Highway Construction — Juab, Utah

WD UT20260107-17851-hwy · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER in Juab, Utah (construction type: highway) is $32.17/hr base + $17.50/hr fringe = $49.67/hr total package (WD UT20260107-17851-hwy, Rev. 1).

Scroll down for all 35 trade classifications covered by this determination.

WD Number: UT20260107-17851-hwy
Revision: 1
Construction Type: highway
State: Utah (UT)
County: Juab
Effective: May 17, 2026
Trades covered: 35
Official source: SAM.gov reference UT20260107View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER $32.17 $17.50 $49.67 +100% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $22.59 $5.41 $28.00 +13% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $20.59 $2.41 $23.00 -14% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, INCLUDES LOW VOLTAGE WIRING $27.45 $2.30 $29.75 Above median +1% vs market $0.00 $0.00 $0.00 $0.00
FENCE ERECTOR $15.16 $2.53 $17.69 Top 10% $0.00 $0.00 $0.00 $0.00
HIGHWAY/PARKING LOT STRIPING: PAINTER $17.60 $2.53 $20.13 $0.00 $0.00 $0.00 $0.00
INSTALLER - GUARDRAIL $14.80 $2.66 $17.46 Above median $0.00 $0.00 $0.00 $0.00
INSTALLER - SIGN $15.00 $2.53 $17.53 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $26.61 $13.76 $40.37 Above median +76% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR $23.83 $5.92 $29.75 Above median +34% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $22.83 $12.25 $35.08 Above median +58% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $15.40 $2.53 $17.93 Above median -19% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $13.46 $2.64 $16.10 Above median -27% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $17.23 $2.79 $20.02 Above median -10% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $22.28 $5.64 $27.92 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $23.97 $10.06 $34.03 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BROOM/SWEEPER $14.52 $7.83 $22.35 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: CONCRETE FINISHING MACHINE $20.03 $6.55 $26.58 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: CRANE $30.66 $10.61 $41.27 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: DRILL $27.44 $15.65 $43.09 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $27.33 $15.42 $42.75 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $24.86 $12.91 $37.77 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $26.92 $13.23 $40.15 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MILLING MACHINE $26.78 $15.65 $42.43 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVEMENT MARKING GRINDER $27.95 $7.05 $35.00 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $24.37 $15.65 $40.02 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $23.16 $12.31 $35.47 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: SCREED $23.95 $12.17 $36.12 Top 10% $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR $31.99 $17.64 $49.63 Above median +73% vs market $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: FLAGGER $13.14 $1.75 $14.89 Above median $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER $20.59 $8.65 $29.24 Above median $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $24.09 $13.04 $37.13 Top 10% +30% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: OIL DISTRIBUTOR TRUCK $25.68 $11.25 $36.93 Top 10% +29% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: VACTOR $23.40 $0.00 $23.40 Top 10% -18% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: WATER TRUCK $24.35 $11.73 $36.08 Top 10% +26% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Juab, UT — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.