Wage Determination MI20260096-17145-bld
Ottawa, MI · building · Rev. 1 · Effective May 17, 2026
Quick Answer
Wage determination MI20260096-17145-bld covers 40 trade classifications for building construction in Ottawa, MI. Total packages (base + fringe) range from $10.55/hr to $80.24/hr, with the highest going to BOILERMAKER. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: MI20260096-17145-bld
Revision: 1
Type: building
County: Ottawa
State: MI
Effective: May 17, 2026
Trades covered: 40
Highest rate: $80.24/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $47.28 | $25.25 | $72.53 | $0.00 | $0.00 | $0.00 | $0.00 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $40.00 | $23.65 | $63.65 | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $43.50 | $36.74 | $80.24 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $21.73 | $5.37 | $27.10 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $31.50 | $21.15 | $52.65 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $17.26 | $2.69 | $19.95 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $17.43 | $4.42 | $21.85 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $20.81 | $5.01 | $25.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| HVAC MECHANIC | $18.92 | $4.71 | $23.63 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, ORNAMENTAL | $18.48 | $7.93 | $26.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: REINFORCING | $36.55 | $29.51 | $66.06 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: STRUCTURAL | $36.55 | $29.51 | $66.06 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL; GRADE CHECKER; SANDBLASTER | $28.56 | $12.95 | $41.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LANDSCAPE & IRRIGATION | $8.93 | $1.62 | $10.55 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - BRICK | $17.61 | $4.13 | $21.74 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $14.82 | $3.59 | $18.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $18.32 | $3.28 | $21.60 | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $40.04 | $26.47 | $66.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $14.96 | $4.01 | $18.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $17.56 | $4.95 | $22.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $16.38 | $3.44 | $19.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 2 CRANE OPERATOR WITH MAIN BOOM AND JIB 140' OR LONGER, TOWER CRANE, GANTRY CRANE, WHIRLEY DERRICK FOOTNOTES: CRANE O | $43.93 | $25.25 | $69.18 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 3 BACKHOE/EXCAVATOR/TRACKHOE; CONCRETE PUMP; CRANE; GRADER/BLADE; HIGHLIFT; HOIST; ROLLER; SCRAPER; STIFF LEG DERRICK | $41.28 | $25.25 | $66.53 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 4 BROOM/SWEEPER; FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE | $39.57 | $25.25 | $64.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE | $39.57 | $25.25 | $64.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE | $33.71 | $25.25 | $58.96 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT: GROUP 7 OILER FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE | $31.23 | $25.25 | $56.48 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: TRACTOR | $15.72 | $1.92 | $17.64 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH AND SPRAY | $28.75 | $18.68 | $47.43 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: ROLLER | $17.28 | $3.43 | $20.71 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $47.40 | $23.35 | $70.75 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION | $47.40 | $23.35 | $70.75 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $26.60 | $16.75 | $43.35 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $20.96 | $7.35 | $28.31 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT AND UNIT INSTALLATION | $35.41 | $15.86 | $51.27 | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $18.07 | $4.93 | $23.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $27.94 | $21.15 | $49.09 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $32.20 | $23.46 | $55.66 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $19.82 | $2.19 | $22.01 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK | $13.57 | $1.18 | $14.75 | $0.00 | $0.00 | $0.00 | $0.00 |