Building Construction — Mifflin, Pennsylvania

WD PA20260060-14540-bld · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Mifflin, Pennsylvania (construction type: building) is $39.18/hr base + $26.07/hr fringe = $65.25/hr total package (WD PA20260060-14540-bld, Rev. 2).

Scroll down for all 40 trade classifications covered by this determination.

WD Number: PA20260060-14540-bld
Revision: 2
Construction Type: building
State: Pennsylvania (PA)
County: Mifflin
Effective: May 17, 2026
Trades covered: 40
Official source: SAM.gov reference PA20260060View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $39.18 $26.07 $65.25 Above median +176% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $48.28 $33.17 $81.45 Above median +93% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $32.66 $21.58 $54.24 Above median +68% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $34.76 $20.64 $55.40 +95% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $25.71 $12.02 $37.73 +32% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $19.81 $9.03 $28.84 +0% vs market $0.00 $0.00 $0.00 $0.00
DAY AFTER THE HOLIDAY): NEW YEARS'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY AND THE FRIDAY AFTER THANKSGIVING $61.41 $38.44 $99.85 Top 10% $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $39.27 $22.28 $61.55 Above median +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $25.44 $12.35 $37.79 +20% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, EXCLUDES ALARM INSTALLATION, SOUND AND COMMUNICATION INSTALLATION, HVAC/TEMPERATURE CONTROL INSTALLATION, AND LOW VOLTAGE WIRING $26.80 $13.68 $40.48 +29% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $37.26 $32.63 $69.89 Above median +79% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: ORNAMENTAL $34.65 $31.12 $65.77 Above median +68% vs market $0.00 $0.00 $0.00 $0.00
LABORER $26.31 $17.05 $43.36 Above median +86% vs market $0.00 $0.00 $0.00 $0.00
LABORER $21.57 $15.04 $36.61 +57% vs market $0.00 $0.00 $0.00 $0.00
LABORER (FORKLIFT) $25.29 $15.04 $40.33 +73% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $22.29 $15.92 $38.21 Above median +64% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $16.09 $3.44 $19.53 Above median -16% vs market $0.00 $0.00 $0.00 $0.00
MASON - STONE $32.66 $21.58 $54.24 Above median +135% vs market $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $43.00 $23.44 $66.44 Above median +121% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $29.88 $14.13 $44.01 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $26.96 $13.93 $40.89 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $36.53 $22.01 $58.54 Top 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: OILER $37.10 $27.62 $64.72 Top 10% $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER, AND SPRAY $27.95 $16.12 $44.07 Top 10% +82% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $41.36 $29.45 $70.81 Above median +121% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $51.69 $27.07 $78.76 Above median +146% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $41.36 $29.45 $70.81 Above median +121% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $24.31 $3.95 $28.26 -12% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR (FORKLIFT) $41.88 $30.03 $71.91 Top 10% +155% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: CRANE $47.14 $31.58 $78.72 Top 10% +180% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: PAVER $36.87 $21.32 $58.19 Above median +107% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $41.37 $13.28 $54.65 Above median +131% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $36.13 $30.32 $66.45 Above median +100% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER: EXCLUDING HVAC DUCT INSTALLATION FOOTNOTE: PAID HOLIDAY: ELECTION DAY $43.09 $42.52 $85.61 Top 10% +157% vs market $0.00 $0.00 $0.00 $0.00
TERRAZZO FINISHER $33.23 $19.03 $52.26 Above median $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER/GRINDER $33.94 $19.03 $52.97 Top 10% $0.00 $0.00 $0.00 $0.00
TERRAZZO WORKER/SETTER $33.83 $20.78 $54.61 $0.00 $0.00 $0.00 $0.00
TILE FINISHER $28.76 $17.16 $45.92 Above median +62% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $35.64 $21.63 $57.27 Above median +102% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $24.98 $11.88 $36.86 Top 10% +31% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Mifflin, PA — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Mifflin

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for PA20260060-14540-bld →