BOILERMAKER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, THANKSGIVING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY AND GOOD FRIDAY, FRIDAY AFTER THAN
|
$68.88 |
$49.83 |
$118.71 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER
|
$52.32 |
$36.25 |
$88.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER, CEMENT MASON, PLASTERER & STONEMASON: BRICKLAYERS, CEMENT MASONS, PLASTERERS, STONE MASONS
|
$46.39 |
$37.45 |
$83.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER
|
$44.69 |
$38.17 |
$82.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTERS
|
$50.12 |
$31.73 |
$81.85 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER
|
$75.46 |
$55.84 |
$131.30 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DIVER TENDER
|
$55.00 |
$55.84 |
$110.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DOCK BUILDER & PILEDRIVERMEN
|
$60.59 |
$55.84 |
$116.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S
|
$51.50 |
$42.22 |
$93.72 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO
|
$40.81 |
$6.99 |
$47.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA
|
$20.53 |
$6.39 |
$26.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE
|
$38.73 |
$6.93 |
$45.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION-LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE TRAFFIC SIGNAL SYSTEMS, AND TRAFF
|
$43.35 |
$30.73 |
$74.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION-LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE TRAFFIC SIGNAL SYSTEMS, AND TRAFF
|
$54.19 |
$35.69 |
$89.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION-LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE TRAFFIC SIGNAL SYSTEMS, AND TRAFF
|
$48.77 |
$31.31 |
$80.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION-LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR THE TRAFFIC SIGNAL SYSTEMS, AND TRAFF
|
$32.51 |
$29.93 |
$62.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER
|
$63.14 |
$33.82 |
$96.96 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid
|
$64.59 |
$42.92 |
$107.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RA
|
$76.12 |
$38.98 |
$115.10 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
HAZARDOUS MATERIAL HANDLER
|
$46.62 |
$49.30 |
$95.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
INSULATOR/ASBESTOS WORKER
|
$46.62 |
$49.30 |
$95.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER A) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY
|
$42.63 |
$53.70 |
$96.33 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER
|
$44.05 |
$32.40 |
$76.45 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 1 BLASTERS. FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY, I
|
$52.11 |
$28.98 |
$81.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 2 BURNER, JUMBO DRILLER, JOY DRILLER, WAGON DRILLER, AIR TRACK DRILLER, HYDRAULIC DRILLER, CONCRETE FORM ALIGNER, CONCRETE FORM
|
$50.71 |
$28.98 |
$79.69 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 3 ASPHALT CURB MACHINE OPERATOR, JEEPER OPERATOR, PAVEMENT BREAKER OPERATOR, POWER SAW OPERATOR, JACK HAMMER DRILLER. ALL TYPES
|
$50.29 |
$28.98 |
$79.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 4 GENERAL CONCRETE LABORERS-ANYTHING PERTAINING TO CONCRETE, AGGREGATE OR CONCRETE MATERIAL HANDLING, PUDDLERS, ASPHALT WORKER
|
$49.93 |
$28.98 |
$78.91 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 5 COMMON LABORERS, SIGNAL PERSON AND PIT PERSON , TRUCK SPOTTERS, POWDER PERSON, LANDSCAPE AND NURSERY PERSON, DUMP PERSON. FOO
|
$49.56 |
$28.98 |
$78.54 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 6 FLAGPERSON FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, MEMORIAL DAY
|
$42.96 |
$28.98 |
$71.94 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HEAVY: GROUP 7 ASBESTOS AND TOXIC WASTE LABORER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD
|
$51.64 |
$28.98 |
$80.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY: GROUP 1 FLAGPERSON, PLACING AND MAINTENANCE OF ALL FLARES, CONES, LIGHTS, SIGNS, BARRICADES, TRAFFIC PATTERNS, AND ALL REFLECTIVE T
|
$36.45 |
$27.80 |
$64.25 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY: GROUP 2 GENERAL LABORERS, DUMPMAN, PITMAN, CONCRETE MAN, SIGNAL MAN, PIPELAYER, RIP RAP, DRY STONE LAYER, JACK HAMMER, POWDERMAN, H
|
$42.80 |
$27.80 |
$70.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY: GROUP 3 ASPHALT RAKER, ASPHALT SCREEMAN, DRILLERS, LASER BEAM OPERATOR, FORM SETTER/ALIGNERS, BLASTERS, LEAD MAN, TUNNEL & CAISSON
|
$43.90 |
$27.80 |
$71.70 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MARBLE FINISHER
|
$49.99 |
$37.54 |
$87.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MARBLE MASON
|
$63.92 |
$40.20 |
$104.12 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MILLWRIGHT
|
$60.83 |
$58.03 |
$118.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$48.63 |
$38.93 |
