BRICKLAYERS, CEMENT MASONS, STONE MASONS, POINTERS, CAULKERS AND CLEANERS: BUILDING CONSTRUCTION
|
$33.68 |
$29.89 |
$63.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER
|
$39.52 |
$27.16 |
$66.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASONS: HEAVY/HIGHWAY CONSTRUCTION
|
$38.63 |
$25.05 |
$63.68 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO
|
$40.81 |
$6.99 |
$47.80 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA
|
$20.53 |
$6.39 |
$26.92 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE
|
$38.73 |
$6.93 |
$45.66 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$42.29 |
$30.66 |
$72.95 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$52.86 |
$35.60 |
$88.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$47.57 |
$31.03 |
$78.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT
|
$31.72 |
$29.87 |
$61.59 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER
|
$63.14 |
$33.82 |
$96.96 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid
|
$64.59 |
$42.92 |
$107.51 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga
|
$35.34 |
$30.12 |
$65.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t
|
$55.40 |
$31.78 |
$87.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un
|
$61.56 |
$36.21 |
$97.77 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g
|
$49.25 |
$31.15 |
$80.40 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIANS: ELECTRICIANS
|
$50.50 |
$35.03 |
$85.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER
|
$37.16 |
$30.68 |
$67.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER GROUP 1 LABORERS; FLAGGERS; OUTBOARD AND HAND BOATS
|
$35.56 |
$25.60 |
$61.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: GROUP 2 BULL FLOAT; CHAIN SAW; CONCRETE AGGREGATE BIN; CONCRETE BOOTMAN; GIN BUGGY; HAND OR MACHINE VIBRATOR; JACKHAMMER; MASON TENDER; MORTA
|
$35.76 |
$25.60 |
$61.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: GROUP 3 ALL ROCK OR DRILL MACHINE OPERATORS; ACETYLENE TORCH OPERATOR; ASPHALT RAKER; POWDERMAN FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; M
|
$35.96 |
$25.60 |
$61.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: GROUP 4 BLASTERS; FORM SETTERS; STONE OR GRANITE CURB SETTERS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LAB
|
$36.16 |
$25.60 |
$61.76 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORER: GROUP 5 HAZARDOUS WASTE REMOVAL FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; THANKSGIVING DAY; CHRI
|
$38.76 |
$25.60 |
$64.36 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
MARBLE MASONS, TILE LAYERS AND TERRAZZO WORKERS: BUILDING CONSTRUCTION
|
$33.68 |
$29.89 |
$63.57 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS
|
$28.80 |
$24.73 |
$53.53 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS
|
$29.70 |
$24.73 |
$54.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS
|
$29.10 |
$24.73 |
$53.83 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS
|
$29.30 |
$24.73 |
$54.03 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PLUMBER, PIPEFITTER, STEAMFITTER
|
$35.51 |
$24.57 |
$60.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO
|
$55.85 |
$33.40 |
$89.25 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY
|
$54.97 |
$33.40 |
$88.37 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 3
|
$51.69 |
$33.40 |
$85.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DA
|
$65.51 |
$33.40 |
$98.91 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, C
|
$60.35 |
$33.40 |
$93.75 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY
|
$58.85 |
$33.40 |
$92.25 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS
|
$57.20 |
$33.40 |
$90.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 1 YARDMAN; PICKUPS; PANEL TRUCKS; FLATBOY MATERIALS TRUCKS; SINGLE AXLE DUMP TRUCKS; DUMPSTERS; RECEIVERS; GREASERS; TRUCK TIREMAN
|
$35.48 |
$31.58 |
$67.06 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVER GROUP 2 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED; STRADDLE CARRIER; SELF
|
$35.83 |
$31.58 |
$67.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |