BIO-REMEDIATION, PHYTO-REMEDIATION, LEAD OR HAZARDOUS MATERIAL ABATEMENT WHEN PROTECTIVE CLOTHING AND EQUIPMENT IS REQUIRED, ALL WORKING FOREMEN INCLU — Prevailing Wage Rates

Davis-Bacon prevailing wages for BIO-REMEDIATION, PHYTO-REMEDIATION, LEAD OR HAZARDOUS MATERIAL ABATEMENT WHEN PROTECTIVE CLOTHING AND EQUIPMENT IS REQUIRED, ALL WORKING FOREMEN INCLUs across all covered states and counties. Rates vary by location and construction type.

Quick Answer

Across 6 Davis-Bacon rate records nationwide, the median total package (base + fringe) for BIO-REMEDIATION, PHYTO-REMEDIATION, LEAD OR HAZARDOUS MATERIAL ABATEMENT WHEN PROTECTIVE CLOTHING AND EQUIPMENT IS REQUIRED, ALL WORKING FOREMEN INCLU is $72.30/hr, with the middle 80% of counties paying between $72.30 and $72.30/hr. The highest state average is New York at $72.30/hr; the lowest is New York at $72.30/hr.

Bottom 10%
$72.30
Median
$72.30
Average
$72.30
Top 10%
$72.30

Range: $72.30 – $72.30/hr across 1 state. Total package = base hourly rate + fringe benefits.

Average Rates by State

New York NY
Avg base: $41.90/hr
Avg total: $72.30/hr
6 rates

All Rates

6 county-level rates for BIO-REMEDIATION, PHYTO-REMEDIATION, LEAD OR HAZARDOUS MATERIAL ABATEMENT WHEN PROTECTIVE CLOTHING AND EQUIPMENT IS REQUIRED, ALL WORKING FOREMEN INCLU, ordered by state and county.

County State Type Base $/hr Fringe $/hr Total
Broome NY building $41.90 $30.40 $72.30 WD →
Broome NY heavy $41.90 $30.40 $72.30 WD →
Broome NY highway $41.90 $30.40 $72.30 WD →
Chenango NY building $41.90 $30.40 $72.30 WD →
Chenango NY heavy $41.90 $30.40 $72.30 WD →
Chenango NY highway $41.90 $30.40 $72.30 WD →
Top-paying counties for BIO-REMEDIATION, PHYTO-REMEDIATION, LEAD OR HAZARDOUS MATERIAL ABATEMENT WHEN PROTECTIVE CLOTHING AND EQUIPMENT IS REQUIRED, ALL WORKING FOREMEN INCLU →