Building Construction — Lares, Puerto Rico
WD PR20260001-17867-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for BRICKLAYER in Lares, Puerto Rico (construction type: building) is $7.25/hr base + $0.42/hr fringe = $7.67/hr total package (WD PR20260001-17867-bld, Rev. 1).
Scroll down for all 13 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BRICKLAYER | $7.25 | $0.42 | $7.67 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $7.25 | $0.34 | $7.59 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $7.25 | $0.31 | $7.56 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER, UNSKILLED | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $7.25 | $0.31 | $7.56 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATORS | $7.25 | $0.00 | $7.25 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATORS | $7.25 | $0.26 | $7.51 | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $7.25 | $0.31 | $7.56 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| TRUCK DRIVER | $7.25 | $0.30 | $7.55 Bottom 10% | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Lares, PR — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Lares
Compliance Notes
- This wage determination applies to federal contracts for building construction in Lares, Puerto Rico.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.