BRICKLAYER (HUNTERDON COUNTY; MIDDLESEX COUNTY (DOES NOT INCLUDE THE BOROUGH OF DUNELLEN; TOWNSHIP OF EDISON; TOWNSHIP OF PISCATAWAY; BOROUGH OF SOUTH
|
$49.57 |
$37.06 |
$86.63 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
BRICKLAYER WORK 100 DEGREES F. AND OVER: TO BE PAID AT THE RATE OF DOUBLE TIME. WORK ON HIGH STACKS: 22% PER HOUR ADDITIONAL
|
$57.70 |
$45.92 |
$103.62 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CARPENTER
|
$57.42 |
$34.02 |
$91.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASON
|
$53.21 |
$33.72 |
$86.93 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
CEMENT MASON CEMENT MASON: EPOXY, ACID AND LATEX WORK: $.50 PER HOUR ADDITIONAL
|
$45.20 |
$33.26 |
$78.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
DOCK BUILDER & PILEDRIVERMEN WORK ON LAND PILE DRIVING, WHILE HANDLING AND WORKING WITH CREOSOTE AND CREOSOTE-IMPREGNATED PRODUCTS: $.25 PER HOUR ADDI
|
$52.98 |
$52.44 |
$105.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN (HUNTERDON COUNTY (TOWNSHIP OF DELAWARE; TOWNSHIP OF EAST AMWELL; BOROUGH OF FLEMINGTON; CITY OF LAMBERTVILLE; TOWNSHIP OF RARITAN; BOROUG
|
$37.35 |
$27.17 |
$64.52 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIAN: CABLE SPLICER (BURLINGTON COUNTY; MERCER COUNTY
|
$63.82 |
$41.99 |
$105.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIANS:, CABLE SPLICER (MIDDLESEX COUNTY; SOMERSET COUNTY (TOWNSHIP OF FRANKLIN):) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDI
|
$45.20 |
$33.26 |
$78.46 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIANS:, ELECTRICIAN (MIDDLESEX COUNTY; SOMERSET COUNTY (TOWNSHIP OF FRANKLIN):) WORK ON LINE VOLTAGE OF 440 VOLTS AND OVER: 10% PER HOUR ADDITI
|
$59.29 |
$33.56 |
$92.85 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
ELECTRICIANS:: ELECTRICIAN AND CABLE SPLICER (ATLANTIC COUNTY; BURLINGTON COUNTY (SOUTH OF A LINE FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON BO
|
$55.05 |
$48.76 |
$103.81 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKER
|
$54.24 |
$40.40 |
$94.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: HIGHWAY CONSTRUCTION: (ATLANTIC COUNTY; BURLINGTON COUNTY; CAPE MAY COUNTY; CUMBERLAND COUNTY; OCEAN COUNTY
|
$54.24 |
$40.40 |
$94.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: REINFORCING (MONMOUTH COUNTY; OCEAN COUNTY
|
$49.94 |
$50.32 |
$100.26 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
IRONWORKERS: STRUCTURAL (MONMOUTH COUNTY; OCEAN COUNTY
|
$52.24 |
$50.32 |
$102.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: ASPHALT WORK
|
$50.95 |
$38.53 |
$89.48 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: ASPHALT WORK: BLASTER PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESI
|
$55.45 |
$38.53 |
$93.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: ASPHALT WORK: FINISHER; RAMMER; SETTER OF BRICK OR STONE PAVERS; HARDSCAPING; GUNITE NOZZLE PERSON; STONECUTTER; FORM
|
$51.90 |
$38.53 |
$90.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: ASPHALT WORK: PIPELAYER; LASER PERSON; CONDUIT AND DUCT LINE LAYER; JACKHAMMER; CHIPPING HAMMER; PAVEMENT BREAKER; CON
|
$51.65 |
$38.53 |
$90.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: GROUP 1 BASIC LABORER; LANDSCAPE LABORER; RAILROAD TRACK LABORER; UTILITY METER INSTALLER; TRAFFIC DIRECTOR/FLAG PERSO
|
$50.95 |
$38.53 |
$89.48 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: GROUP 2 PIPELAYER; LASER PERSON; CONDUIT AND DUCT LINE LAYER; JACKHAMMER; CHIPPING HAMMER; PAVEMENT BREAKER; CONCRETE
