CABLE SPLICER
|
$36.73 |
$23.39 |
$60.12 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER (WYOMING COUNTY)
|
$41.19 |
$29.81 |
$71.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTERS
|
$29.00 |
$18.89 |
$47.89 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTERS, INCLUDING DRYWALL HANGING
|
$41.19 |
$29.81 |
$71.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASON/CONCRETE FINISHER: CEMENT MASONS
|
$38.63 |
$25.05 |
$63.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES INCLUDING OUTSIDE PLANT, TEL
|
$44.50 |
$36.05 |
$80.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES INCLUDING OUTSIDE PLANT, TEL
|
$22.90 |
$21.38 |
$44.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
COMMUNICATIONS SYSTEM WORK COVERS LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE, AND REMOVAL OF TELEDATA FACILITIES INCLUDING OUTSIDE PLANT, TEL
|
$14.20 |
$14.02 |
$28.22 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$44.50 |
$36.06 |
$80.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN
|
$44.30 |
$30.20 |
$74.50 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO
|
$40.81 |
$6.99 |
$47.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA
|
$20.53 |
$6.39 |
$26.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE
|
$38.73 |
$6.93 |
$45.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$42.29 |
$30.66 |
$72.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$52.86 |
$35.60 |
$88.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$47.57 |
$31.03 |
$78.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$31.72 |
$29.87 |
$61.59 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER
|
$63.14 |
$33.82 |
$96.96 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid
|
$64.59 |
$42.92 |
$107.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
GLAZIER
|
$34.68 |
$27.64 |
$62.32 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: FENCE ERECTOR
|
$34.06 |
$30.80 |
$64.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: ORNAMENTAL, REINFORCING STONE DERRICKMAN, RIGGER, RODMAN, STRUCTURAL MACHINERY MOVERS FENCE ERECTORS, PRECAST CONCRETE ERECTOR (WYOMING C
|
$35.75 |
$30.80 |
$66.55 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: SHEETER (WYOMING COUNTY)
|
$36.00 |
$30.80 |
$66.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING STEEL, WELDERS, RIGGERS, RODMAN
|
$35.49 |
$32.30 |
$67.79 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: GROUP 1 FLAGGERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY
|
$32.96 |
$25.30 |
$58.26 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: GROUP 2 LABORERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY
|
$33.66 |
$25.30 |
$58.96 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: GROUP 3 RAKERS, DRILLERS, PIPELAYERS, AND TORCH OPERATORS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR
|
$33.86 |
$25.30 |
$59.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: GROUP 4 BLASTERS FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY
|
$34.69 |
$25.30 |
$59.99 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: GROUP 5 HAZARDOUS WASTE REMOVAL FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND
|
$35.44 |
$25.30 |
$60.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MILLWRIGHT (WYOMING COUNTY)
|
$34.60 |
$26.35 |
$60.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER
|
$33.00 |
$28.21 |
$61.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER
|
$34.00 |
$28.51 |
$62.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER: BRUSH & ROLLER
|
$33.00 |
$28.21 |
$61.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PIPEFITTER
|
$42.20 |
$29.80 |
$72.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 1 AIR HOIST, ALL BOOM TYPE EQUIPMENT, ALL PAN AND CARRY-ALLS, ARCHER HOIST, ASPHALT ROLLER ASPHALT SPREADER OR PAVER
|
$47.39 |
$36.89 |
$84.28 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 2 AGGREGATE BIN, CMI AND SIMILAR TYPE CONCRETE SPREADS, CEMENT BIN, CHIPPING MACHINE AND CHIP SPREADER, COMPRESSORS
|
$42.89 |
$36.89 |
$79.78 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 3 CRANES 5 - 60 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S
|
$50.64 |
$36.89 |
$87.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 4 CRANES 61 - 199 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'
|
$51.64 |
$36.89 |
$88.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 200 - 399 TONS NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR
|
$52.14 |
$36.89 |
$89.03 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 400 TONS & OVER NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEA
|
$52.64 |
$36.89 |
$89.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MEACHANIC NOTE: HAZARDOUS WASTE PREMIUM $2.50 TUNNEL WORK $1.00 FOOTNOTES: A. PAID HOLIDAYS: A-NEW YEAR'S DA
|
$48.46 |
$36.89 |
$85.35 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFERS: COMPOSITION
|
$34.96 |
$26.03 |
$60.99 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFERS: SLATE & TILE
|
$35.11 |
$26.03 |
$61.14 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER
|
$39.50 |
$29.18 |
$68.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
STEAMFITTER
|
$42.20 |
$29.80 |
$72.00 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: ()
|
$49.23 |
$8.75 |
$57.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 1 PICK-UPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS; SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN. HAZAR
|
$31.39 |
$27.77 |
$59.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 2 TANDEMS; BATCH TRUCK; MECHANICS. HAZARDOUS WASTE SITE WORK RECEIVES AN ADDITIONAL $1.50 PER HOUR FOOTNOTE: A. PAID HOLIDAYS: NE
|
$31.44 |
$27.77 |
$59.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 3 SEMI-TRAILERS; LOW-BOY TRUCKS; ASPHALT DISTRIBUTOR TRUCKS; AGITATOR; MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES; TRUCK MECHANIC
|
$31.49 |
$27.77 |
$59.26 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 4 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE CARRIER; SEL
|
$31.64 |
$27.77 |
$59.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS: GROUP 5 OFF-HIGHWAY TANDEM BACK DUMP; TWIN ENGINE EQUIPMENT; DOUBLE-HITCHED EQUIPMENT SHERE NOT SELF-LOADED. HAZARDOUS WASTE SITE WORK
|
$31.79 |
$27.77 |
$59.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |