Wage Determination GA20260057-16672-hvy
Putnam, GA · heavy · Rev. 1 · Effective May 17, 2026
Quick Answer
Wage determination GA20260057-16672-hvy covers 9 trade classifications for heavy construction in Putnam, GA. Total packages (base + fringe) range from $11.48/hr to $46.71/hr, with the highest going to ELECTRICIAN. Federal contracts of $2,000+ for this work must pay no less than the rates below.
WD Number: GA20260057-16672-hvy
Revision: 1
Type: heavy
County: Putnam
State: GA
Effective: May 17, 2026
Trades covered: 9
Highest rate: $46.71/hr
Prevailing Wage Rates
| Trade | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| CARPENTER | $15.21 | $0.00 | $15.21 | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $14.11 | $1.78 | $15.89 | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $32.00 | $14.71 | $46.71 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $11.69 | $2.07 | $13.76 | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $11.48 | $0.00 | $11.48 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $18.86 | $1.76 | $20.62 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $18.88 | $1.32 | $20.20 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $15.92 | $0.00 | $15.92 | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: DUMP TRUCK | $12.00 | $2.14 | $14.14 | $0.00 | $0.00 | $0.00 | $0.00 |