Building Construction — Storey, Nevada

WD NV20260039-17487-bld · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKER/HEAT & FROST INSULATOR in Storey, Nevada (construction type: building) is $52.36/hr base + $26.62/hr fringe = $78.98/hr total package (WD NV20260039-17487-bld, Rev. 2).

Scroll down for all 46 trade classifications covered by this determination.

WD Number: NV20260039-17487-bld
Revision: 2
Construction Type: building
State: Nevada (NV)
County: Storey
Effective: May 17, 2026
Trades covered: 46
Official source: SAM.gov reference NV20260039View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR $52.36 $26.62 $78.98 Above median +165% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $42.85 $17.02 $59.87 Above median +106% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $46.50 $17.92 $64.42 Above median +115% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $43.06 $13.69 $56.75 Above median +95% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $48.50 $23.04 $71.54 Above median +129% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC. FOOTNOTE: A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YE $84.05 $38.44 $122.49 Top 10% +85% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $50.70 $35.15 $85.85 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $50.70 $35.15 $85.85 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: ORNAMENTAL $50.70 $35.15 $85.85 Top 10% +184% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( COMMON OR GENERAL) $33.95 $16.30 $50.25 Top 10% +119% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( CONCRETE SAW, MASON TENDER - BRICK, MASON TENDER - CEMENT/CONCRETE) $34.20 $16.30 $50.50 +120% vs market $0.00 $0.00 $0.00 $0.00
LABORER ( PIPELAYER) $34.45 $16.30 $50.75 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $47.90 $23.89 $71.79 Top 10% +185% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $46.00 $16.21 $62.21 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
PAINTER $39.43 $15.71 $55.14 Above median +119% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $53.38 $27.29 $80.67 Above median +179% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $26.56 $0.00 $26.56 -8% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 01 FORKLIFT - LESS THAN 5 TONS $63.43 $36.40 $99.83 +185% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 02 FORKLIFT - 5 TONS OR MORE $63.57 $36.40 $99.97 +186% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 03 BOBCAT $63.79 $36.40 $100.19 +186% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 04 $63.90 $36.40 $100.30 Top 10% +187% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 05 PEDESTAL CRANE $64.02 $36.40 $100.42 +187% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 06 $64.19 $36.40 $100.59 Top 10% +187% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 07 HOIST - STIFF LEGS, GUY DERRICK, OR SIMILAR, 25 TONS TO 50 TONS; K-CRANE; POLAR CRANE; SELF-ERECTING TOWER CRANE - 1 $64.36 $36.40 $100.76 +188% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 08 $64.52 $36.40 $100.92 Top 10% +188% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 09 OILER - OVER 200 TONS $65.20 $36.40 $101.60 +190% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 10 $65.36 $36.40 $101.76 Top 10% +191% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 12 $65.99 $36.40 $102.39 Top 10% +193% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 15 HOIST - STIFF LEGS, GUY DERRICK, OR SIMILAR, 200 TONS TO 300 TONS.$ 67.36 36.40 POWER EQUIPMENT OPERATOR GROUP 13 HO $65.99 $36.40 $102.39 +193% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 16 $67.41 $36.40 $103.81 Top 10% +197% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 17 CRANE - 80 TONS TO 150 TONS $67.91 $36.40 $104.31 +198% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 18 TOWER CRANE; HOIST - STIFF LEGS, GUY DERRICK, OR SIMILAR, GREATER THAN 300 TONS $68.36 $36.40 $104.76 +199% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 19 CRANE - 150 TONS TO 200 TONS $69.94 $36.40 $106.34 +204% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 20 CRANE - 200 TONS TO 250 TONS $70.55 $36.40 $106.95 +206% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 21 CRANE - 250 TONS TO 300 TONS $71.16 $36.40 $107.56 +207% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 22 CRANE - 300 TONS TO 350 TONS $71.92 $36.40 $108.32 +210% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 23 CRANE - OVER 350 TONS $72.38 $36.40 $108.78 +211% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR, LOADER: GROUP 08 UP TO AND INCLUDING 2.5 CY $49.61 $30.38 $79.99 +129% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR, LOADER: GROUP 10 OVER 2.5 CY, UP TO AND INCLUDING 4 CY $50.28 $30.38 $80.66 +131% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR, LOADER: GROUP 11 OVER 4 CY, UP TO AND INCLUDING 12 CY $50.71 $30.38 $81.09 +132% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR, LOADER: GROUP 11A OVER 12 CY $52.35 $30.38 $82.73 +136% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $49.65 $22.19 $71.84 Top 10% +204% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $47.51 $29.38 $76.89 Above median +236% vs market $0.00 $0.00 $0.00 $0.00
TILE FINISHER $31.05 $12.82 $43.87 +57% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $37.86 $15.96 $53.82 Above median +92% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $37.21 $33.41 $70.62 Top 10% +141% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Storey, NV — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Storey

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for NV20260039-17487-bld →