Building Construction — Douglas, Wisconsin

WD WI20260007-15545-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER in Douglas, Wisconsin (construction type: building) is $49.17/hr base + $23.83/hr fringe = $73.00/hr total package (WD WI20260007-15545-bld, Rev. 1).

Scroll down for all 33 trade classifications covered by this determination.

WD Number: WI20260007-15545-bld
Revision: 1
Construction Type: building
State: Wisconsin (WI)
County: Douglas
Effective: May 17, 2026
Trades covered: 33
Official source: SAM.gov reference WI20260007View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER $49.17 $23.83 $73.00 Above median $0.00 $0.00 $0.00 $0.00
ASBESTOS WORKER/HEAT AND FROST INSULATOR $25.36 $8.37 $33.73 Above median +28% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $46.52 $34.63 $81.15 Above median +73% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER & TILE SETTER $48.60 $29.31 $77.91 Top 10% +106% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $40.79 $27.90 $68.69 Above median +137% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $47.22 $31.90 $79.12 Top 10% +159% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $47.46 $33.34 $80.80 Top 10% +124% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIANS: TELEDATA SYSTEM INSTALLER/TECHNICIAN. LOW VOLTAGE CONSTRUCTION, INSTALLATION, MAINTENANCE AND REMOVAL OF TELEDATA FACILITIES INCLUDING O $31.17 $20.08 $51.25 Top 10% +42% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR MECHANIC FOOTNOTE: A.PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEAR $62.52 $38.44 $100.96 +265% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $41.60 $27.89 $69.49 Bottom 10% $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $43.13 $27.89 $71.02 Bottom 10% $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $45.20 $27.89 $73.09 $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $45.73 $27.89 $73.62 Above median $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $49.28 $27.89 $77.17 Above median $0.00 $0.00 $0.00 $0.00
HAZARDOUS WASTE PREMIUMS: EPA LEVEL ""A"" PROTECTION: $3.00 PER HOUR EPA LEVEL ""B"" PROTECTION: $2.00 PER HOUR EPA LEVEL ""C"" PROTECTION: $1.00 PER $50.53 $27.89 $78.42 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKERS $42.89 $36.86 $79.75 Top 10% +80% vs market $0.00 $0.00 $0.00 $0.00
LABORER, GENERAL $36.04 $23.47 $59.51 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ASBESTOS/HAZARDOUS MATERIAL REMOVER $37.04 $23.47 $60.51 Top 10% +142% vs market $0.00 $0.00 $0.00 $0.00
LABORERS $16.34 $3.59 $19.93 -20% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: LANDSCAPE $8.73 $4.90 $13.63 Above median -45% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: BRUSH AND ROLLER..$ 36.67 27.26 PAINTERS: BRUSH AND ROLLER $38.17 $27.26 $65.43 +172% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAPERHANGER, SPRAY, TAPER $38.77 $27.26 $66.03 +175% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY, SANDBLAST, STEEL $37.27 $27.26 $64.53 +168% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: SPRAY, SANDBLAST, STEEL..$ 38.77 27.26 PAINTERS: PAPERHANGER, SPRAY, TAPER $37.27 $27.26 $64.53 +168% vs market $0.00 $0.00 $0.00 $0.00
PILEDRIVER $47.71 $30.98 $78.69 Above median $0.00 $0.00 $0.00 $0.00
PLASTERER $40.84 $25.66 $66.50 Above median +163% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER/PIPEFITTER $52.24 $27.56 $79.80 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $18.01 $3.28 $21.29 -11% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $31.61 $16.52 $48.13 +32% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $51.68 $29.73 $81.41 Above median +116% vs market $0.00 $0.00 $0.00 $0.00
TILE & MARBLE FINISHER $13.89 $8.30 $22.19 Bottom 10% $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER $36.06 $24.13 $60.19 Top 10% +118% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER $35.79 $24.13 $59.92 Top 10% +117% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Douglas, WI — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.