Wage Determination VA20260008-15418-bld

Page, VA · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination VA20260008-15418-bld covers 11 trade classifications for building construction in Page, VA. Total packages (base + fringe) range from $11.50/hr to $60.94/hr, with the highest going to ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DA. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: VA20260008-15418-bld
Revision: 1
Type: building
County: Page
State: VA
Effective: May 17, 2026
Trades covered: 11
Highest rate: $60.94/hr
Official source: SAM.gov reference VA20260008View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL A. PAID HOLIDAYS: NEW YEAR'S DAY, MARTIN LUTHER KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DA $40.77 $20.17 $60.94 $0.00 $0.00 $0.00 $0.00
CARPENTER $16.59 $1.73 $18.32 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $19.75 $0.00 $19.75 $0.00 $0.00 $0.00 $0.00
GLAZIER $14.91 $0.00 $14.91 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $11.29 $2.08 $13.37 $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $11.00 $0.50 $11.50 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $21.47 $7.19 $28.66 $0.00 $0.00 $0.00 $0.00
PLUMBER $18.45 $3.05 $21.50 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: BULLDOZER $38.79 $18.05 $56.84 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION.$ 22.33 7.94 ROOFER $15.56 $3.06 $18.62 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $11.25 $0.57 $11.82 $0.00 $0.00 $0.00 $0.00