Wage Determination MT20260038-17754-bld

Jefferson, MT · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination MT20260038-17754-bld covers 23 trade classifications for building construction in Jefferson, MT. Total packages (base + fringe) range from $19.18/hr to $106.05/hr, with the highest going to ELEVATOR MECHANIC FOOTNOTE: ADDITIONAL FRINGE BENEFITS DUE INCLUDE A. EMPLOYER CONTRIBUTES 8% OF THE BASIC HOURLY RATE FOR OVER 5 YEAR'S SERVICE AND 6. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: MT20260038-17754-bld
Revision: 1
Type: building
County: Jefferson
State: MT
Effective: May 17, 2026
Trades covered: 23
Highest rate: $106.05/hr
Official source: SAM.gov reference MT20260038View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $38.75 $32.31 $71.06 $0.00 $0.00 $0.00 $0.00
BRICKLAYER $33.11 $17.18 $50.29 $0.00 $0.00 $0.00 $0.00
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL FINISHING/TAPING, DRYWALL HANGING, AND FORMWORK $20.51 $7.13 $27.64 $0.00 $0.00 $0.00 $0.00
CARPENTER. Zone Definition: The hourly rate applicable to each project is determined by measuring the raod miles over the shortest practical route fro $32.05 $15.02 $47.07 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $18.27 $1.50 $19.77 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $40.00 $19.88 $59.88 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: Low Voltage Wiring for Alarms and Computers $23.90 $12.85 $36.75 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: ADDITIONAL FRINGE BENEFITS DUE INCLUDE A. EMPLOYER CONTRIBUTES 8% OF THE BASIC HOURLY RATE FOR OVER 5 YEAR'S SERVICE AND 6 $67.61 $38.44 $106.05 $0.00 $0.00 $0.00 $0.00
GLAZIER $17.93 $2.62 $20.55 $0.00 $0.00 $0.00 $0.00
HEAT AND FROST INSULATOR $43.81 $21.87 $65.68 $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING AND STRUCTURAL $36.83 $25.30 $62.13 $0.00 $0.00 $0.00 $0.00
LABORER, ZONE 1: MASON TENDER-BRICK ZONE DEFINITIONS FOR LABORERS THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING TH $23.05 $12.72 $35.77 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $17.77 $5.23 $23.00 $0.00 $0.00 $0.00 $0.00
OPERATOR: CRANE $24.04 $7.41 $31.45 $0.00 $0.00 $0.00 $0.00
OPERATOR: EXCAVATOR $22.20 $6.75 $28.95 $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $21.44 $8.05 $29.49 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING $19.18 $0.00 $19.18 $0.00 $0.00 $0.00 $0.00
PIPEFITTER, EXCLUDES HVAC PIPE INSTALLATION $46.45 $19.92 $66.37 $0.00 $0.00 $0.00 $0.00
PLUMBER, INCLUDES HVAC PIPE INSTALLATION $46.45 $19.92 $66.37 $0.00 $0.00 $0.00 $0.00
ROOFER $15.48 $5.28 $20.76 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $40.00 $22.07 $62.07 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $39.97 $24.40 $64.37 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $19.36 $5.37 $24.73 $0.00 $0.00 $0.00 $0.00
View all WDs for Jefferson → Revision history →