Wage determination IA20260077-15995-bld covers 25 trade classifications for building construction in Woodbury, IA. Total packages (base + fringe) range from $14.57/hr to $94.74/hr, with the highest going to YEAR'S DAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERAN'S DAY; THANKSGIVING DAY; DAY AFTER THANKSGIVING; & CHRISTMAS DAY. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: IA20260077-15995-bld
Revision: 1
Type: building
County: Woodbury
State: IA
Effective: May 17, 2026
Trades covered: 25
Highest rate: $94.74/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BOILERMAKER | $48.48 | $33.91 | $82.39 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $29.80 | $17.16 | $46.96 | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $30.72 | $19.43 | $50.15 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $32.29 | $28.45 | $60.74 | $0.00 | $0.00 | $0.00 | $0.00 |
| DRYWALL FINISHER/TAPER | $18.70 | $5.53 | $24.23 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $40.68 | $16.95 | $57.63 | $0.00 | $0.00 | $0.00 | $0.00 |
| INSULATOR - MECHANICAL | $23.50 | $8.25 | $31.75 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: ORNAMENTAL | $35.53 | $24.45 | $59.98 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: REINFORCING | $37.50 | $30.99 | $68.49 | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER: STRUCTURAL | $32.14 | $15.91 | $48.05 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER | $20.40 | $16.20 | $36.60 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - BRICK | $14.57 | $0.00 | $14.57 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $16.11 | $0.00 | $16.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $17.41 | $0.00 | $17.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $24.20 | $9.62 | $33.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: FORKLIFT | $22.96 | $7.49 | $30.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $21.35 | $8.54 | $29.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: SPRAY | $19.77 | $6.64 | $26.41 | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $43.20 | $23.25 | $66.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $45.20 | $23.25 | $68.45 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR:- BOBCAT/SKID STEER/SKID LOADER, LOADER WITH OR WITHOUT ATTACHMENTS, PAVER, ROLLER ) | $31.44 | $18.35 | $49.79 | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR:- BULLDOZER, LOADER | $32.99 | $18.35 | $51.34 | $0.00 | $0.00 | $0.00 | $0.00 |
| ROOFER | $20.11 | $4.99 | $25.10 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, INCLUDES HVAC DUCT, AND HVAC UNIT INSTALLATION | $22.13 | $6.00 | $28.13 | $0.00 | $0.00 | $0.00 | $0.00 |