Wage Determination MS20260046-15635-bld
Sunflower, MS · building · Rev. 1 · Effective May 17, 2026
Quick Answer
Wage determination MS20260046-15635-bld covers 12 trade classifications for building construction in Sunflower, MS. Total packages (base + fringe) range from $10.00/hr to $49.58/hr, with the highest going to IRONWORKER, STRUCTURAL. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: MS20260046-15635-bld
Revision: 1
Type: building
County: Sunflower
State: MS
Effective: May 17, 2026
Trades covered: 12
Highest rate: $49.58/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| CARPENTER | $18.11 | $1.69 | $19.80 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $20.00 | $0.00 | $20.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $17.03 | $9.10 | $26.13 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $30.00 | $19.58 | $49.58 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $10.00 | $0.00 | $10.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $12.98 | $0.00 | $12.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $12.52 | $0.75 | $13.27 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.00 | $0.00 | $18.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $15.17 | $0.00 | $15.17 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $30.41 | $11.47 | $41.88 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT INSTALLATION.$ 21.86 11.18 PIPEFITTER | $22.77 | $6.96 | $29.73 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $13.92 | $1.91 | $15.83 | $0.00 | $0.00 | $0.00 | $0.00 |