Wage Determination MA20260003-15435-bld

Franklin, MA · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination MA20260003-15435-bld covers 67 trade classifications for building construction in Franklin, MA. Total packages (base + fringe) range from $54.28/hr to $105.61/hr, with the highest going to SPRINKLER FITTER A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOY. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: MA20260003-15435-bld
Revision: 1
Type: building
County: Franklin
State: MA
Effective: May 17, 2026
Trades covered: 67
Highest rate: $105.61/hr
Official source: SAM.gov reference MA20260003View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
$2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLU $44.73 $30.58 $75.31 $0.00 $0.00 $0.00 $0.00
BOILERMAKER $50.62 $28.82 $79.44 $0.00 $0.00 $0.00 $0.00
BREAKERS; SELF-POWERED CONCRETE PAVEMENT FINISHING HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S $36.35 $30.58 $66.93 $0.00 $0.00 $0.00 $0.00
BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS $50.81 $32.27 $83.08 $0.00 $0.00 $0.00 $0.00
BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS $50.81 $32.27 $83.08 $0.00 $0.00 $0.00 $0.00
CABLEWAYS; SHAFT HOISTS; MUCKING MACHINES DERRICKS; BACKHOES; BULLDOZERS; GRADALLS; ELEVATING GRADERS; PILE DRIVERS; CONCRETE PAVERS; TRENCHING MACHIN $41.23 $30.58 $71.81 $0.00 $0.00 $0.00 $0.00
CARPENTER $43.33 $27.82 $71.15 $0.00 $0.00 $0.00 $0.00
CARPENTER (FRANKLIN COUNTY) $43.33 $27.82 $71.15 $0.00 $0.00 $0.00 $0.00
CARPENTER/LATHER/DRYWALL APPLICATOR (HAMPDEN; HAMPSHIRE AND FRANKLIN) $43.33 $27.82 $71.15 $0.00 $0.00 $0.00 $0.00
COMPACTORS; TRACTOR WITHOUT BLADE DRAWING SHEEPSFOOT ROLLER; RUBBER TIRE ROLLER; VIBRATORY ROLLER OR OTHER TYPE OF COMPACTORS INCLUDING MACHINES FOR P $37.47 $30.58 $68.05 $0.00 $0.00 $0.00 $0.00
COMPRESSOR HOUSE; ROCK AND EARTH BORING MACHINES; FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 $40.92 $30.58 $71.50 $0.00 $0.00 $0.00 $0.00
CU FT; PUMPS 4 INCHES TO 16 INCHES. HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON $34.41 $30.58 $64.99 $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.14 $37.35 $78.49 $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.02 $37.35 $78.37 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (BERKSHIRE; FRANKLIN; HAMPDEN; HAMPSHIRE) $52.16 $29.56 $81.72 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN (HAMPDEN; HAMPSHIRE) $52.16 $29.56 $81.72 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RA $66.41 $38.44 $104.85 $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: CARPET $43.23 $27.79 $71.02 $0.00 $0.00 $0.00 $0.00
FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS D $42.72 $30.58 $73.30 $0.00 $0.00 $0.00 $0.00
GLAZIER FOOTNOTE: A. PAID HOLIDAY: LABOR DAY (PROVIDED EMPLOYEE HAS WORKED ANY PART OF THE WEEK PRIOR TO LABOR DAY AND ANY PART OF THE WEEK AFTER LABO $43.13 $21.00 $64.13 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDE $50.73 $30.58 $81.31 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDE $49.23 $30.58 $79.81 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDE $48.23 $30.58 $78.81 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDE $47.23 $30.58 $77.81 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDE $45.73 $30.58 $76.31 $0.00 $0.00 $0.00 $0.00
INSULATOR/ASBESTOS WORKER $44.36 $36.63 $80.99 $0.00 $0.00 $0.00 $0.00
IRONWORKER (BERKSHIRE) $40.75 $31.91 $72.66 $0.00 $0.00 $0.00 $0.00
IRONWORKER (BERKSHIRE; FRANKLIN; HAMPDEN; HAMPSHIRE) $41.89 $33.90 $75.79 $0.00 $0.00 $0.00 $0.00
IRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING, FENCE ERECTOR, MACHINERY MOVER, RIGGER, RODMAN, STONE DERRICKMAN (BERKSHIRE)..$ 40.75 31.91 IRONWORK $41.00 $31.91 $72.91 $0.00 $0.00 $0.00 $0.00
