Wage Determination VA20260170-16912-bld
Prince George, VA · building · Rev. 1 · Effective May 17, 2026
Quick Answer
Wage determination VA20260170-16912-bld covers 33 trade classifications for building construction in Prince George, VA. Total packages (base + fringe) range from $12.52/hr to $89.83/hr, with the highest going to CREDIT. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: VA20260170-16912-bld
Revision: 1
Type: building
County: Prince George
State: VA
Effective: May 17, 2026
Trades covered: 33
Highest rate: $89.83/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DA | $40.77 | $20.17 | $60.94 | $0.00 | $0.00 | $0.00 | $0.00 |
| BOILERMAKER | $38.97 | $27.39 | $66.36 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $20.00 | $1.00 | $21.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $21.10 | $1.11 | $22.21 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $17.23 | $0.00 | $17.23 | $0.00 | $0.00 | $0.00 | $0.00 |
| CREDIT | $51.39 | $38.44 | $89.83 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $37.95 | $18.02 | $55.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| GLAZIER | $18.43 | $3.71 | $22.14 | $0.00 | $0.00 | $0.00 | $0.00 |
| HVAC MECHANIC | $20.60 | $2.93 | $23.53 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $27.18 | $4.13 | $31.31 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: STRUCTURAL AND ORNAMENTAL | $31.00 | $18.28 | $49.28 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $11.53 | $0.99 | $12.52 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - BRICK | $13.41 | $3.15 | $16.56 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $12.96 | $3.12 | $16.08 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $12.28 | $1.96 | $14.24 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $19.74 | $1.43 | $21.17 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $18.95 | $4.03 | $22.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER | $17.50 | $0.00 | $17.50 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: FORKLIFT | $19.40 | $7.00 | $26.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $21.28 | $3.17 | $24.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $16.25 | $4.88 | $21.13 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $16.87 | $0.00 | $16.87 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: SPRAY | $16.58 | $0.00 | $16.58 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $33.25 | $19.47 | $52.72 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $33.25 | $19.47 | $52.72 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR | $39.99 | $18.05 | $58.04 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR | $40.99 | $18.05 | $59.04 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 19.72 1.83 ROOFER | $17.40 | $1.55 | $18.95 | $0.00 | $0.00 | $0.00 | $0.00 |
| SPRINKLER FITTER | $20.50 | $2.93 | $23.43 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE FINISHER | $23.40 | $0.00 | $23.40 | $0.00 | $0.00 | $0.00 | $0.00 |
| TILE SETTER | $27.80 | $10.25 | $38.05 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $14.88 | $0.00 | $14.88 | $0.00 | $0.00 | $0.00 | $0.00 |
| WATERPROOFER | $21.17 | $3.41 | $24.58 | $0.00 | $0.00 | $0.00 | $0.00 |