/SLURRY SEAL: GROUP 4 STRIPER: LAYOUT AND APPLICATION OF TRAFFIC STRIPES AND MARKINGS; HOT THERMO PLASTIC; TAPE TRAFFIC STRIPES AND
|
$54.35 |
$23.97 |
$78.32 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MARBLE FINISHER
|
$43.38 |
$15.36 |
$58.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MODULAR FURNITURE INSTALLER
|
$25.00 |
$13.06 |
$38.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VA
|
$50.65 |
$25.25 |
$75.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 11: HEAVY DUTY REPAIRMAN - WELDER COMBINATION, WELDER - CERTIFIED. PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL P
|
$49.41 |
$25.25 |
$74.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 14: CANAL LINER OPERATOR; CANAL TRIMMER OPERATOR; REMOTE- CONTROL EARTH-MOVING EQUIPMENT OPERATOR; WHEEL EXCAVATOR OPE
|
$48.61 |
$25.25 |
$73.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 15: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM; RUBBER-TIRED EARTH-MOVING
|
$48.69 |
$25.25 |
$73.94 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 17: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM; TANDEM TRACTOR OPERATOR P
|
$48.98 |
$25.25 |
$74.23 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 18: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON AL
|
$49.08 |
$25.25 |
$74.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 1: BARGEMAN; BRAKEMAN; COMPRESSOR OPERATOR; DITCH WITCH, WITH SEAT OR SIMILAR TYPE EQUIPMENT; ELEVATOR OPERATOR-INSIDE
|
$45.30 |
$25.25 |
$70.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 21: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON AL
|
$49.48 |
$25.25 |
$74.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 22: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM PREMIUM PAY: $1
|
$49.58 |
$25.25 |
$74.83 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 23: RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM; RUBBER-TIRED E
|
$49.69 |
$25.25 |
$74.94 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 25: CONCRETE PUMP OPERATOR-TRUCK MOUNTED; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE T
|
$49.98 |
$25.25 |
$75.23 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 2: ASPHALT-RUBBER PLANT OPERATOR; CONCRETE MIXER OPERATOR-SKIP TYPE; CONVEYOR OPERATOR; FIREMAN; FORKLIFT OPERATOR (IN
|
$46.08 |
$25.25 |
$71.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 3: ASPHALT-RUBBER BLEND OPERATOR; BOBCAT OR SIMILAR TYPE; EQUIPMENT GREASER; FORD FERGUSON; HELICOPTER RADIOMAN; STATI
|
$46.37 |
$25.25 |
$71.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 4: ASPHALT PLANT FIREMAN; BACKHOE OPERATOR; BORING MACHINE OPERATOR; BOXMAN OR MIXERMAN; CHIP SPREADING MACHINE OPERAT
|
$47.86 |
$25.25 |
$73.11 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 5: EQUIPMENT GREASER. PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG
|
$48.96 |
$25.25 |
$74.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 6: ARTICULATING MATERIAL HAULER; ASPHALT PLANT ENGINEER; BATCH PLANT OPERATOR; BIT SHARPENER; CONCRETE JOINT MACHINE O
|
$48.08 |
$25.25 |
$73.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 7: WELDER - GENERAL PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG M
|
$49.18 |
$25.25 |
$74.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 8: ASPHALT OR CONCRETE SPREADING OPERATOR; ASPHALT PAVING MACHINE OPERATOR; ASPHALT-RUBBER DISTRIBUTION OPERATOR; BACK
|
$48.19 |
$25.25 |
$73.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT GROUP 9: HEAVY DUTY REPAIRMAN PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJ
|
$49.29 |
$25.25 |
$74.54 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 12: CRANE OPERATOR; DERRICK BARGE OPERATOR; HOIST OPERATOR, STIFF LEGS, GUY DERRICK O
|
$51.65 |
$25.25 |
$76.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 13: CRANE OPERATOR; DERRICK BARGE OPERATOR; HELICOPTER PILOT; HOIST OPERATOR, STIFF L
|
$52.65 |
$25.25 |
$77.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 1: ENGINEER OILER; FORK LIFT OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON A
|
$46.65 |
$25.25 |