LABORERS: (BERKSHIRE COUNTY, FRANKLIN COUNTY, HAMPSHIRE COUNTY) $31.54 $25.63 $57.17 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1 LABORERS, CARPENTER TENDERS, WRECKING LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY FRANKLIN COUNTY) $35.00 $28.87 $63.87 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS (FRANKLIN) $38.95 $29.70 $68.65 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2 ASPHALT RAKER; FENCE AND GUARD RAIL ERECTOR; LASER BEAM OPERATOR; MASON TENMDER; PIPELAYER; PNEUMATIC DRILL OPERATOR; PNEUMATIC TOOL $39.20 $29.70 $68.90 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2 ASPHALT RAKERS, CARBIDE CORE DRILLER OPERATORS, CHAIN SAW OPERATORS, PIPELAYERS, JACKHAMMER AND PAVING BREAKER OPERATORS, BARCO TYPE $35.25 $28.87 $64.12 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (FRANKLIN) $39.70 $29.70 $69.40 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3 PRECAST FLOOR AND ROOF PLANK ERECTORS, SIGN ERECTORS, ASBESTOS REMOVAL LABORERS, HAZ-MAT LABORERS (HAMPDEN COUNTY, HAMPSHIRE COUNTY $35.75 $28.87 $64.62 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4 AIR TRACK OPERATORS, BLOCK PAVERS, RAMMERS AND CURB SETTERS, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (HAMPDEN COUNTY, HAMPSHIRE CO $35.75 $28.87 $64.62 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN) $39.95 $29.70 $69.65 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5 POWDERMAN AND BLASTER (HAMPDEN COUNTY, HAMPSHIRE COUNTY FRANKLIN COUNTY) $36.00 $28.87 $64.87 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5 PRECAST FLOOR AND ROOF, PLANK ERECTOR (FRANKLIN) $39.70 $29.70 $69.40 $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN) $40.95 $29.70 $70.65 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATOR $42.26 $22.56 $64.82 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN, CABLE SPLICER AND DYNAMITE MAN $46.96 $25.05 $72.01 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: MATERIAL MAN, TRACTOR TRAILER DRIVER, EQUIPMENT OPERATOR $39.92 $21.80 $61.72 $0.00 $0.00 $0.00 $0.00
MARBLE FINISHER $28.43 $25.85 $54.28 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $43.42 $33.00 $76.42 $0.00 $0.00 $0.00 $0.00
PAINTER REPAINT: BRUSH, TAPER $35.40 $31.95 $67.35 $0.00 $0.00 $0.00 $0.00
PAINTER REPAINT: SPRAY, SANDBLAST $36.80 $31.95 $68.75 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, TAPER $38.08 $31.95 $70.03 $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY, SANDBLAST $39.48 $31.95 $71.43 $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN $55.79 $35.47 $91.26 $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER (BERKSHIRE; FRANKLIN) $52.26 $31.05 $83.31 $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER (FRANKLIN) $55.00 $31.57 $86.57 $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS (BERKSHIRE; FRANKLIN; HAMPDEN; HAMPSHIRE) $52.26 $31.05 $83.31 $0.00 $0.00 $0.00 $0.00
PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR D $42.41 $30.58 $72.99 $0.00 $0.00 $0.00 $0.00
ROOFERS: COMPOSITION ROOFERS & DAMP WATERPROOFERS ALL TEAR-OFF AND/OR REMOVAL, AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL ARE $42.48 $30.14 $72.62 $0.00 $0.00 $0.00 $0.00
ROOFERS: PITCH,SLATE, TILE AND PRECAST CONCRETE ALL TEAR-OFF AND/OR REMOVAL, AND ALL SPUDDING, SWEEPING, VACUUMING AND/OR CLEANUP OF ANY AND ALL AREAS $42.48 $30.14 $72.62 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $43.48 $36.46 $79.94 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER A. PAID HOLIDAYS: MEMORIAL DAY, JULY 4TH, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS BEEN IN THE EMPLOY $64.85 $40.76 $105.61 $0.00 $0.00 $0.00 $0.00
TELEDATA SYSTEM INSTALLER $52.16 $29.56 $81.72 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $40.78 $37.35 $78.13 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS $40.95 $37.35 $78.30 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTO $41.24 $37.35 $78.59 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $41.53 $37.35 $78.88 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATE $41.82 $37.35 $79.17 $0.00 $0.00 $0.00 $0.00
WITH SKIP; PUMPS UP TO 4 INCHES; POWER HEATERS; OILER; A-FRAME TRUCKS; FORKLIFTS-UP TO 7 FT. LIFT AND UP TO 3 TON CAPACITY; HYDRO BROOM; STUD WELDER $52.73 $30.58 $83.31 $0.00 $0.00 $0.00 $0.00
YD; SCRAPERS UP TO 21 CU YD; TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PL $40.70 $30.58 $71.28 $0.00 $0.00 $0.00 $0.00
View all WDs for Franklin → Revision history →