Highway Construction — Essex, Vermont

WD VT20260051-17764-hwy · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER, INCLUDES FORM WORK in Essex, Vermont (construction type: highway) is $20.00/hr base + $1.64/hr fringe = $21.64/hr total package (WD VT20260051-17764-hwy, Rev. 1).

Scroll down for all 27 trade classifications covered by this determination.

WD Number: VT20260051-17764-hwy
Revision: 1
Construction Type: highway
State: Vermont (VT)
County: Essex
Effective: May 17, 2026
Trades covered: 27
Official source: SAM.gov reference VT20260051View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER, INCLUDES FORM WORK $20.00 $1.64 $21.64 Above median -28% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $25.34 $0.00 $25.34 -10% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $28.15 $2.03 $30.18 +5% vs market $0.00 $0.00 $0.00 $0.00
HIGHWAY/PARKING LOT STRIPING: PAINTER $20.36 $3.87 $24.23 Above median $0.00 $0.00 $0.00 $0.00
INSTALLER - SIGN $16.25 $3.20 $19.45 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $21.70 $1.60 $23.30 -21% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $28.77 $7.91 $36.68 +25% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL, INCLUDING ASPHALT RAKING, SHOVELING, SPREADING AND CONCRETE WORK $16.35 $2.63 $18.98 Above median -15% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $14.70 $1.03 $15.73 Above median -30% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $21.83 $3.91 $25.74 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $19.78 $5.09 $24.87 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BROOM/SWEEPER $19.25 $5.97 $25.22 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $21.35 $3.84 $25.19 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: CRANE $23.42 $2.38 $25.80 $0.00 $0.00 $0.00 $0.00
OPERATOR: DRILL $19.83 $3.94 $23.77 $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $21.13 $5.53 $26.66 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $21.95 $4.63 $26.58 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $23.14 $6.08 $29.22 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: MILLING MACHINE $22.50 $10.24 $32.74 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $20.54 $5.53 $26.07 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: POUNDER $22.31 $0.00 $22.31 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $19.39 $6.26 $25.65 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: SCREED $20.87 $7.24 $28.11 Above median $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: FLAGGER $12.29 $2.75 $15.04 Above median $0.00 $0.00 $0.00 $0.00
TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER $17.20 $6.71 $23.91 Above median $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER, INCLUDES ALL AXLES INCLUDING DUMP TRUCKS $18.75 $4.01 $22.76 Top 10% -16% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DISTRIBUTOR TRUCK $22.55 $11.87 $34.42 Above median +27% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Essex, VT — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Essex

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for VT20260051-17764-hwy →