|
$51.65 |
$38.53 |
$90.18 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: GROUP 3 FINISHER; RAMMER; SETTER OF BRICK OR STONE PAVERS; HARDSCAPING; GUNITE NOZZLE PERSON; STONECUTTER; FORM SETTER
|
$51.90 |
$38.53 |
$90.43 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LABORERS: HIGHWAY CONSTRUCTION: GROUP 4 BLASTER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE
|
$55.45 |
$38.53 |
$93.98 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: ALL OTHER WORK: BURLINGTON COUNTY; MERCER COUNTY
|
$61.84 |
$40.04 |
$101.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: ALL OTHER WORK: BURLINGTON COUNTY; MERCER COUNTY
|
$49.47 |
$32.03 |
$81.50 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: ALL OTHER WORK: WORK WITH HAZARDOUS MATERIALS: 10% PER HOUR ADDITIONAL
|
$53.35 |
$38.81 |
$92.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: CONTINUOUS PIPE-TYPE UNDERGROUND OIL-FILLED TRANSMISSION CONDUIT INSTALLATIONS
|
$61.84 |
$40.04 |
$101.88 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: CONTINUOUS PIPE-TYPE UNDERGROUND OIL-FILLED TRANSMISSION CONDUIT INSTALLATIONS
|
$49.47 |
$32.03 |
$81.50 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: CONTINUOUS PIPE-TYPE UNDERGROUND OIL-FILLED TRANSMISSION CONDUIT INSTALLATIONS
|
$45.55 |
$29.86 |
$75.41 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: CONTINUOUS PIPE-TYPE UNDERGROUND OIL-FILLED TRANSMISSION CONDUIT INSTALLATIONS: WORK WITH HAZARDOUS MATERIALS: 10% PER HOUR ADDITIO
|
$53.35 |
$38.81 |
$92.16 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION: CONTINUOUS PIPE-TYPE UNDERGROUND OIL-FILLED TRANSMISSION CONDUIT INSTALLATIONS: WORK WITH HAZARDOUS MATERIALS: 10% PER HOUR ADDITIO
|
$53.12 |
$38.81 |
$91.93 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION:: GROUNDMEN (ATLANTIC COUNTY; BURLINGTON COUNTY (SOUTH OF A LINE FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON BOROUGH FROM THE
|
$30.88 |
$33.36 |
$64.24 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION:: HEAVY EQUIPMENT OPERATOR (ATLANTIC COUNTY; BURLINGTON COUNTY (SOUTH OF A LINE FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON BO
|
$46.12 |
$42.70 |
$88.82 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
LINE CONSTRUCTION:: LINEMAN (ATLANTIC COUNTY; BURLINGTON COUNTY (SOUTH OF A LINE FOLLOWING THE WEST AND SOUTH LIMITS OF BURLINGTON BOROUGH FROM THE DE
|
$57.65 |
$49.77 |
$107.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS: (WORK ON BRIDGES)
|
$53.21 |
$33.42 |
$86.63 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS:: BRUSH AND ROLLER
|
$51.77 |
$39.65 |
$91.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PAINTERS:: SPRAY
|
$53.24 |
$40.40 |
$93.64 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
PILEDRIVER PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVID
|
$46.73 |
$41.69 |
$88.42 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 1 AUTOGRADE - COMBINATION SUBGRADER; BASE METAL SPREADER AND BASE TRIMMER; AUTOGRADE PLACER - TRIMMER SPREADER COMBIN
|
$61.72 |
$37.50 |
$99.22 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 2 ""A"" FRAME/BACKHOE COMBINATION; BOOM ATTACHMENT ON LOADER; BORING AND DRILLING MACHINE; BRUSH CHOPPER, SHREDDER AN
|
$60.13 |
$37.50 |
$97.63 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT CURBING MACHINE; ASPHALT PLANT ENGINEER; ASPHALT SPREADER; AUTOGRADE TUBE FINISHING AND TEXTURING MACHINE