$71.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 2: TRUCK CRANE OILER PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMEN
|
$47.43 |
$25.25 |
$72.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 3: A-FRAME OR WINCH TRUCK OPERATOR; ROSS CARRIER OPERATOR PREMIUM PAY: $10.00 PER HOU
|
$47.72 |
$25.25 |
$72.97 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 4: BRIDGE-TYPE UNLOADER AND TURNTABLE OPERATOR; HELICOPTER HOIST OPERATOR PREMIUM PAY
|
$47.86 |
$25.25 |
$73.11 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 5: HYDRAULIC BOOM TRUCK; STINGER CRANE; TUGGER HOIST OPERATOR PREMIUM PAY: $10.00 PER
|
$48.08 |
$25.25 |
$73.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 6: BRIDGE CRANE OPERATOR; CRETOR CRANE OPERATOR; HOIST OPERATOR; LIFT MOBILE OPERATOR
|
$48.19 |
$25.25 |
$73.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 7: PEDESTAL CRANE OPERATOR; SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR; TOWER CRAN
|
$48.31 |
$25.25 |
$73.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 9: CRANE OPERATOR; DERRICK BARGE OPERATOR; HIGHLINE CABLEWAY OPERATOR; HOIST OPERATOR
|
$48.65 |
$25.25 |
$73.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OPERATOR; TOWER CRANE OPERATOR AND TOWER GANTRY PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILIT
|
$49.65 |
$25.25 |
$74.90 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
OR SIMILAR TYPES - HUGHES SUPER DUTY, AUGER 200 OR SIMILAR TYPES - DRILLING DEPTH OF 175' MAXIMUM); HOE RAM OR SIMILAR WITH COMPRESSOR; MASS EXCAVATOR
|
$49.48 |
$25.25 |
$74.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER, INCLUDING LEAD ABATEMENT: ALL OTHER WORK
|
$32.12 |
$16.09 |
$48.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER, INCLUDING LEAD ABATEMENT: ALL OTHER WORK
|
$30.04 |
$16.03 |
$46.07 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER, INCLUDING LEAD ABATEMENT: JOURNEYMAN & INDUSTRIAL
|
$34.02 |
$16.49 |
$50.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER, INCLUDING LEAD ABATEMENT: REPAINT
|
$28.59 |
$15.97 |
$44.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER, INCLUDING LEAD ABATEMENT: REPAINT
|
$25.40 |
$15.87 |
$41.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. PAID HOLIDAYS: NEW YEARS DAY, MEMORIAL DAY, IND
|
$69.43 |
$38.44 |
$107.87 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POI
|
$49.81 |
$25.25 |
$75.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POI
|
$49.31 |
$25.25 |
$74.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO
|
$49.19 |
$25.25 |
$74.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWJNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO
|
$48.58 |
$25.25 |
$73.83 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLASTERER: 1 - 3 STORIES IMPERIAL, KERN, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA
|
$44.34 |
$19.64 |
$63.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLASTERER: 4-STORIES IMPERIAL, KERN, LOS ANGELES, ORANGE, RIVERSIDE, SAN BERNARDINO, SAN LUIS OBISPO, SANTA BARBARA AND VENTURA
|
$47.37 |
$19.64 |
$67.01 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER
|
$48.84 |
$23.58 |
$72.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER
|
$44.75 |
$26.20 |
$70.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER/PIPEFITTER
|
$48.83 |
$22.73 |
$71.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
REFRIGERATION MECHANIC: REFRIGERATION FITTER
|
$57.65 |
$25.01 |
$82.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
REPAIRMAN; TRACTOR LOADER OPERATOR; WOODS MIXER OPERATOR PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOW
|
$48.31 |
$25.25 |
$73.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFER
|
$42.80 |
$12.64 |
$55.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFER FOOTNOTE: Pitch premium: Work on which employees are exposed to pitch fumes or required to handle pitch, pitch base or pitch impregnated produc
|
$51.58 |
$20.73 |
$72.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL TECHNICIAN SHEET METAL TECHNICIAN - SCOPE: A. EXISTING RESIDENTIAL BUILDINGS, BOTH SINGLE AND MULTI-FAMILY, WHERE EACH UNIT IS HEATED AND/
