Heavy Construction — Missoula, Montana
WD MT20260067-17853-hvy · Revision 2 · Effective May 17, 2026
The Davis-Bacon prevailing wage for 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 in Missoula, Montana (construction type: heavy) is $42.23/hr base + $16.20/hr fringe = $58.43/hr total package (WD MT20260067-17853-hvy, Rev. 2).
Scroll down for all 20 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $42.23 | $16.20 | $58.43 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $41.15 | $16.20 | $57.35 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $23.47 | $10.40 | $33.87 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $38.75 | $32.31 | $71.06 +78% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER. ZONE DEFINITION: THE HOURLY RATE APPLICABLE TO EACH PROJECT IS DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL ROUTE FRO | $36.49 | $14.33 | $50.82 +82% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $40.71 | $17.94 | $58.65 +77% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: REINFORCING AND STRUCTURAL | $32.08 | $29.06 | $61.14 Above median +127% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $16.91 | $9.08 | $25.99 Above median +10% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ASPHALT ROLLER | $22.39 | $3.96 | $26.35 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE | $22.12 | $8.37 | $30.49 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $25.67 | $8.05 | $33.72 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $22.67 | $6.54 | $29.21 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH AND SPRAY | $25.00 | $0.00 | $25.00 +6% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $39.38 | $16.23 | $55.61 Above median +48% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ZONE 1: EXCAVATOR, CRANE OILER. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJ | $23.94 | $10.40 | $34.34 +19% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ZONE 1: MECHANIC, SCRAPER. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT S | $24.34 | $10.40 | $34.74 Top 10% +20% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ZONE 1:CRANES, 25-44 TONS. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT S | $38.98 | $16.20 | $55.18 +91% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: ZONE 1:CRANES, 45-74 TONS. ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT S | $40.07 | $16.20 | $56.27 +95% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER WATER TRUCK ZONE A. ZONE B: ADD $3.05 PER HOUR TO ZONE A RATES ZONE C: ADD $4.85 PER HOUR TO ZONE A RATES. *ZONE PAY WILL BE CALCULATED F | $32.88 | $13.98 | $46.86 +65% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $19.38 | $4.74 | $24.12 Above median -15% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Missoula, MT — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Missoula
Compliance Notes
- This wage determination applies to federal contracts for heavy construction in Missoula, Montana.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.