Building Construction — Stephens, Oklahoma
WD OK20260064-16848-bld · Revision 1 · Effective May 17, 2026
The Davis-Bacon prevailing wage for BOILERMAKER in Stephens, Oklahoma (construction type: building) is $33.70/hr base + $24.41/hr fringe = $58.11/hr total package (WD OK20260064-16848-bld, Rev. 1).
Scroll down for all 24 trade classifications covered by this determination.
Prevailing Wage Rates — All Trades
Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.
| Trade Classification | Base $/hr | Fringe $/hr | Total Package | H&W | Pension | Vacation | Training |
|---|---|---|---|---|---|---|---|
| BOILERMAKER | $33.70 | $24.41 | $58.11 | $0.00 | $0.00 | $0.00 | $0.00 |
| BRICKLAYER | $26.92 | $13.09 | $40.01 +76% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CAPACITY CRANES. ALL TOWER CRANES | $38.09 | $19.05 | $57.14 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| CARPENTER | $15.71 | $5.50 | $21.21 -8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| CEMENT MASON/CONCRETE FINISHER | $16.10 | $0.00 | $16.10 -29% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN | $19.73 | $4.55 | $24.28 -16% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN, EXCLUDES LOW VOLTAGE WIRING AND INSTALLATION OF ALARMS | $23.00 | $3.64 | $26.64 -8% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| ELECTRICIAN: ALARM INSTALLATION | $17.50 | $2.27 | $19.77 Bottom 10% -32% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| IRONWORKER, STRUCTURAL | $32.10 | $17.38 | $49.48 Above median +115% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: COMMON OR GENERAL | $12.25 | $0.84 | $13.09 Above median -32% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - BRICK | $11.88 | $0.00 | $11.88 -38% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $13.04 | $0.00 | $13.04 -32% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LABORER: PIPELAYER | $13.03 | $0.00 | $13.03 -32% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER | $35.40 | $19.05 | $54.45 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| LESS THAN 200 TON CAPACITY | $36.14 | $19.05 | $55.19 Top 10% | $0.00 | $0.00 | $0.00 | $0.00 |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE | $19.34 | $0.74 | $20.08 | $0.00 | $0.00 | $0.00 | $0.00 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $12.15 | $0.00 | $12.15 -45% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PIPEFITTER | $41.00 | $16.03 | $57.03 +116% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| PLUMBER | $41.00 | $16.03 | $57.03 Above median +116% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 10 OILER | $27.25 | $19.05 | $46.30 Top 10% +104% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER | $34.07 | $19.05 | $53.12 Top 10% +134% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT | $28.77 | $19.05 | $47.82 Top 10% +111% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER | $33.38 | $16.36 | $49.74 +61% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
| SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 16.32 0.00 ROOFER | $15.00 | $0.29 | $15.29 Top 10% -51% vs market | $0.00 | $0.00 | $0.00 | $0.00 |
Crew Labor Cost Estimator
Estimate total federal-contract labor cost using the Stephens, OK — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.
| Trade | Workers | Hours/worker | Rate $/hr | Subtotal |
|---|
This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.
Other Construction Types in Stephens
Compliance Notes
- This wage determination applies to federal contracts for building construction in Stephens, Oklahoma.
- The Davis-Bacon Act applies to contracts ≥$2,000 involving construction, alteration, or repair of federal or federally assisted buildings.
- The total package (base + fringe) is the minimum hourly labor cost per worker. Employers may satisfy fringe requirements by contributing to bona fide benefit plans.
- Apprentices must be registered with a DOL-approved apprenticeship program to be paid apprentice rates.
- Contractors must post this wage determination at the job site. Certified payroll records must be submitted weekly using Form WH-347.
- If a trade classification you need isn't listed below, request a conformance from the DOL Wage and Hour Division.