Wage Determination WV20260108-17698-hwy
Jackson, WV · highway · Rev. 1 · Effective May 17, 2026
Quick Answer
Wage determination WV20260108-17698-hwy covers 27 trade classifications for highway construction in Jackson, WV. Total packages (base + fringe) range from $42.89/hr to $60.65/hr, with the highest going to OPERATOR: CRANE. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: WV20260108-17698-hwy
Revision: 1
Type: highway
County: Jackson
State: WV
Effective: May 17, 2026
Trades covered: 27
Highest rate: $60.65/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| CARPENTER | $27.72 | $19.44 | $47.16 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $28.67 | $18.85 | $47.52 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $34.87 | $19.50 | $54.37 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $29.00 | $17.40 | $46.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $29.00 | $17.40 | $46.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GRADE CHECKER | $29.00 | $17.40 | $46.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GUARDRAIL INSTALLATION | $29.00 | $17.40 | $46.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: LASER SCREED OPERATOR | $30.03 | $17.40 | $47.43 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $26.59 | $16.30 | $42.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $29.00 | $17.40 | $46.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BROOM/SWEEPER | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $40.35 | $20.30 | $60.65 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: DRILL | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: FORKLIFT | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER (UP TO SIX CUBIC YARD CAPACITY) | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MECHANIC | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MILLING MACHINE | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER/SPREADER/FINISH EQUIPMENT | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: POST DRIVER | $37.59 | $20.30 | $57.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $29.38 | $18.60 | $47.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRAFFIC CONTROL PERSON | $27.91 | $17.40 | $45.31 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRAFFIC SIGNALIZATION: GROUNDSMAN | $22.12 | $26.26 | $48.38 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $29.04 | $16.15 | $45.19 | $0.00 | $0.00 | $0.00 | $0.00 |