Residential Construction — Dukes, Massachusetts

WD MA20260009-15432-res · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BOILERMAKER in Dukes, Massachusetts (construction type: residential) is $50.62/hr base + $28.82/hr fringe = $79.44/hr total package (WD MA20260009-15432-res, Rev. 1).

Scroll down for all 47 trade classifications covered by this determination.

WD Number: MA20260009-15432-res
Revision: 1
Construction Type: residential
State: Massachusetts (MA)
County: Dukes
Effective: May 17, 2026
Trades covered: 47
Official source: SAM.gov reference MA20260009View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $50.62 $28.82 $79.44 Above median $0.00 $0.00 $0.00 $0.00
BRICKLAYER, CEMENT MASON, PLASTERER $64.50 $37.54 $102.04 +125% vs market $0.00 $0.00 $0.00 $0.00
CARPENTERS $50.10 $31.45 $81.55 Top 10% +139% vs market $0.00 $0.00 $0.00 $0.00
CARPENTRY WORK ON WOOD FRAME PROJECTS $26.55 $13.02 $39.57 $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.14 $37.35 $78.49 Top 10% $0.00 $0.00 $0.00 $0.00
DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 Y $41.02 $37.35 $78.37 Bottom 10% $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $50.02 $31.05 $81.07 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE FOR ELEVATOR MECHANICS: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BAS $74.17 $38.44 $112.61 Top 10% +74% vs market $0.00 $0.00 $0.00 $0.00
FLOOR LAYER: CARPET $49.18 $31.75 $80.93 Top 10% +162% vs market $0.00 $0.00 $0.00 $0.00
FRAMING, SIDING AND EXTERIOR TRIM WORK $26.55 $13.02 $39.57 $0.00 $0.00 $0.00 $0.00
GLAZIER FOOTNOTE: A. PAID HOLIDAY: LABOR DAY, PROVIDED EMPLOYEE HAS WORKED ANY PART OF THE WEEK PRIOR TO LABOR DAY AND PART OF THE WEEK AFTER LABOR DA $43.13 $21.00 $64.13 +31% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER $43.03 $33.53 $76.56 Above median +37% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2 JACKHAMMER OPERATOR; PAVEMENT BREAKER; ASPHAL RAKER CARBIDE CORE DRILLING MACHINE; CHAIN SAW OPERTOR; PIPELAYER; BARCO TYPE JUMPING $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3 AIR TRACK, BLOCK PAVER; RUMMER; CURB SETTER; HYDRAULIC AND SIMILAR SELF POWERED DRILLS $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4 BLASTER; POWDERMAN $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5 PRE-CAST FLOOR AND ROOF PLANK ERECTOR $38.95 $29.70 $68.65 +129% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 6 ASBESTOS REMOVAL LABORERS $46.10 $29.70 $75.80 +152% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 7 FLAGGERS $27.01 $29.70 $56.71 +89% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 1 ADZEMAN, WRECKING LABORER $46.25 $29.70 $75.95 Top 10% +153% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 2 BURNERS, JACKHAMMERS $47.00 $29.70 $76.70 Top 10% +155% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 3 SMALL BACKHOES, LOADERS ON TRACKS, BOBCAT TYPE LOADERS, HYDRAULIC ""BROCK"" TYPE HAMMER OPERATORS, CONCRETE CUTTING SAWS $47.25 $29.70 $76.95 Top 10% +156% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 4 YARDMAN $42.25 $29.70 $71.95 Top 10% +140% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 5 YARDMAN, BURNERS, SAWYERS $45.35 $29.70 $75.05 Top 10% +150% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, WRECKING: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE $46.25 $29.70 $75.95 Top 10% +153% vs market $0.00 $0.00 $0.00 $0.00
MARBLE & TILE FINISHER $49.32 $35.26 $84.58 Top 10% $0.00 $0.00 $0.00 $0.00
MARBLE, TILE & TERRAZZO WORKERS $64.52 $37.51 $102.03 Top 10% $0.00 $0.00 $0.00 $0.00
NANTUCKET; PLYMOUTH) $49.70 $29.75 $79.45 Bottom 10% $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.29 OVER 350 FT. +13.14 $30.85 $33.70 $64.55 $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.29 OVER 350 FT. +13.14 $46.52 $33.70 $80.22 $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.29 OVER 350 FT. +13.14 $37.02 $33.70 $70.72 $0.00 $0.00 $0.00 $0.00
OVER 295 FT. +11.29 OVER 350 FT. +13.14 $57.83 $33.70 $91.53 $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH, TAPER $44.32 $36.00 $80.32 +199% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH, TAPER $46.26 $36.00 $82.26 +206% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY, SANDBLAST $45.72 $36.00 $81.72 Top 10% +204% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY, SANDBLAST $47.66 $36.00 $83.66 Top 10% +211% vs market $0.00 $0.00 $0.00 $0.00
PLUMBERS AND PIPEFITTERS $52.49 $33.60 $86.09 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 OILER FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON,S BIRTHDAY, LABOR DAY, M $25.02 $33.70 $58.72 +68% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: OOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON,S BIRTHDAY, LABOR DAY, MEMORIAL DAY, IN $57.18 $33.70 $90.88 +160% vs market $0.00 $0.00 $0.00 $0.00
ROOFERS $53.53 $35.69 $89.22 Top 10% +156% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $49.70 $29.75 $79.45 Above median +98% vs market $0.00 $0.00 $0.00 $0.00
TERRAZZO FINISHER $63.44 $37.33 $100.77 Top 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $40.78 $37.35 $78.13 Top 10% +168% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS $40.95 $37.35 $78.30 Top 10% +169% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 5 SPECIALIZED EARTH MOVING EQUIPMENT UNDER 35 TONS OTHER THAN CONVENTIONAL TYPE TRUCKS; LOW BED; VACHUAL; MECHANICS, PAVING RESTO $41.24 $37.35 $78.59 Top 10% +170% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HA $41.53 $37.35 $78.88 Top 10% +171% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATE $41.82 $37.35 $79.17 Top 10% +172% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Dukes, MA — Residential construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Dukes

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for MA20260009-15432-res →