|
$38.65 |
$10.31 |
$48.96 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER
|
$51.45 |
$30.92 |
$82.37 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, PRESIDENT'S DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPDENDENCE DAY, LABOR DAY, VETERAN
|
$46.87 |
$31.15 |
$78.02 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER: AREA 1: LOS ANGELES COUNTY Work on general sheet metal and heating and air conditioning on single family dwellings, multiple famil
|
$33.10 |
$10.81 |
$43.91 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER: AREA 2: LOS ANGELES, ORANGE, RIVERSIDE & SAN BERNARDINO COUNTIES Work on general sheet metal and heating and air conditioning on s
|
$29.54 |
$19.09 |
$48.63 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SOFT FLOOR LAYER
|
$40.77 |
$19.37 |
$60.14 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SOFT FLOOR LAYER
|
$45.15 |
$19.43 |
$64.58 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SPRINKLER FITTER (LOS ANGELES COUNTY; ORANGE COUNTY; SAN BERNARDINO COUNTY; VENTURA COUNTY (PORT HUENEME, PORT MUGU, THE CITY OF SANTA PAULA, AND THAT
|
$58.60 |
$33.65 |
$92.25 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SPRINKLER FITTER: AREA 1: IMPERIAL COUNTY; LOS ANGELES COUNTY; ORANGE COUNTY; RIVERSIDE COUNTY; AND SAN BERNARDINO COUNTY
|
$50.79 |
$29.80 |
$80.59 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SPRINKLER FITTER: AREA 2: SAN LUIS OBISPO, SANTA BARBARA COUNTIES, VENTURA COUNTIES
|
$49.69 |
$29.72 |
$79.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO FINISHER
|
$42.11 |
$14.67 |
$56.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO WORKER/SETTER
|
$49.62 |
$15.26 |
$64.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE FINISHER
|
$37.96 |
$13.77 |
$51.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE LAYER
|
$51.82 |
$19.32 |
$71.14 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 1 TRUCK DRIVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS A
|
$41.59 |
$35.69 |
$77.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 10 DUMP TRUCK - 50 YDS. OR MORE WATER LEVEL; WATER PULL - SINGLE ENGINE WITH ATTACHMENT WORK ON ALL MILITARY BASES - $3.00 PER HO
|
$43.12 |
$35.69 |
$78.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 11 WATER PULL - TWIN ENGINE; WATER PULL - TWIN ENGINE WITH ATTACHMENTS; WINCH TRUCK DRIVER - $1.25 ADDITIONAL WHEN OPERATING WINC
|
$43.62 |
$35.69 |
$79.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 12 BOOM TRUCK 17K AND ABOVE WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LA
|
$44.05 |
$35.69 |
$79.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 2 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 2 AXLES; TRAFFIC CONTROL PILOT CAR EXCLUDING MOVING HEAVY EQUIPMENT PERMIT LOAD
|
$41.74 |
$35.69 |
$77.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 3 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 3 AXLES; BOOT PERSON; CEMENT MASON DISTRIBUTION TRUCK; FUEL TRUCK DRIVER; WATER
|
$41.87 |
$35.69 |
$77.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 4 DRIVER OF TRANSIT MIX TRUCK, UNDER 3 YDS.; DUMPCRETE TRUCK, LESS THAN 6-1/2 YDS. WATER LEVEL WORK ON ALL MILITARY BASES - $3.00
|
$42.06 |
$35.69 |
$77.75 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 5 WATER TRUCK, 3 OR MORE AXLES; TRUCK GREASER AND TIRE PERSON; PIPELINE AND UTILITY WORKING TRUCK DRIVER, INCLUDING WINCH TRUCK A
|
$42.09 |
$35.69 |
$77.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 7 A Frame, Swedish crane or similar; Forklift driver; Ross carrier driver WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL
|
$42.37 |
$35.69 |
$78.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 8 DUMP TRUCK, 25 YDS. TO 49 YDS. WATER LEVEL; TRUCK REPAIR PERSON; WATER PULL - SINGLE ENGINE; WELDER WORK ON ALL MILITARY BASES
|
$42.62 |
$35.69 |
$78.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 9 TRUCK REPAIR PERSON/WELDER; LOW BED DRIVER, 9 AXLES OR OVER WORK ON ALL MILITARY BASES - $3.00 PER HOUR ADDITIONAL: [29 PALMS M
|
$42.82 |
$35.69 |
$78.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |