WD ID20260021-17229-bld · Revision 2 · Effective May 17, 2026
The Davis-Bacon prevailing wage for BRICKLAYER in Teton, Idaho (construction type: building) is $26.79/hr base + $17.34/hr fringe = $44.13/hr total package (WD ID20260021-17229-bld, Rev. 2).
Scroll down for all 22 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BRICKLAYER | $26.79 | $17.34 | $44.13 +46% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $14.76 | $2.80 | $17.56 -25% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $40.00 | $18.74 | $58.74 +101% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| INSULATOR - MECHANICAL | $20.13 | $1.80 | $21.93 Above median +10% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $33.37 | $22.98 | $56.35 Above median +88% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GROUP 1 COMMON OR GENERAL | $32.62 | $16.50 | $49.12 +125% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GROUP 4 MASON TENDER - CEMENT/CONCRETE | $33.93 | $16.50 | $50.43 +131% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $16.12 | $0.00 | $16.12 Above median -28% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $36.75 | $18.93 | $55.68 Above median +102% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 3 FORKLIFT ZONE 1 ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE | $36.33 | $16.10 | $52.43 Top 10% +84% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 5 BACKHOE, INDUSTRIAL OILER ZONE 1 ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 | $36.81 | $16.10 | $52.91 Top 10% +86% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 6 BACKHOE, CRANE ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MILES: FREE ZONE | $36.98 | $16.10 | $53.08 Top 10% +87% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 | $35.68 | $18.24 | $53.92 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $29.02 | $19.90 | $48.92 Above median +111% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $26.80 | $12.00 | $38.80 +41% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SUPPLIED AIR SHALL RECEIVE $1.00 PER HOUR ABOVE CLASSIFICATION) ZONE PAY: ZONE CENTERS: BOISE, TWIN FALLS, POCATELLO, AND IDAHO FALLS ZONE 1 0 - 30 MI | $37.35 | $16.10 | $53.45 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5A DUMP | $35.60 | $17.00 | $52.60 Top 10% +105% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5B DUMP | $35.78 | $17.00 | $52.78 Top 10% +106% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5C DUMP | $36.01 | $17.00 | $53.01 Top 10% +107% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5D DUMP | $36.12 | $17.00 | $53.12 Top 10% +107% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5E DUMP | $36.75 | $17.00 | $53.75 Top 10% +110% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER, GROUP 5F DUMP | $37.19 | $17.00 | $54.19 Top 10% +112% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Teton, ID — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Teton
Compliance Notes
- This wage determination applies to federal contracts for building construction in Teton, Idaho.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.