Wage Determination OK20260037-14382-bld

Carter, OK · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination OK20260037-14382-bld covers 29 trade classifications for building construction in Carter, OK. Total packages (base + fringe) range from $11.65/hr to $58.11/hr, with the highest going to BOILERMAKER. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: OK20260037-14382-bld
Revision: 1
Type: building
County: Carter
State: OK
Effective: May 17, 2026
Trades covered: 29
Highest rate: $58.11/hr
Official source: SAM.gov reference OK20260037View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $33.70 $24.41 $58.11 $0.00 $0.00 $0.00 $0.00
BRICKLAYER $20.00 $0.00 $20.00 $0.00 $0.00 $0.00 $0.00
CAPACITY CRANES. ALL TOWER CRANES $38.09 $19.05 $57.14 $0.00 $0.00 $0.00 $0.00
CARPENTER $14.96 $0.00 $14.96 $0.00 $0.00 $0.00 $0.00
CARPENTER $16.20 $0.00 $16.20 $0.00 $0.00 $0.00 $0.00
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, AND FORM WORK $16.19 $0.96 $17.15 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $14.50 $0.00 $14.50 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $21.60 $0.00 $21.60 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $21.51 $6.27 $27.78 $0.00 $0.00 $0.00 $0.00
FLOOR LAYER $18.74 $1.10 $19.84 $0.00 $0.00 $0.00 $0.00
FORM WORKER $13.79 $0.92 $14.71 $0.00 $0.00 $0.00 $0.00
GLAZIER $15.27 $1.46 $16.73 $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $32.10 $17.38 $49.48 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $11.58 $0.77 $12.35 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $12.00 $0.00 $12.00 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $13.04 $0.00 $13.04 $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $11.65 $0.00 $11.65 $0.00 $0.00 $0.00 $0.00
LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER $35.40 $19.05 $54.45 $0.00 $0.00 $0.00 $0.00
LESS THAN 200 TON CAPACITY $36.14 $19.05 $55.19 $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $16.83 $0.00 $16.83 $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $18.02 $0.00 $18.02 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY $12.32 $0.00 $12.32 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $41.00 $16.03 $57.03 $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $18.00 $3.23 $21.23 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 10 OILER $27.25 $19.05 $46.30 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER $34.07 $19.05 $53.12 $0.00 $0.00 $0.00 $0.00
ROOFER $15.00 $0.29 $15.29 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $33.38 $16.36 $49.74 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $21.52 $6.00 $27.52 $0.00 $0.00 $0.00 $0.00
View all WDs for Carter → Revision history →