Wage Determination MI20260072-15467-hvy

St Clair, MI · heavy · Rev. 1 · Effective May 17, 2026

Revision history →
Quick Answer

Wage determination MI20260072-15467-hvy covers 37 trade classifications for heavy construction in St Clair, MI. Total packages (base + fringe) range from $24.51/hr to $86.17/hr, with the highest going to LINE CONSTRUCTION: LINEMEN/CABLE SPLICER. Federal contracts of $2,000+ for this work must pay no less than the rates below.

WD Number: MI20260072-15467-hvy
Revision: 1
Type: heavy
County: St Clair
State: MI
Effective: May 17, 2026
Trades covered: 37
Highest rate: $86.17/hr
Official source: SAM.gov reference MI20260072View on SAM.gov →

Prevailing Wage Rates

Trade Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER AND SKIDSTEER $29.93 $9.10 $39.03 $0.00 $0.00 $0.00 $0.00
BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM $47.17 $25.35 $72.52 $0.00 $0.00 $0.00 $0.00
BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM $47.99 $25.35 $73.34 $0.00 $0.00 $0.00 $0.00
BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM $48.29 $25.35 $73.64 $0.00 $0.00 $0.00 $0.00
BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM $49.79 $25.35 $75.14 $0.00 $0.00 $0.00 $0.00
BE PAID THE CRANE OPERATOR RATE DETERMINED BY THE COMBINED LENGTH OF THE MAST AND THE BOOM $51.29 $25.35 $76.64 $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.50 $36.74 $80.24 $0.00 $0.00 $0.00 $0.00
CARPENTER, INCLUDES FORM WORK $42.44 $31.43 $73.87 $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $32.23 $22.11 $54.34 $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $51.32 $28.54 $79.86 $0.00 $0.00 $0.00 $0.00
IRONWORKER: REINFORCING $36.55 $33.37 $69.92 $0.00 $0.00 $0.00 $0.00
IRONWORKER: STRUCTURAL $36.55 $35.93 $72.48 $0.00 $0.00 $0.00 $0.00
LABORER ( COMMON OR GENERAL) $23.39 $13.15 $36.54 $0.00 $0.00 $0.00 $0.00
LABORER ( GRADE CHECKER) $23.70 $13.15 $36.85 $0.00 $0.00 $0.00 $0.00
LABORER ( LANDSCAPE) $18.29 $12.85 $31.14 $0.00 $0.00 $0.00 $0.00
LABORER ( MASON TENDER-CEMENT/CONCRETE) $23.53 $13.15 $36.68 $0.00 $0.00 $0.00 $0.00
LABORER ( PIPELAYER) $23.84 $13.52 $37.36 $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - CEMENT/CONCRETE; PIPELAYER $30.35 $17.90 $48.25 $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMEN/CABLE SPLICER $61.06 $25.11 $86.17 $0.00 $0.00 $0.00 $0.00
OPERATOR, MATERIAL MOVER, TRUCK DRIVER AND LAWN SPRINKLER INSTALLER TENDER $27.71 $9.10 $36.81 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 6 REGULAR CRANE OPERATOR FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RA $46.31 $25.35 $71.66 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 7 BACKHOE/EXCAVATOR, BOBCAT/SKID LOADER, BORING MACHINE, BROOM/SWEEPER, BULLDOZER $45.34 $25.35 $70.69 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 8 FORKLIFT FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED $43.63 $25.35 $68.98 $0.00 $0.00 $0.00 $0.00
OPERATOR: POWER EQUIPMENT, EXCLUDES UNDERGROUND CONSTRUCTION: GROUP 9 OILER FOOTNOTES: TOWER CRANES: TO BE PAID THE CRANE OPERATOR RATE DETERMINED BY $35.29 $25.35 $60.64 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH & ROLLER $23.79 $12.02 $35.81 $0.00 $0.00 $0.00 $0.00
PAINTER: SPRAY $24.79 $12.02 $36.81 $0.00 $0.00 $0.00 $0.00
PILEDRIVERMAN $38.48 $30.22 $68.70 $0.00 $0.00 $0.00 $0.00
PIPEFITTER $40.41 $29.35 $69.76 $0.00 $0.00 $0.00 $0.00
PLUMBER $35.77 $35.13 $70.90 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 1 BACKHOE/ EXCAVATOR, BORING MACHINE, BULLDOZER, CRANE, GRADER/ BLADE, LOADER, ROLLER, SCRAPE $45.98 $25.25 $71.23 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 2 TRENCHER $41.25 $25.25 $66.50 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 3 BOOM TRUCK $40.52 $25.25 $65.77 $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: UNDERGROUND CONSTRUCTION GROUP 4 BROOM/ SWEEPER, FORK TRUCK, TRACTOR, BOBCAT/ SKID STEER /SKID LOADER $39.95 $25.25 $65.20 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK UNDER 8 CU. YDS.; TRACTOR HAUL TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.30 $0.75 $34.05 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK, 8 CU. YDS. AND OVER $33.40 $0.75 $34.15 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: LOWBOY/SEMI-TRAILER TRUCK FOOTNOTE: A. $470.70 PER WEEK. B. $68.70 DAILY $33.55 $0.75 $34.30 $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: OFF THE ROAD TRUCK $20.82 $3.69 $24.51 $0.00 $0.00 $0.00 $0.00
View all WDs for St Clair → Revision history →