Wage Determination VA20260020-16466-bld
Fauquier, VA · building · Rev. 3 · Effective May 17, 2026
Quick Answer
Wage determination VA20260020-16466-bld covers 32 trade classifications for building construction in Fauquier, VA. Total packages (base + fringe) range from $17.93/hr to $82.56/hr, with the highest going to ELECTRICIAN. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: VA20260020-16466-bld
Revision: 3
Type: building
County: Fauquier
State: VA
Effective: May 17, 2026
Trades covered: 32
Highest rate: $82.56/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DA | $40.77 | $20.17 | $60.94 | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $38.97 | $27.39 | $66.36 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICK POINTER/CAULKER/CLEANER | $19.68 | $0.00 | $19.68 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $38.80 | $15.17 | $53.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND FORM WORK | $23.89 | $5.23 | $29.12 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $21.94 | $3.36 | $25.30 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL FINISHER/TAPER | $29.16 | $11.86 | $41.02 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $59.50 | $23.06 | $82.56 | $0.00 | $0.00 | $0.00 | $0.00 |
| FIRESTOPPER INCLUDES THE APPLICATION OF MATERIALS OR DEVICES WITHIN OR AROUND PENETRATIONS AND OPENINGS IN ALL RATED WALL OR FLOOR ASSEMBLIES, IN ORDE | $30.21 | $10.43 | $40.64 | $0.00 | $0.00 | $0.00 | $0.00 |
| FLOOR LAYER: SOFT FLOORS | $18.75 | $0.00 | $18.75 | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $32.41 | $14.46 | $46.87 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, ORNAMENTAL AND STRUCTURAL | $37.86 | $25.86 | $63.72 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $25.85 | $6.94 | $32.79 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL, INCLUDING BRICK MASON TENDING AND CEMENT MASON TENDING | $15.03 | $2.90 | $17.93 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $16.81 | $4.26 | $21.07 | $0.00 | $0.00 | $0.00 | $0.00 |
| MASON - STONE | $45.65 | $21.21 | $66.86 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $23.50 | $4.50 | $28.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $18.95 | $4.03 | $22.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $21.99 | $4.98 | $26.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $31.68 | $2.64 | $34.32 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: FORKLIFT | $21.56 | $7.57 | $29.13 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $22.26 | $3.57 | $25.83 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $16.25 | $4.88 | $21.13 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $29.16 | $11.86 | $41.02 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER: INCLUDES HVAC PIPE, UNIT AND TEMPERATURE CONTROLS INSTALLATIONS | $22.23 | $4.40 | $26.63 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $27.11 | $8.77 | $35.88 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION.$ 24.19 7.28 ROOFER | $15.83 | $3.06 | $18.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $45.22 | $27.69 | $72.91 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $23.40 | $0.00 | $23.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $27.80 | $10.25 | $38.05 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $19.22 | $2.58 | $21.80 | $0.00 | $0.00 | $0.00 | $0.00 |
| WATERPROOFER | $21.75 | $1.57 | $23.32 | $0.00 | $0.00 | $0.00 | $0.00 |