Wage determination LA20260038-15354-bld covers 25 trade classifications for building construction in Jefferson, LA. Total packages (base + fringe) range from $12.39/hr to $89.55/hr, with the highest going to ELEVATOR MECHANIC A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANK. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: LA20260038-15354-bld
Revision: 2
Type: building
County: Jefferson
State: LA
Effective: May 17, 2026
Trades covered: 25
Highest rate: $89.55/hr
Official source: SAM.gov reference LA20260038View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $32.66 $9.86 $42.52 $0.00 $0.00 $0.00 $0.00
BRICKLAYER $18.88 $0.00 $18.88 $0.00 $0.00 $0.00 $0.00
CARPENTER $15.00 $0.00 $15.00 $0.00 $0.00 $0.00 $0.00
CARPENTER, EXCLUDES DRYWALL HANGING AND METAL STUD INSTALLATION, AND FORM WORK $18.45 $3.18 $21.63 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $30.47 $7.97 $38.44 $0.00 $0.00 $0.00 $0.00
DRYWALL HANGER AND METAL STUD INSTALLER $18.35 $4.33 $22.68 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $36.00 $16.66 $52.66 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $28.93 $6.31 $35.24 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, THE FRIDAY AFTER THANK $51.11 $38.44 $89.55 $0.00 $0.00 $0.00 $0.00
GLAZIER $25.44 $12.20 $37.64 $0.00 $0.00 $0.00 $0.00
IRONWORKER $34.75 $13.86 $48.61 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $14.68 $0.00 $14.68 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $12.39 $0.00 $12.39 $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $21.03 $0.00 $21.03 $0.00 $0.00 $0.00 $0.00
PAINTER $18.83 $9.48 $28.31 $0.00 $0.00 $0.00 $0.00
PAINTER, EXCLUDES DRYWALL FINISHING/TAPING $18.95 $8.91 $27.86 $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $18.63 $3.43 $22.06 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $33.30 $14.98 $48.28 $0.00 $0.00 $0.00 $0.00
PLUMBER $34.87 $17.79 $52.66 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: CRANE CRANE PREMIUMS: 50-150 TONS $1.75 OVER 150 TONS $2.25 $23.46 $8.35 $31.81 $0.00 $0.00 $0.00 $0.00
ROOFER $16.77 $5.66 $22.43 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 20.66 0.00 SHEET METAL WORKER $25.54 $10.30 $35.84 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $20.98 $5.46 $26.44 $0.00 $0.00 $0.00 $0.00
TILE SETTER $20.00 $0.00 $20.00 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $15.00 $0.00 $15.00 $0.00 $0.00 $0.00 $0.00