Wage Determination OK20260045-14390-bld
Grady, OK · building · Rev. 2 · Effective May 17, 2026
Quick Answer
Wage determination OK20260045-14390-bld covers 41 trade classifications for building construction in Grady, OK. Total packages (base + fringe) range from $11.40/hr to $89.55/hr, with the highest going to PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: OK20260045-14390-bld
Revision: 2
Type: building
County: Grady
State: OK
Effective: May 17, 2026
Trades covered: 41
Highest rate: $89.55/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BRICKLAYER | $26.92 | $13.09 | $40.01 | $0.00 | $0.00 | $0.00 | $0.00 |
| CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $27.79 | $10.05 | $37.84 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $14.45 | $0.00 | $14.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION | $16.31 | $2.96 | $19.27 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $16.72 | $0.00 | $16.72 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL FINISHER/TAPER | $14.25 | $0.00 | $14.25 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL HANGER, INCLUDES METAL STUD INSTALLATION | $14.08 | $0.00 | $14.08 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $41.40 | $13.14 | $54.54 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $24.26 | $9.76 | $34.02 | $0.00 | $0.00 | $0.00 | $0.00 |
| FENCE ERECTOR | $16.00 | $0.00 | $16.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $12.02 | $2.42 | $14.44 | $0.00 | $0.00 | $0.00 | $0.00 |
| HVAC MECHANIC | $21.64 | $6.46 | $28.10 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $17.11 | $0.00 | $17.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: ORNAMENTAL AND STRUCTURAL | $32.10 | $17.38 | $49.48 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $11.40 | $0.00 | $11.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LANDSCAPE | $13.75 | $0.00 | $13.75 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - BRICK | $12.00 | $0.00 | $12.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.00 | $1.91 | $14.91 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $12.39 | $0.00 | $12.39 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PLASTER TENDER | $12.00 | $0.00 | $12.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER | $35.40 | $19.05 | $54.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $29.15 | $11.81 | $40.96 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $21.25 | $4.35 | $25.60 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $20.64 | $2.35 | $22.99 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $14.28 | $1.70 | $15.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $16.18 | $0.00 | $16.18 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER | $13.38 | $1.54 | $14.92 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $12.17 | $0.00 | $12.17 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE | $51.11 | $38.44 | $89.55 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION | $41.00 | $16.03 | $57.03 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $41.00 | $16.03 | $57.03 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER; SEMI- TRAILER TRUCK DRIVER | $27.25 | $19.05 | $46.30 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT | $28.77 | $19.05 | $47.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $26.30 | $10.34 | $36.64 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $33.38 | $16.36 | $49.74 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 19.45 6.38 PLASTERER | $17.50 | $0.00 | $17.50 | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $39.05 | $25.77 | $64.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP AND FLATBED TRUCK | $11.60 | $0.00 | $11.60 | $0.00 | $0.00 | $0.00 | $0.00 |