Wage determination KS20260054-15698-bld covers 40 trade classifications for building construction in Linn, KS. Total packages (base + fringe) range from $12.48/hr to $99.13/hr, with the highest going to ELEVATOR MECHANIC A. VACATION PAY: 6% FOR 6 MONTHS TO 5 YEARS SERVICE; 8% WITH 5 OR MORE YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: KS20260054-15698-bld
Revision: 1
Type: building
County: Linn
State: KS
Effective: May 17, 2026
Trades covered: 40
Highest rate: $99.13/hr
Official source: SAM.gov reference KS20260054View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR (MECHANICAL) $45.60 $35.47 $81.07 $0.00 $0.00 $0.00 $0.00
BRICKLAYER $43.57 $23.02 $66.59 $0.00 $0.00 $0.00 $0.00
CARPENTER $43.28 $21.25 $64.53 $0.00 $0.00 $0.00 $0.00
CARPENTER $44.63 $22.40 $67.03 $0.00 $0.00 $0.00 $0.00
CARPENTER $40.94 $21.25 $62.19 $0.00 $0.00 $0.00 $0.00
CARPENTER $30.00 $1.62 $31.62 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $40.13 $20.50 $60.63 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $37.61 $22.60 $60.21 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $51.01 $26.25 $77.26 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC A. VACATION PAY: 6% FOR 6 MONTHS TO 5 YEARS SERVICE; 8% WITH 5 OR MORE YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL $60.69 $38.44 $99.13 $0.00 $0.00 $0.00 $0.00
GLAZIER $39.32 $22.34 $61.66 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $31.60 $16.95 $48.55 $0.00 $0.00 $0.00 $0.00
LABORER: CONCRETE SAW $31.51 $11.60 $43.11 $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $12.48 $0.00 $12.48 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $26.84 $11.38 $38.22 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $17.86 $1.01 $18.87 $0.00 $0.00 $0.00 $0.00
LABORERS: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR $31.99 $16.03 $48.02 $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $33.12 $13.96 $47.08 $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $41.36 $21.74 $63.10 $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $30.35 $12.04 $42.39 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $32.68 $13.57 $46.25 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER, AND SPRAY $36.18 $19.97 $56.15 $0.00 $0.00 $0.00 $0.00
PAINTER: DRYWALL FINISHING/TAPING $36.18 $19.97 $56.15 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $55.56 $25.80 $81.36 $0.00 $0.00 $0.00 $0.00
PLASTERER $29.85 $13.29 $43.14 $0.00 $0.00 $0.00 $0.00
PLUMBER $54.28 $23.79 $78.07 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $45.48 $22.42 $67.90 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER $45.48 $22.42 $67.90 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: CRANE $47.29 $22.42 $69.71 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: FORKLIFT $44.14 $22.42 $66.56 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: OILER $39.93 $22.42 $62.35 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: PAVER $45.48 $22.42 $67.90 $0.00 $0.00 $0.00 $0.00
ROOFER $38.45 $22.29 $60.74 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $52.18 $27.15 $79.33 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $26.68 $11.61 $38.29 $0.00 $0.00 $0.00 $0.00
TILE FINISHER $20.74 $1.46 $22.20 $0.00 $0.00 $0.00 $0.00
TILE SETTER $30.18 $13.52 $43.70 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP $27.29 $10.71 $38.00 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY TRUCK $39.89 $15.85 $55.74 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: SEMI-TRAILER TRUCK $39.89 $15.85 $55.74 $0.00 $0.00 $0.00 $0.00