Wage determination MO20260033-15853-bld covers 50 trade classifications for building construction in Montgomery, MO. Total packages (base + fringe) range from $24.90/hr to $85.86/hr, with the highest going to PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: MO20260033-15853-bld
Revision: 1
Type: building
County: Montgomery
State: MO
Effective: May 17, 2026
Trades covered: 50
Highest rate: $85.86/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $43.48 | $27.24 | $70.72 | $0.00 | $0.00 | $0.00 | $0.00 |
| ASBESTOS WORKER/HEAT & FROST INSULATOR | $31.97 | $14.00 | $45.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $27.66 | $5.88 | $33.54 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK | $39.53 | $21.85 | $61.38 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDING DRYWALL HANGING & FORM WORK | $41.30 | $21.85 | $63.15 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: INCLUDING DRYWALL HANGING & FORM WORK | $44.19 | $21.85 | $66.04 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: INCLUDING DRYWALL HANGING, FORM WORK & RESILIENT/VINYL FLOOR INSTALLATION | $31.51 | $22.25 | $53.76 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER: RESILIENT & VINYL FLOORING ONLY | $40.08 | $21.85 | $61.93 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $33.52 | $15.88 | $49.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $36.63 | $9.85 | $46.48 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $54.01 | $27.85 | $81.86 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $40.50 | $23.26 | $63.76 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $37.60 | $22.14 | $59.74 | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $29.87 | $1.47 | $31.34 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $21.02 | $9.49 | $30.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $36.00 | $34.25 | $70.25 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $41.67 | $31.25 | $72.92 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: ASBESTOS ABATEMENT | $24.90 | $0.00 | $24.90 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $28.95 | $14.95 | $43.90 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $32.23 | $15.91 | $48.14 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: BRICK MASON TENDER | $29.71 | $15.50 | $45.21 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $26.95 | $14.95 | $41.90 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $30.33 | $15.91 | $46.24 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL & LANDSCAPE | $27.71 | $15.50 | $43.21 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL, LANDSCAPE & BRICK MASON TENDER | $41.18 | $15.96 | $57.14 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH & ROLLER ONLY | $24.43 | $17.76 | $42.19 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH & ROLLER ONLY | $33.90 | $17.21 | $51.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER, & DRYWALL FINISHING/TAPING ONLY | $28.56 | $17.21 | $45.77 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $25.39 | $17.76 | $43.15 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: DRYWALL FINISHING/TAPING ONLY | $34.90 | $17.21 | $52.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: SPRAY | $18.79 | $8.12 | $26.91 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION | $57.51 | $28.35 | $85.86 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER | $48.66 | $30.13 | $78.79 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION | $50.60 | $29.38 | $79.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION | $58.38 | $25.29 | $83.67 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK $7.0 MILLION & UNDER | $48.66 | $30.13 | $78.79 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER, EXCLUDES HVAC PIPE INSTALLATION: MECHANICAL CONTRACTS INCLUDING ALL PIPING AND TEMPERATURE CONTROL WORK OVER $7.0 MILLION | $50.60 | $29.38 | $79.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR | $39.06 | $30.38 | $69.44 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: BULLDOZER | $39.06 | $30.38 | $69.44 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE | $39.06 | $30.38 | $69.44 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ROLLER | $35.76 | $30.38 | $66.14 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $40.00 | $22.05 | $62.05 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $32.25 | $17.46 | $49.71 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $33.60 | $19.99 | $53.59 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $47.20 | $26.28 | $73.48 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $52.00 | $27.12 | $79.12 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT AND UNIT INSTALLATION | $36.51 | $22.39 | $58.90 | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $45.94 | $27.53 | $73.47 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $32.79 | $21.31 | $54.10 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $25.57 | $0.00 | $25.57 | $0.00 | $0.00 | $0.00 | $0.00 |