|
$58.22 |
$37.50 |
$95.72 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 4 BROOM AND SWEEPER; CHIPPER; COMPRESSOR; CONCRETE SPREADER; CONVEYOR LOADER; ENGINE, LARGE DIESEL AND STAGING PUMP
|
$56.59 |
$37.50 |
$94.09 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 5 OILER; TIRE REPAIR AND MAINTENANCE HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS
|
$52.88 |
$37.50 |
$90.38 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS: GROUP 6 HELICOPTER PILOT; HELICOPTER ENGINEER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDO
|
$63.54 |
$37.50 |
$101.04 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: ""A"" FRAME; CHERRY PICKER; HOIST; JACK (SCREW, AIR, HYDRAULIC POWER-OPERATED UNIT OR CONSOLE TYPE; SIDE B
|
$58.63 |
$37.50 |
$96.13 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: AERIAL PLATFORM USED AS A HOIST; COMPRESSOR, TWO OR THREE IN BATTERY; DIRECTIONAL BORING MACHINE; ELEVATOR
|
$57.10 |
$37.50 |
$94.60 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: COMPRESSOR, SINGLE; OFF-ROAD BACK DUMP; WELDING MACHINE; WELDING SYSTEM, MULTIPLE; GENERATOR, SINGLE HAZAR
|
$53.34 |
$37.50 |
$90.84 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: CRANES; DERRICKS HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SIT
|
$68.58 |
$37.50 |
$106.08 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: CRANES; DERRICKS HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SIT
|
$70.24 |
$37.50 |
$107.74 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: HELICOPTER PILOT HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SIT
|
$61.29 |
$37.50 |
$98.79 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
POWER EQUIPMENT OPERATORS:, STEEL ERECTION: OILER; DECKHAND HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE
|
$65.74 |
$37.50 |
$103.24 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 1 DRIVERS OF THE FOLLOWING TYPE VEHICLES: DUMP, FLAT, FLOAT, PICK-UP, CONTAINER HAULER, FUEL, WATER SPRINKLER, ROAD OIL, STRINGE
|
$48.88 |
$42.66 |
$91.54 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 2 DRIVER OF 3-AXLE TRUCKS AND FLOATS (BURLINGTON COUNTY; MERCER, MONMOUTH AND OCEAN COUNTIES:) HAZARDOUS WASTE REMOVAL WORK: WOR
|
$48.78 |
$42.66 |
$91.44 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 2 TRUCK DRIVER, DUMP TRUCK DRIVER, WATER TRUCK DRIVER, TRANSIT MIX DRIVER, PICK-UP TRUCK DRIVER, TANK TRUCK DRIVER, TRACK TRUCK
|
$48.23 |
$25.98 |
$74.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 3 DRIVER OF ALL EUCLID-TYPE VEHICLES: EUCLID, INTERNATIONAL HARVESTER, WABCO, CATERPILLAR, KOEHRING TRACTOR AND WAGON, DUMPTOR
|
$48.68 |
$42.66 |
$91.34 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 3 TOW TRUCK DRIVER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER
|
$48.23 |
$25.98 |
$74.21 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 4 TRAILER TRUCK DRIVER, WINCH TRUCK DRIVER, OFF-ROAD DUMP TRUCK DRIVER, FUEL TRUCK DRIVER, TRACTOR TRAILER DRIVER, ASPHALT OIL D
|
$48.58 |
$25.98 |
$74.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 4 WINCH TRAILER DRIVER (BURLINGTON COUNTY; MERCER, MONMOUTH AND OCEAN COUNTIES) HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR
|
$48.63 |
$42.66 |
$91.29 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |
|
TRUCK DRIVERS:, GROUP 5 MECHANIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DI
|
$48.58 |
$25.98 |
$74.56 |
$0.00 |
$0.00 |
$0.00 |
$0.00 |