Building Construction — Webb, Texas

WD TX20260273-15014-bld · Revision 1 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BOILERMAKER in Webb, Texas (construction type: building) is $33.17/hr base + $24.92/hr fringe = $58.09/hr total package (WD TX20260273-15014-bld, Rev. 1).

Scroll down for all 37 trade classifications covered by this determination.

WD Number: TX20260273-15014-bld
Revision: 1
Construction Type: building
State: Texas (TX)
County: Webb
Effective: May 17, 2026
Trades covered: 37
Official source: SAM.gov reference TX20260273View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BOILERMAKER $33.17 $24.92 $58.09 +88% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER $16.17 $0.00 $16.17 Bottom 10% -34% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $14.15 $2.42 $16.57 -28% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $12.46 $0.00 $12.46 -45% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $18.44 $4.53 $22.97 -16% vs market $0.00 $0.00 $0.00 $0.00
INSULATOR - MECHANICAL $14.04 $4.79 $18.83 Bottom 10% -18% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $12.01 $0.00 $12.01 Bottom 10% -49% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, STRUCTURAL $15.04 $4.34 $19.38 -18% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: ORNAMENTAL $28.26 $8.13 $36.39 Bottom 10% +53% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $9.20 $0.00 $9.20 -50% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $10.00 $0.00 $10.00 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $10.89 $0.96 $11.85 -35% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $11.00 $3.47 $14.47 -21% vs market $0.00 $0.00 $0.00 $0.00
LABORER: ROOF TEAROFF $10.06 $0.00 $10.06 -45% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $14.04 $1.01 $15.05 $0.00 $0.00 $0.00 $0.00
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $13.93 $0.00 $13.93 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $18.29 $1.31 $19.60 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: DRILL $16.22 $0.34 $16.56 $0.00 $0.00 $0.00 $0.00
OPERATOR: FORKLIFT $14.83 $0.00 $14.83 $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $13.07 $0.00 $13.07 Bottom 10% $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $12.87 $0.70 $13.57 $0.00 $0.00 $0.00 $0.00
OPERATOR: MECHANIC $17.00 $0.00 $17.00 $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $16.03 $0.00 $16.03 $0.00 $0.00 $0.00 $0.00
OPERATOR: ROLLER $12.70 $0.00 $12.70 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER, AND SPRAY $11.27 $0.00 $11.27 Bottom 10% -47% vs market $0.00 $0.00 $0.00 $0.00
PIPEFITTER $15.22 $3.16 $18.38 Bottom 10% -35% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $40.74 $15.35 $56.09 Above median +99% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR ( HYDRAULIC CRANES 59 TONS AND UNDER) $32.35 $13.10 $45.45 Top 10% +90% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR ( TOWER CRANE) $32.85 $13.10 $45.95 Top 10% +93% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $11.42 $0.00 $11.42 -48% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 21.13 6.53 SHEET METAL WORKER $18.40 $2.12 $20.52 Bottom 10% -24% vs market $0.00 $0.00 $0.00 $0.00
TILE FINISHER $11.22 $0.00 $11.22 Bottom 10% -46% vs market $0.00 $0.00 $0.00 $0.00
TILE SETTER $12.15 $0.00 $12.15 Bottom 10% -42% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP TRUCK $12.39 $1.18 $13.57 -47% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: FLATBED TRUCK $19.65 $8.57 $28.22 Top 10% +11% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: SEMI-TRAILER TRUCK $12.50 $0.00 $12.50 Above median -51% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: WATER TRUCK $12.00 $4.11 $16.11 -37% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Webb, TX — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Webb

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for TX20260273-15014-bld →