Wage Determination MO20260087-15860-bld

St Charles, MO · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination MO20260087-15860-bld covers 26 trade classifications for building construction in St Charles, MO. Total packages (base + fringe) range from $46.71/hr to $101.17/hr, with the highest going to ELEVATOR MECHANIC. FOOTNOTES: A. VACATION: EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE AS VACATION PAY CREDIT FOR MORE THAN 5 YEARS OF SERVICE; AND 6. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: MO20260087-15860-bld
Revision: 1
Type: building
County: St Charles
State: MO
Effective: May 17, 2026
Trades covered: 26
Highest rate: $101.17/hr
Official source: SAM.gov reference MO20260087View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BRICKLAYER $41.15 $23.90 $65.05 $0.00 $0.00 $0.00 $0.00
CARPENTER $39.78 $22.40 $62.18 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $38.46 $20.15 $58.61 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $49.29 $33.64 $82.93 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC. FOOTNOTES: A. VACATION: EMPLOYER CONTRIBUTES 8% OF BASIC HOURLY RATE AS VACATION PAY CREDIT FOR MORE THAN 5 YEARS OF SERVICE; AND 6 $62.73 $38.44 $101.17 $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: SOFT FLOORS $40.08 $21.85 $61.93 $0.00 $0.00 $0.00 $0.00
HEAT & FROST INSULATOR $43.48 $27.24 $70.72 $0.00 $0.00 $0.00 $0.00
IRONWORKER $44.27 $31.65 $75.92 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $41.18 $15.96 $57.14 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $37.58 $17.21 $54.79 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $31.80 $14.91 $46.71 $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $40.82 $17.56 $58.38 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $39.61 $30.15 $69.76 $0.00 $0.00 $0.00 $0.00
PAINTER $39.40 $17.66 $57.06 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $52.60 $29.93 $82.53 $0.00 $0.00 $0.00 $0.00
PLUMBER $52.60 $29.93 $82.53 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $43.46 $30.22 $73.68 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER $43.46 $30.22 $73.68 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BULLDOZER $45.96 $30.57 $76.53 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: CRANE $45.96 $30.57 $76.53 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: FORKLIFT $43.46 $30.22 $73.68 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: OILER $39.06 $30.38 $69.44 $0.00 $0.00 $0.00 $0.00
ROOFER $40.00 $22.05 $62.05 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $52.00 $27.12 $79.12 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $51.73 $29.55 $81.28 $0.00 $0.00 $0.00 $0.00
TILE SETTER $34.09 $20.36 $54.45 $0.00 $0.00 $0.00 $0.00
View all WDs for St Charles → Revision history →