Building Construction — Grayson, Texas

WD TX20260249-14844-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Grayson, Texas (construction type: building) is $33.23/hr base + $7.52/hr fringe = $40.75/hr total package (WD TX20260249-14844-bld, Rev. 1).

Scroll down for all 38 trade classifications covered by this determination.

WD Number: TX20260249-14844-bld
Revision: 1
Construction Type: building
State: Texas (TX)
County: Grayson
Effective: May 17, 2026
Trades covered: 38
Official source: SAM.gov reference TX20260249View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $33.23 $7.52 $40.75 Bottom 10% +77% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $33.17 $24.92 $58.09 +88% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $19.95 $0.00 $19.95 -19% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $15.81 $0.00 $15.81 -32% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $13.27 $0.00 $13.27 -41% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $20.59 $3.36 $23.95 -12% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $12.33 $0.00 $12.33 Bottom 10% -48% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $16.83 $4.58 $21.41 -10% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: ORNAMENTAL $29.64 $8.43 $38.07 Bottom 10% +60% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $10.00 $0.00 $10.00 -46% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $10.95 $0.00 $10.95 -40% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $10.76 $0.00 $10.76 -41% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $13.00 $0.35 $13.35 -27% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ROOF TEAROFF $11.28 $0.00 $11.28 Top 10% -39% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $12.89 $0.00 $12.89 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $13.93 $0.00 $13.93 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $18.29 $1.31 $19.60 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: DRILL $17.60 $0.50 $18.10 $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $13.63 $0.00 $13.63 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $12.95 $0.00 $12.95 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $13.39 $0.90 $14.29 $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $17.52 $3.33 $20.85 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $18.44 $0.00 $18.44 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $15.04 $0.00 $15.04 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER, AND SPRAY $13.46 $2.49 $15.95 -25% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $39.76 $14.04 $53.80 +91% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $39.76 $14.04 $53.80 Above median +91% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $22.27 $4.81 $27.08 -4% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR ( HYDRAULIC CRANES 59 TONS AND UNDER) $32.35 $13.10 $45.45 Top 10% +90% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR ( TOWER CRANE) $32.85 $13.10 $45.95 Top 10% +93% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $16.53 $0.00 $16.53 -24% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 21.31 4.66 SHEET METAL WORKER $21.04 $5.28 $26.32 -2% vs market $0.00 $0.00 $0.00 $0.00
TILE FINISHER $11.22 $0.00 $11.22 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $14.25 $0.00 $14.25 -32% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $12.39 $1.18 $13.57 -47% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: FLATBED TRUCK $19.65 $8.57 $28.22 Top 10% +11% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: SEMI-TRAILER TRUCK $12.50 $0.00 $12.50 Above median -51% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: WATER TRUCK $12.00 $4.11 $16.11 -37% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Grayson, TX — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.