Wage Determination NY20260009-16097-hvy

Jefferson, NY · heavy · Rev. 2 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination NY20260009-16097-hvy covers 57 trade classifications for heavy construction in Jefferson, NY. Total packages (base + fringe) range from $26.92/hr to $107.51/hr, with the highest going to ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: NY20260009-16097-hvy
Revision: 2
Type: heavy
County: Jefferson
State: NY
Effective: May 17, 2026
Trades covered: 57
Highest rate: $107.51/hr
Official source: SAM.gov reference NY20260009View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $35.23 $26.61 $61.84 $0.00 $0.00 $0.00 $0.00
CARPENTERS: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY $39.52 $27.16 $66.68 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $43.50 $28.38 $71.88 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY RA $58.44 $38.44 $96.88 $0.00 $0.00 $0.00 $0.00
GLAZIER $31.05 $31.55 $62.60 $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL, ORNAMENTAL, REINFORCING PRECAST CONCRETE ERECTOR, MACHINERY MOVER & RIGGER, FENCE ERECTOR, STONE DERRICKMAN, WELDER, SHEETER $37.16 $30.68 $67.84 $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL, ORNAMENTAL, RODMAN, MACHINERY MOVERS & RIGGER, FENCE ERECTOR, REINFORCING, STONE DERRICKMAN $35.50 $31.39 $66.89 $0.00 $0.00 $0.00 $0.00
LABORERS: HEAVY & HIGHWAY GROUP 1 $31.27 $27.80 $59.07 $0.00 $0.00 $0.00 $0.00
LABORERS: HEAVY & HIGHWAY GROUP 2 $31.27 $27.80 $59.07 $0.00 $0.00 $0.00 $0.00
LABORERS: HEAVY & HIGHWAY GROUP 3 $31.47 $27.80 $59.27 $0.00 $0.00 $0.00 $0.00
LABORERS: HEAVY & HIGHWAY GROUP 4 $31.67 $27.80 $59.47 $0.00 $0.00 $0.00 $0.00
LABORERS: HEAVY & HIGHWAY GROUP 5 $34.27 $27.80 $62.07 $0.00 $0.00 $0.00 $0.00
PAINTER, BRIDGE BRIDGES $42.06 $30.59 $72.65 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH & ROLL, DRYWALL TAPING/FINISHING LEWIS COUNTY $27.27 $26.23 $53.50 $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY/SANDBLASTING/STRUCTURAL STEEL LEWIS COUNTY $27.77 $26.23 $54.00 $0.00 $0.00 $0.00 $0.00
PAINTERS: BRIDGE (JEFFERSON COUNTY; LEWIS COUNTY; ST. LAWRENCE COUNTY) $42.06 $30.59 $72.65 $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER (JEFFERSON, LEWIS AND ST. LAWRENCE COUNTIES) $31.43 $23.61 $55.04 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 1 $36.84 $23.80 $60.64 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $55.85 $33.40 $89.25 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $54.97 $33.40 $88.37 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $51.69 $33.40 $85.09 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DA $65.51 $33.40 $98.91 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, C $60.35 $33.40 $93.75 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY $58.85 $33.40 $92.25 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS $57.20 $33.40 $90.60 $0.00 $0.00 $0.00 $0.00
ROOFER $35.80 $25.99 $61.79 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER: INCL. HVAC DUCT $36.29 $23.31 $59.60 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER: PROJECTS OVER $10 MILLION $46.29 $23.31 $69.60 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 $0.00 $0.00 $0.00 $0.00
THE EMPLOYEE IS EMPLOYED ONE DAY BEFORE AND ONE DAY AFTER THE HOLIDAY) $37.23 $19.51 $56.74 $0.00 $0.00 $0.00 $0.00
TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES GROUP 1 RATE PLUS 1.10 FOOTNOTE: A. PAI $38.84 $23.80 $62.64 $0.00 $0.00 $0.00 $0.00
TON CAPACITY AND OVER) GROUP 1 RATE PLUS 1.75 ALL HYDRAULIC CRANES GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES GROUP 1 RATE PLUS 1.10 FOOTNOTE: A. PAI $30.68 $23.80 $54.48 $0.00 $0.00 $0.00 $0.00
TON CAPACITY TO 99 TON CAPACITY) GROUP 1 RATE PLUS 1.25 ALL HYDRAULIC CRANES GROUP 1 RATE PLUS 1.10 FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORI $34.78 $23.80 $58.58 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 PICK-UPS, PANEL TRUCKS, FLATBOY MATERIAL TRUCKS, SINGLE AXLE DUMP TRUCKS, DUMPSTERS, GREASERS, TRUCK TIREMEN,, PARTS CHASER, TA $34.81 $27.02 $61.83 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 SPECIAL EARTH MOVING QUIPMENT, OR SIMILAR OFF HIGHWAY EQUIPMENT, WHERE NOT SELF LOADED, STRADDLE CARRIER, AND SELF CONTAINED CO $35.03 $27.02 $62.05 $0.00 $0.00 $0.00 $0.00
View all WDs for Jefferson → Revision history →