Wage Determination NJ20260030-16034-bld

Cumberland, NJ · building · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination NJ20260030-16034-bld covers 36 trade classifications for building construction in Cumberland, NJ. Total packages (base + fringe) range from $49.99/hr to $110.29/hr, with the highest going to ELEVATOR A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of B. Eight Paid. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: NJ20260030-16034-bld
Revision: 1
Type: building
County: Cumberland
State: NJ
Effective: May 17, 2026
Trades covered: 36
Highest rate: $110.29/hr
Official source: SAM.gov reference NJ20260030View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS REMOVAL LABORER The removal, abatement, enclosure and decontamination of personal protective equipment, chemical protective clothing and mach $28.37 $21.62 $49.99 $0.00 $0.00 $0.00 $0.00
ASBESTOS WORKER/HEAT & FROST INSULATOR (Includes the application of all insulating materials, protective coverings, coatings and finishings to all typ $55.80 $40.80 $96.60 $0.00 $0.00 $0.00 $0.00
BRICKLAYER Work on high stacks: 22% per hour additional $45.20 $33.26 $78.46 $0.00 $0.00 $0.00 $0.00
CARPENTER $57.42 $34.17 $91.59 $0.00 $0.00 $0.00 $0.00
CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter $57.42 $34.17 $91.59 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $53.21 $33.42 $86.63 $0.00 $0.00 $0.00 $0.00
DRYWALL FINISHER/TAPER $44.87 $30.15 $75.02 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN : CABLE SPLICER ON LEAD CABLE $46.51 $34.39 $80.90 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN AND CABLE SPLICER $55.05 $48.76 $103.81 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: TELEDATA TECHNICIANS: 15 VOICE DATA LINES OR LESS $41.00 $32.75 $73.75 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: TELEDATA TECHNICIANS: 16 VOICE DATA LINES OR MORE AND FIBER OPTICS $41.00 $32.75 $73.75 $0.00 $0.00 $0.00 $0.00
ELEVATOR A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of B. Eight Paid $71.85 $38.44 $110.29 $0.00 $0.00 $0.00 $0.00
GLAZIER Work at 30 ft. above the working surface, or on a swing stage: $1.00 per hour additional $49.96 $35.11 $85.07 $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $53.24 $38.40 $91.64 $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL AND ORNAMENTAL $54.24 $38.40 $92.64 $0.00 $0.00 $0.00 $0.00
LABORER: ASPHALT RAKER, ASPHALT SHOVELER, ASPHALT SPREADER, COMMON OR GENERAL LABORER, LANDSCAPE LABORER, PIPELAYER, POWER TOOL OPERATOR AND SCREEDMAN $35.75 $30.22 $65.97 $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE $36.50 $30.22 $66.72 $0.00 $0.00 $0.00 $0.00
MARBLE SETTER $64.66 $40.97 $105.63 $0.00 $0.00 $0.00 $0.00
MILLWRIGHT Work of erection and dismantling of elevators and towers, such as concrete conveyors and temporary material elevators, scaffolding or other $58.84 $35.06 $93.90 $0.00 $0.00 $0.00 $0.00
PAINTER $45.55 $29.86 $75.41 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $56.30 $50.76 $107.06 $0.00 $0.00 $0.00 $0.00
PLASTERER $38.37 $31.64 $70.01 $0.00 $0.00 $0.00 $0.00
PLUMBER $56.30 $50.76 $107.06 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE; DRILL; ELEVATING GRADER; EXCAVATOR; FRONT E $61.72 $37.50 $99.22 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE; HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER; S $60.13 $37.50 $97.63 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR; FORKLIFT; FRONT END LOADER; LULL; MAN LIFT/OUTSIDE ELEVATOR; MECHANIC; PAVE $58.22 $37.50 $95.72 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR; FARM TRACTOR; FRONT END LOADER; HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDO $56.59 $37.50 $94.09 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 OILER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER $52.88 $37.50 $90.38 $0.00 $0.00 $0.00 $0.00
ROOFER: ALL OTHER Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those day $46.03 $34.27 $80.30 $0.00 $0.00 $0.00 $0.00
ROOFER: Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those days on which $35.95 $21.85 $57.80 $0.00 $0.00 $0.00 $0.00
ROOFER: SLATE AND Mopper, and operator of felt-laying machine: $.50 per hour Work applying roofing material, on any new construction job, on those day $38.95 $21.85 $60.80 $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $59.08 $47.06 $106.14 $0.00 $0.00 $0.00 $0.00
SOFT FLOOR LAYER $57.42 $34.17 $91.59 $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $59.19 $36.51 $95.70 $0.00 $0.00 $0.00 $0.00
TERRAZZO FINISHER $43.63 $32.12 $75.75 $0.00 $0.00 $0.00 $0.00
TILE SETTER $52.31 $38.01 $90.32 $0.00 $0.00 $0.00 $0.00
View all WDs for Cumberland → Revision history →