Heavy Construction — Clark, Nevada
WD NV20260024-16025-hvy · Revision 2 · Effective May 17, 2026
The Davis-Bacon prevailing wage for BRICKLAYER in Clark, Nevada (construction type: heavy) is $27.36/hr base + $0.00/hr fringe = $27.36/hr total package (WD NV20260024-16025-hvy, Rev. 2).
Scroll down for all 40 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BRICKLAYER | $27.36 | $0.00 | $27.36 -6% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDES FORM WORK | $31.78 | $16.03 | $47.81 Top 10% +60% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $52.29 | $19.79 | $72.08 Top 10% +148% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $58.48 | $27.62 | $86.10 Top 10% +176% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $50.70 | $35.15 | $85.85 Top 10% +184% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $46.20 | $34.30 | $80.50 Top 10% +166% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( ASPHALT RAKER; PIPELAYER) | $30.55 | $15.02 | $45.57 +98% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( ASPHALT SHOVELER, SPREADER AND DISTRIBUTOR) | $30.30 | $15.02 | $45.32 +97% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( COMMON OR GENERAL) | $38.53 | $33.41 | $71.94 Top 10% +213% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( CONES/ BARRICADES/ BARRELS-SETTER/MOVER/SWEEPER) | $30.05 | $15.02 | $45.07 +96% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( FLAGGER) | $27.18 | $15.02 | $42.20 +84% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( MASON TENDER-CEMENT/CONCRETE; CONCRETE SAW) | $38.84 | $33.41 | $72.25 +215% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LINE CONSTRUCTION, HEAVY EQUIPMENT OPERATOR ZONE PAY - NNSS $5.00 NTTR $5.00 | $43.04 | $19.51 | $62.55 Bottom 10% +8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LINE CONSTRUCTION: GROUNDMAN | $38.74 | $19.36 | $58.10 Above median +0% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LINE CONSTRUCTION: LINEMAN | $55.77 | $19.95 | $75.72 +31% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $29.93 | $0.00 | $29.93 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BROOM/SWEEPER | $36.66 | $12.22 | $48.88 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER | $28.99 | $0.00 | $28.99 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $27.35 | $0.00 | $27.35 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER/PIPEFITTER | $60.00 | $26.80 | $86.80 Top 10% +200% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR GROUP 10 GRADER/BLADE | $64.02 | $36.40 | $100.42 +187% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR GROUP 12 VERMEER ROCK TRENCHER | $64.19 | $36.40 | $100.59 +187% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, BACKHOE/EXCAVATOR/TRACKHOE: GROUP 10 BACKHOE OPERATOR | $64.02 | $36.40 | $100.42 +187% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, BACKHOE/EXCAVATOR/TRACKHOE: GROUP 12 BACKHOE OPERATOR; EXCAVATOR TRACK/RUBBER-TIRED | $64.19 | $36.40 | $100.59 +187% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, BACKHOE/EXCAVATOR/TRACKHOE: GROUP 16 EXCAVATOR TRACK/RUBBER-TIRED | $64.52 | $36.40 | $100.92 +188% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, BACKHOE/EXCAVATOR/TRACKHOE: GROUP 4 BACKHOE OPERATOR; EXCAVATOR TRACK/RUBBER-TIRED | $63.57 | $36.40 | $99.97 +186% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, BACKHOE/EXCAVATOR/TRACKHOE: GROUP 8 BACKHOE OPERATOR;; EXCAVATOR TRACK/RUBBER-TIRED | $64.29 | $36.40 | $100.69 +188% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 12 CRANE OPERATOR | $65.99 | $36.40 | $102.39 Top 10% +193% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 16 CRANE OPERATOR | $67.41 | $36.40 | $103.81 Top 10% +197% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 17 CRANE OPERATOR | $67.91 | $36.40 | $104.31 Top 10% +198% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 19 CRANE OPERATOR | $69.94 | $36.40 | $106.34 Top 10% +204% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 20 CRANE OPERATOR | $70.55 | $36.40 | $106.95 Top 10% +206% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 21 CRANE OPERATOR | $71.16 | $36.40 | $107.56 Top 10% +207% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 22 CRANE OPERATOR | $71.92 | $36.40 | $108.32 Top 10% +210% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, CRANE: GROUP 23 CRANE OPERATOR | $72.38 | $36.40 | $108.78 Top 10% +211% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 01 Oiler | $60.84 | $36.40 | $97.24 +178% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 04 Greaser; Screed Operator; Rock Wheel Saw/Trencher | $63.57 | $36.40 | $99.97 +186% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 06 Heavy Duty Repairman/Mechanic | $63.79 | $36.40 | $100.19 +186% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 08 Loader Operator; Compactor; Drilling Machine Operator, Bucket or Auger Types; Grade Checker; Tractor Operator; Rubb | $63.90 | $36.40 | $100.30 +187% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $22.43 | $0.00 | $22.43 Above median -23% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Clark, NV — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Clark
Compliance Notes
- This wage determination applies to federal contracts for heavy construction in Clark, Nevada.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.