Highway Construction — Bristol*, Virginia
WD VA20260194-14781-hwy · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for CARPENTER, INCLUDES FORM WORK in Bristol*, Virginia (construction type: highway) is $17.65/hr base + $0.00/hr fringe = $17.65/hr total package (WD VA20260194-14781-hwy, Rev. 1).
Scroll down for all 34 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| CARPENTER, INCLUDES FORM WORK | $17.65 | $0.00 | $17.65 Above median -27% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $19.94 | $0.00 | $19.94 -14% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN, INCLUDES TRAFFIC SIGNALIZATION | $36.85 | $14.13 | $50.98 Top 10% +72% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| INSTALLER - GUARDRAIL | $24.00 | $0.00 | $24.00 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, REINFORCING | $22.71 | $0.00 | $22.71 -19% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $27.38 | $0.00 | $27.38 -2% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $15.40 | $0.00 | $15.40 -20% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $15.15 | $0.00 | $15.15 Above median -22% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: GRADE CHECKER | $15.07 | $0.00 | $15.07 -22% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $13.19 | $0.00 | $13.19 -32% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: POWER TOOL OPERATOR | $15.69 | $0.00 | $15.69 -19% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ASPHALT SPREADER AND DISTRIBUTOR | $16.51 | $0.00 | $16.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $14.97 | $0.00 | $14.97 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $19.16 | $4.45 | $23.61 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BROOM/SWEEPER | $14.32 | $0.25 | $14.57 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BULLDOZER, INCLUDING UTILITY | $15.98 | $0.00 | $15.98 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: CRANE | $25.82 | $0.00 | $25.82 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: DRILL | $24.66 | $0.00 | $24.66 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADALL | $18.65 | $0.00 | $18.65 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: GRADER/BLADE | $26.13 | $0.00 | $26.13 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: HYDROSEEDER | $16.64 | $0.00 | $16.64 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: LOADER | $18.39 | $0.00 | $18.39 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MECHANIC | $20.60 | $0.00 | $20.60 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: MILLING MACHINE | $23.12 | $3.60 | $26.72 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PAVER | $16.92 | $0.00 | $16.92 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: PILEDRIVER | $21.83 | $4.08 | $25.91 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: ROLLER | $15.53 | $0.00 | $15.53 | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: SCREED | $22.13 | $4.89 | $27.02 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| PAVEMENT MARKING OPERATOR | $20.00 | $0.00 | $20.00 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| TRAFFIC CONTROL: FLAGGER | $12.96 | $0.00 | $12.96 Above median | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER : HEAVY 7CY & UNDER | $15.36 | $0.00 | $15.36 Bottom 10% -41% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: FUEL AND LUBRICANT SERVICE | $18.25 | $0.00 | $18.25 Top 10% -30% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: HEAVY OVER 7 CY | $16.60 | $0.00 | $16.60 Bottom 10% -37% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER: SINGLE & MULTI AXLE | $16.12 | $0.00 | $16.12 -38% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Bristol*, VA — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Bristol*
Compliance Notes
- This wage determination applies to federal contracts for highway construction in Bristol*, Virginia.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.