Heavy Construction — Calhoun, Michigan
WD MI20260053-15490-hvy · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER in Calhoun, Michigan (construction type: heavy) is $29.93/hr base + $9.10/hr fringe = $39.03/hr total package (WD MI20260053-15490-hvy, Rev. 1).
Scroll down for all 29 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER | $29.93 | $9.10 | $39.03 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER, INCLUDES FORM WORK | $28.29 | $21.42 | $49.71 Top 10% +68% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $22.31 | $12.83 | $35.14 Above median +24% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $41.00 | $25.74 | $66.74 Above median +91% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: REINFORCING | $36.55 | $34.04 | $70.59 Top 10% +130% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: STRUCTURAL | $36.55 | $34.04 | $70.59 Above median +130% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER | $27.21 | $13.45 | $40.66 Above median +74% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( COMMON OR GENERAL) | $22.42 | $12.95 | $35.37 Above median +51% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( GRADE CHECKER) | $22.73 | $12.55 | $35.28 +51% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( LANDSCAPER) | $18.41 | $12.95 | $31.36 +34% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( MASON TENDER-CEMENT/CONCRETE) | $22.55 | $12.95 | $35.50 Above median +52% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER ( PIPELAYER) | $22.85 | $12.95 | $35.80 +53% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER | $27.71 | $9.10 | $36.81 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $25.26 | $5.00 | $30.26 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 1 BACKHOE/EXCAVATOR; BORING MACHINE; BULLDOZER; GRADER/BLADE; LOADER; ROLLER; SCRA | $44.00 | $25.25 | $69.25 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 2 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK PAID HOLIDAYS: NEW YEAR'S DAY, MEM | $41.32 | $25.25 | $66.57 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 3 BOOM TRUCK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DA | $41.32 | $25.25 | $66.57 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 4 FORK TRUCK PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DA | $35.46 | $25.25 | $60.71 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH & ROLLER | $21.75 | $11.94 | $33.69 +42% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: SPRAY | $22.75 | $11.94 | $34.69 +46% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $38.79 | $23.08 | $61.87 Above median +67% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION: GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, GRADER/ BLADE, LOADER, ROLLER, SCRAPER, TRE | $45.98 | $25.25 | $71.23 +137% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION: GROUP 2 TRENCHER | $41.25 | $25.25 | $66.50 Top 10% +121% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR, UNDERGROUND CONSTRUCTION: GROUP 3 BOOM TRUCK | $40.52 | $25.25 | $65.77 +119% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: Underground Construction- GROUP 4 : BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER | $39.95 | $25.25 | $65.20 +117% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $18.00 | $6.43 | $24.43 Above median -8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | $33.55 | $0.75 | $34.30 Top 10% +29% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | $20.82 | $3.69 | $24.51 Above median -8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY | $33.30 | $0.75 | $34.05 +28% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Calhoun, MI — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Calhoun
Compliance Notes
- This wage determination applies to federal contracts for heavy construction in Calhoun, Michigan.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.