Building Construction — Rock, Minnesota
WD MN20260093-15600-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for ARTICULATED HAULER in Rock, Minnesota (construction type: building) is $18.00/hr base + $5.00/hr fringe = $23.00/hr total package (WD MN20260093-15600-bld, Rev. 1).
Scroll down for all 45 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ARTICULATED HAULER | $18.00 | $5.00 | $23.00 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| ASBESTOS ABATEMENT WORKER | $41.23 | $25.99 | $67.22 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $20.13 | $0.44 | $20.57 Bottom 10% -58% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $30.54 | $20.77 | $51.31 +20% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $33.14 | $27.60 | $60.74 Above median +95% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPET LAYER | $28.55 | $14.03 | $42.58 +8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON | $34.06 | $24.15 | $58.21 Above median +90% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| DRUMS); MECHANIC; POWER PLANT; PUMP OPERATOR AND/OR CONVEYOR; SELF-ERECTING TOWER CRANE UNDER 100 FEET MEASURED FROM BOOM FOOT PIN; STRADDLE CARRIER | $44.54 | $26.88 | $71.42 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL TAPER | $27.71 | $15.68 | $43.39 +45% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $35.00 | $5.03 | $40.03 +2% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELEVATOR CONSTRUCTORS | $62.52 | $45.36 | $107.88 Top 10% +91% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $37.74 | $12.96 | $50.70 +57% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| HEATING AND FROST INSULATORS | $57.24 | $31.95 | $89.19 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $46.00 | $34.11 | $80.11 Above median +79% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $32.97 | $24.46 | $57.43 Top 10% +103% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LANDSCAPE | $11.13 | $0.00 | $11.13 -61% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: SKILLED | $32.97 | $24.46 | $57.43 Bottom 10% +103% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LANDSCAPING EQUIPMENT (INCLUDES HYDRO SEEDER OR MULCHER, SOD ROLLER, FARM TRACTOR WITH ATTACHMENT SPECIFICLLY SEEDING, SODDING, OR PLANT, AND TWO-FRAM | $16.25 | $0.00 | $16.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| METERS/164 FEET OF BOOM AND OVER; PILE DRIVING WHEN THREE DRUMS IN USE; TRUCK OR CRAWLER CRANE WITH 150 FEET OF BOOM UP TO AND NOT INCLUDING 200 FEET | $48.53 | $26.88 | $75.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| MILLWRIGHT | $41.66 | $35.40 | $77.06 Above median +131% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $36.33 | $24.83 | $61.16 Top 10% +109% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PILEDRIVER | $49.46 | $30.23 | $79.69 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER/STEAMFITTER | $41.00 | $14.42 | $55.42 +38% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPELAYER | $42.51 | $26.01 | $68.52 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $44.12 | $27.17 | $71.29 Above median +78% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 1: HELICOPTER PILOT; TOWER CRANE 250 FEET AND OVER; TRUCK CRAWLER CRANE WITH 200 FEET OF BOOM AND OVER, INC | $48.89 | $26.88 | $75.77 Above median +101% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 3: ALL-TERRAIN VEHICLE CRANES; CONCRETE PUMP 32-49 METERS/102-164 FEET; DERRICK; SELF-ERECTING TOWER CRANE | $47.02 | $26.88 | $73.90 +96% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 4: CRAWLER BACKHOE INCLUDING ATTACHMENTS; FIREPERSON, CHIEF BOILER LICENSE; HOIST ENGINEER; LOCOMOTIVE; OVE | $36.18 | $19.45 | $55.63 +47% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: COMMERCIAL GROUP 6: CONCRETE BATCH PLANT; FIREPERSON, FIRST CLASS BOILER LICENSE; FRONT END, SKID STEER UP TO 1 C YD; GUNITE | $42.94 | $26.40 | $69.34 +84% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 2: GRADER OR MOTOR PATROL; TUGBOAT 100 H.P. AND OVER WHEN LICENSE REQUIRED | $39.74 | $21.55 | $61.29 Above median +62% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 3: ASPHALT BITUMINOUS STABILIZER PLANT; CABLEWAY; DERRICK; DREDGE OR ENGINEERS, DREDGE AND ENGINEER; LOC | $27.50 | $3.50 | $31.00 Bottom 10% -18% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 4: AIR TRACK ROCK DRILL; AUTOMATIC ROAD MACHINE; BACKFILLER OPERATOR; BITUMINOUS ROLLERS, RUBBER TIRED O | $31.16 | $23.45 | $54.61 Above median +45% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: HIGHWAY/HEAVY GROUP 5: BITUMINOUS ROLLER; CONCRETE SAW; FORM TRENCH DIGGER; HYDRAULIC LOG SPLITTER; LOADER; POST HOLE DRIVIN | $35.85 | $21.55 | $57.40 Above median +52% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PUMP/PUMPCRETE OR COMPLACO TYPE; FIREPERSON, TEMPORARY HEAT SECOND CLASS BOILER LICENSE; OILER; PICK UP SWEEPER; PUMP AND/OR CONVEYOR | $41.73 | $26.88 | $68.61 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $43.30 | $22.90 | $66.20 Above median +77% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $30.00 | $7.40 | $37.40 +24% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SIGN ERECTOR | $37.19 | $19.88 | $57.07 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $41.54 | $21.29 | $62.83 +57% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TERRAZZO WORKER | $43.73 | $20.73 | $64.46 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 1: MECHANIC; TRACTOR TRAILER DRIVER; TRUCK DRIVER | $24.00 | $6.50 | $30.50 +4% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 2: FOUR OR MORE AXLE UNIT, STRAIGHT BODY TRUCK | $20.96 | $5.38 | $26.34 -10% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: GROUP 3: BITUMINOUS DISTRIBUTOR DRIVER; BITUMINOUS DISTRIBUTOR; THREE AXLE UNITS | $17.00 | $5.00 | $22.00 Bottom 10% -25% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| UNDERGROUND AND OPEN DITCH LABORER | $22.09 | $14.90 | $36.99 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEM TECHNICIAN | $36.00 | $4.32 | $40.32 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| WIRING SYSTEMS INSTALLER | $44.61 | $20.17 | $64.78 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Rock, MN — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Rock
Compliance Notes
- This wage determination applies to federal contracts for building construction in Rock, Minnesota.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.