$87.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$50.26 |
$38.93 |
$89.19 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$50.51 |
$38.93 |
$89.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$49.88 |
$38.93 |
$88.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$50.38 |
$38.93 |
$89.31 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$50.01 |
$38.93 |
$88.94 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$49.26 |
$38.93 |
$88.19 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$49.13 |
$38.93 |
$88.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$48.96 |
$38.93 |
$87.89 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$48.51 |
$38.93 |
$87.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND
|
$51.26 |
$38.93 |
$90.19 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER
|
$47.75 |
$44.11 |
$91.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER
|
$44.75 |
$44.11 |
$88.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTER
|
$49.20 |
$57.20 |
$106.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER AND STEAMFITTER
|
$65.07 |
$45.35 |
$110.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POINTER, CLEANER AND CAULKER
|
$41.96 |
$33.38 |
$75.34 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 3-A ASPHALT PLANT; BOILER; CONCRETE MIXING PLANTS; CONCRETE PUMP; FIREMEN; FORKLIFT; FORKLIFT; JOY DRILL OR SIMILAR T
|
$54.41 |
$31.32 |
$85.73 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 3-B COMPRESSOR OVER 125 CU. FEET; CONVEYOR BELT MACHINE REGARDLESS OF SIZE; LIGHTING UNIT; WELDING MACHINE; AND COMPR
|
$52.25 |
$31.32 |
$83.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 4-A AIR TRACTOR DRILL; BATCH PLANT; BENDING MACHINE; CONCRETE BREAKER; CONCRETE SPREADER; CURB CUTTER MACHINE; FARM T
|
$54.33 |
$31.32 |
$85.65 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5 MOTORIZED ROLLER NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS 2.00 CRANE OPE
|
$45.94 |
$31.32 |
$77.26 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5 OILER NOTES: LOADER OPERATOR .50 SHOVAL OPERATORS 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT
|
$64.02 |
$35.25 |
$99.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5-A MASTER MECHANIC NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS 2.00 CRANE OP
|
$61.95 |
$31.32 |
$93.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5-B UTILITY MAN NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS 2.00 CRANE OPERAT
|
$47.00 |
$31.32 |
$78.32 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 6 WAREHOUSE MAN NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS 2.00 CRANE OPERAT
|
$49.26 |
$31.32 |
$80.58 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PUMP-AIR-STEAM; TAR JOINT MACHINE; VIBRATOR; COMPRESSOR TRUCK MOUNTED NOTES: LOADER OPERATOR .50 SHOVAL OPERATORS 1.00 HAZMAT PREMIUM OVER REGULAR RAT
|
$44.19 |
$35.25 |
$79.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ROOFER
|
$50.25 |
$32.62 |
$82.87 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SHEET METAL WORKER
|
$55.29 |
$47.43 |
$102.72 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
SPRINKLER FITTER
|
$57.20 |
$32.66 |
$89.86 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
STEEL CUTTING MACHINE; STONE CRUSHER; SWEEPER; TURBOJET BURNER OR SIMILAR; WELL DRILLING MACHINE ; WINCH TRUCK ""A"" FRAME. JOHN HENRY DRILL OR SIMILA
|
$56.81 |
$35.25 |
$92.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO FINISHER
|
$49.59 |
$34.25 |
$83.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TERRAZZO WORKER/SETTER
|
$64.62 |
$37.63 |
$102.25 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY
|
$70.41 |
$35.25 |
$105.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY
|
$51.57 |
$35.25 |
$86.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY
|
$57.84 |
$35.25 |
$93.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY
|
$68.63 |
$35.25 |
$103.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE FINISHER
|
$49.59 |
$34.25 |
$83.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TILE LAYER
|
$64.40 |
$37.13 |
$101.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TON UP TO 25 TON) NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS 2.00 CRANE OPERATORS 3.00 LOADER OPERATORS .50 S
|
$59.04 |
$31.32 |
$90.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$59.19 |
$35.25 |
$94.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$75.13 |
$35.25 |
$110.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$77.82 |
$35.25 |
$113.07 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$64.02 |
$35.25 |
$99.27 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$59.67 |
$35.25 |
$94.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$63.70 |
$35.25 |
$98.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVIN
|
$60.42 |
$35.25 |
$95.67 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |