Building Construction — Pine, Minnesota

WD MN20260084-15535-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ARTICULATED HAULER in Pine, Minnesota (construction type: building) is $36.04/hr base + $20.30/hr fringe = $56.34/hr total package (WD MN20260084-15535-bld, Rev. 1).

Scroll down for all 56 trade classifications covered by this determination.

WD Number: MN20260084-15535-bld
Revision: 1
Construction Type: building
State: Minnesota (MN)
County: Pine
Effective: May 17, 2026
Trades covered: 56
Official source: SAM.gov reference MN20260084View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ARTICULATED HAULER $36.04 $20.30 $56.34 $0.00 $0.00 $0.00 $0.00
ASBESTOS ABATEMENT WORKER $39.58 $24.94 $64.52 Above median $0.00 $0.00 $0.00 $0.00
BOILERMAKER $48.35 $31.93 $80.28 Above median +63% vs market $0.00 $0.00 $0.00 $0.00
BOOM TRUCK $32.39 $11.74 $44.13 $0.00 $0.00 $0.00 $0.00
BRICKLAYER $45.27 $31.79 $77.06 Top 10% +80% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $45.54 $29.34 $74.88 Top 10% +141% vs market $0.00 $0.00 $0.00 $0.00
CARPET LAYER $45.25 $26.98 $72.23 Top 10% +83% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON $66.41 $5.00 $71.41 Above median +134% vs market $0.00 $0.00 $0.00 $0.00
DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER $46.51 $26.90 $73.41 Top 10% $0.00 $0.00 $0.00 $0.00
DRYWALL TAPER $41.72 $29.72 $71.44 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $48.01 $32.79 $80.80 Top 10% +106% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTORS $62.52 $45.36 $107.88 Top 10% +91% vs market $0.00 $0.00 $0.00 $0.00
FLAG PERSON $26.52 $19.29 $45.81 $0.00 $0.00 $0.00 $0.00
GLAZIER $48.98 $26.75 $75.73 Above median +135% vs market $0.00 $0.00 $0.00 $0.00
HEATING AND FROST INSULATORS $50.51 $23.45 $73.96 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER $41.19 $35.68 $76.87 Above median +71% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $47.86 $0.00 $47.86 Top 10% +70% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $31.66 $22.78 $54.44 Top 10% +93% vs market $0.00 $0.00 $0.00 $0.00
LABORER: SKILLED $35.22 $25.17 $60.39 +114% vs market $0.00 $0.00 $0.00 $0.00
LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICALLY SEEDING, SODDING, OR PLANT, AND TWO-FRA $31.66 $22.78 $54.44 Top 10% $0.00 $0.00 $0.00 $0.00
LATHER $47.00 $26.85 $73.85 Top 10% $0.00 $0.00 $0.00 $0.00
METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET $50.64 $26.90 $77.54 Top 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $41.66 $35.40 $77.06 Above median +131% vs market $0.00 $0.00 $0.00 $0.00
OFF-ROAD TRUCK $40.93 $21.70 $62.63 $0.00 $0.00 $0.00 $0.00
PAINTER $36.76 $26.71 $63.47 Top 10% +117% vs market $0.00 $0.00 $0.00 $0.00
PILEDRIVER $38.91 $22.08 $60.99 $0.00 $0.00 $0.00 $0.00
PIPEFITTER/STEAMFITTER $49.24 $27.18 $76.42 Above median +91% vs market $0.00 $0.00 $0.00 $0.00
PIPELAYER $46.08 $26.33 $72.41 Top 10% $0.00 $0.00 $0.00 $0.00
PLASTERER $40.39 $23.23 $63.62 Above median +94% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $49.24 $27.18 $76.42 Above median +91% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC $45.24 $22.85 $68.09 +80% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE $49.05 $26.90 $75.95 Top 10% +101% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE $48.68 $26.90 $75.58 Top 10% +100% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE $26.05 $6.76 $32.81 -13% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 8: ELEVATOR OPERATOR; GREASER; MECHANICAL SPACE HEATER $37.09 $22.85 $59.94 Above median +59% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED $30.15 $6.91 $37.06 -2% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC $41.73 $22.85 $64.58 Above median +71% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O $31.16 $23.45 $54.61 Above median +45% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN $28.35 $6.91 $35.26 -7% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 6: CAT, CHALLENGER, OR SIMILAR TYPE OF TRACTORS, WHEN PULLING DISK OR ROLLER; DREDGE DECK HAND; GRAVEL S $22.50 $6.91 $29.41 -22% vs market $0.00 $0.00 $0.00 $0.00
PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR $43.55 $26.90 $70.45 Top 10% $0.00 $0.00 $0.00 $0.00
ROOFER $43.12 $21.31 $64.43 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $57.96 $34.57 $92.53 Top 10% +208% vs market $0.00 $0.00 $0.00 $0.00
SIGN ERECTOR $37.19 $19.88 $57.07 Top 10% $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $43.53 $26.67 $70.20 +75% vs market $0.00 $0.00 $0.00 $0.00
SURVEY FIELD TECHNICIAN $29.92 $21.69 $51.61 Above median $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER $48.27 $24.14 $72.41 Above median $0.00 $0.00 $0.00 $0.00
TILE FINISHER $27.80 $23.31 $51.11 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $42.76 $30.32 $73.08 Top 10% +146% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER $25.50 $0.77 $26.27 Bottom 10% -11% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK $24.10 $6.91 $31.01 +6% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS $22.35 $6.76 $29.11 -1% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: GROUP 4: BITUMINOUS DISTRIBUTOR SPRAY OPERATOR; DUMP PERSON; GREASER; PILOT CAR DRIVER; RUBBER-TIRED, SELF-PROPELLED PACKER UNDER 8 TONS $22.40 $5.65 $28.05 -4% vs market $0.00 $0.00 $0.00 $0.00
UNDERGROUND AND OPEN DITCH LABORER $44.08 $26.33 $70.41 Above median $0.00 $0.00 $0.00 $0.00
WIRING SYSTEM TECHNICIAN $47.73 $22.24 $69.97 Top 10% $0.00 $0.00 $0.00 $0.00
WIRING SYSTEMS INSTALLER $33.44 $17.82 $51.26 Top 10% $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Pine, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Pine

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MN20260084-15535-bld →