Building Construction — Cape May, New Jersey

WD NJ20260029-16033-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all typ in Cape May, New Jersey (construction type: building) is $55.80/hr base + $40.80/hr fringe = $96.60/hr total package (WD NJ20260029-16033-bld, Rev. 1).

Scroll down for all 35 trade classifications covered by this determination.

WD Number: NJ20260029-16033-bld
Revision: 1
Construction Type: building
State: New Jersey (NJ)
County: Cape May
Effective: May 17, 2026
Trades covered: 35
Official source: SAM.gov reference NJ20260029View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all typ $55.80 $40.80 $96.60 +260% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER Work on high stacks: 22% per hour additional $45.20 $33.26 $78.46 +117% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $57.42 $34.17 $91.59 Top 10% +208% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter $57.42 $34.17 $91.59 Top 10% +208% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $53.21 $33.42 $86.63 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
DRYWALL FINISHER/TAPER $44.87 $30.15 $75.02 Above median +62% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN : CABLE SPLICER ON LEAD CABLE $46.51 $34.39 $80.90 +130% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN AND CABLE SPLICER $55.05 $48.76 $103.81 Top 10% +195% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: TELEDATA TECHNICIANS: 15 VOICE DATA LINES OR LESS $41.00 $32.75 $73.75 +110% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: TELEDATA TECHNICIANS: 16 VOICE DATA LINES OR MORE AND FIBER OPTICS $41.00 $32.75 $73.75 +110% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of B. Ei $71.85 $38.44 $110.29 +70% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $53.24 $38.40 $91.64 Top 10% +70% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL AND ORNAMENTAL $54.24 $38.40 $92.64 Above median +72% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ASPHALT RAKER, ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN $35.75 $30.22 $65.97 +117% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE $36.50 $30.22 $66.72 Top 10% +120% vs market $0.00 $0.00 $0.00 $0.00
MARBLE SETTER $64.66 $40.97 $105.63 Top 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other $58.84 $35.06 $93.90 Top 10% +175% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $45.55 $29.86 $75.41 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $56.30 $50.76 $107.06 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
PLASTERER $38.37 $31.64 $70.01 Above median +55% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $56.30 $50.76 $107.06 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE; DRILL; ELEVATING GRADER; EXCAVATOR; FRONT E $61.72 $37.50 $99.22 Top 10% +145% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE; HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER; S $60.13 $37.50 $97.63 Top 10% +141% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR; FORKLIFT; FRONT END LOADER; LULL; MAN LIFT/OUTSIDE ELEVATOR; MECHANIC; PAVE $58.22 $37.50 $95.72 +137% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR; FARM TRACTOR; FRONT END LOADER; HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDO $56.59 $37.50 $94.09 Top 10% +132% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER $52.88 $37.50 $90.38 Top 10% +123% vs market $0.00 $0.00 $0.00 $0.00
ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those day $46.03 $34.27 $80.30 +128% vs market $0.00 $0.00 $0.00 $0.00
ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which $35.95 $21.85 $57.80 +64% vs market $0.00 $0.00 $0.00 $0.00
ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those day $38.95 $21.85 $60.80 +72% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $59.08 $47.06 $106.14 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
SOFT FLOOR LAYER $57.42 $34.17 $91.59 Above median +224% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $59.19 $36.51 $95.70 Top 10% +158% vs market $0.00 $0.00 $0.00 $0.00
TERRAZZO FINISHER $43.63 $32.12 $75.75 Top 10% $0.00 $0.00 $0.00 $0.00
TILE SETTER $52.31 $38.01 $90.32 Top 10% +220% vs market $0.00 $0.00 $0.00 $0.00
Work at 30 ft. above the working surface, or on the swing stage: $1.00 per hour additional $49.96 $35.11 $85.07 $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Cape May, NJ — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Cape May

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NJ20260029-16033-bld →