Building Construction — Chelan, Washington
WD WA20260103-16967-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for 120TH MERIDIAN) in Chelan, Washington (construction type: building) is $60.67/hr base + $27.57/hr fringe = $88.24/hr total package (WD WA20260103-16967-bld, Rev. 1).
Scroll down for all 45 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| 120TH MERIDIAN) | $60.67 | $27.57 | $88.24 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $39.57 | $20.50 | $60.07 Above median +34% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $44.21 | $17.28 | $61.49 Above median +75% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $54.16 | $21.27 | $75.43 Top 10% +118% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $53.20 | $29.15 | $82.35 Top 10% +77% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELEVATOR MECHANIC. FOOTNOTE: A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YE | $67.61 | $38.44 | $106.05 Above median +66% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| HEAT & FROST INSULATOR | $75.37 | $18.82 | $94.19 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $57.94 | $34.52 | $92.46 Top 10% +81% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER, MASON TENDER BRICK | $50.38 | $16.96 | $67.34 Top 10% +145% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $29.62 | $7.62 | $37.24 Top 10% +35% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: CONCRETE SAW CHAIN | $51.52 | $16.99 | $68.51 Top 10% +149% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: FIRE WATCH | $40.56 | $15.60 | $56.16 Top 10% +104% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: FORM STRIPPING | $50.38 | $16.96 | $67.34 Top 10% +145% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GRADE CHECKER | $31.86 | $12.98 | $44.84 Above median +63% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: HOD CARRIER | $33.50 | $11.08 | $44.58 Bottom 10% +62% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: JACKHAMMER | $51.52 | $16.99 | $68.51 Top 10% +149% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $50.38 | $16.96 | $67.34 Top 10% +145% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: NOZZLE PERSON | $52.31 | $17.01 | $69.32 Top 10% +152% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $32.17 | $11.49 | $43.66 Top 10% +59% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $53.76 | $0.00 | $53.76 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BLADE FINISH | $59.88 | $27.57 | $87.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $40.53 | $9.56 | $50.09 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER: D9 & UNDER | $59.23 | $27.57 | $86.80 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CONCRETE PUMP | $52.92 | $22.63 | $75.55 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE: 100 TONS THROUGH 199 TONS, OR 150' OF BOOM | $61.56 | $27.57 | $89.13 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE: 20 TONS THROUGH 44 TONS WITH ATTACHMENTS; TRUCK CRANE OILER/DRIVER: 100 TONS | $59.88 | $27.57 | $87.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE: 200 TONS- 299 TONS, OR 250? OF BOOM INCLUDING JIB WITH ATTACHMENTS | $62.47 | $27.57 | $90.04 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE: 45 TONS THROUGH 99 TONS, UNDER 150' OF BOOM | $60.67 | $27.57 | $88.24 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: DRILL | $56.42 | $21.15 | $77.57 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $60.67 | $27.57 | $88.24 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER: OVERHEAD UNDER 6 YARDS | $59.88 | $27.57 | $87.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MECHANIC | $40.77 | $15.91 | $56.68 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: OILER | $36.39 | $16.62 | $53.01 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER | $60.67 | $27.57 | $88.24 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $55.10 | $3.71 | $58.81 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $41.24 | $14.70 | $55.94 Above median +99% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $60.72 | $34.15 | $94.87 Top 10% +150% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $60.72 | $34.15 | $94.87 Top 10% +150% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER, EXCLUDES METAL ROOFS | $27.00 | $0.00 | $27.00 Bottom 10% -7% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEETMETAL WORKER | $45.83 | $27.92 | $73.75 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $36.16 | $0.00 | $36.16 -5% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $27.26 | $11.99 | $39.25 +31% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $36.35 | $14.57 | $50.92 Above median +70% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: CONCRETE TRUCK | $55.43 | $27.52 | $82.95 Top 10% +171% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $31.81 | $16.53 | $48.34 Top 10% +58% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Chelan, WA — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Chelan
Compliance Notes
- This wage determination applies to federal contracts for building construction in Chelan, Washington.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.