Building Construction — Grady, Oklahoma

WD OK20260045-14390-bld · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for BRICKLAYER in Grady, Oklahoma (construction type: building) is $26.92/hr base + $13.09/hr fringe = $40.01/hr total package (WD OK20260045-14390-bld, Rev. 2).

Scroll down for all 41 trade classifications covered by this determination.

WD Number: OK20260045-14390-bld
Revision: 2
Construction Type: building
State: Oklahoma (OK)
County: Grady
Effective: May 17, 2026
Trades covered: 41
Official source: SAM.gov reference OK20260045View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
BRICKLAYER $26.92 $13.09 $40.01 +76% vs market $0.00 $0.00 $0.00 $0.00
CAPACITY CRANES. ALL TOWER CRANES $38.09 $19.05 $57.14 Top 10% $0.00 $0.00 $0.00 $0.00
CARPENTER $27.79 $10.05 $37.84 +65% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $14.45 $0.00 $14.45 -37% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION $16.31 $2.96 $19.27 Bottom 10% -16% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $16.72 $0.00 $16.72 -26% vs market $0.00 $0.00 $0.00 $0.00
DRYWALL FINISHER/TAPER $14.25 $0.00 $14.25 $0.00 $0.00 $0.00 $0.00
DRYWALL HANGER, INCLUDES METAL STUD INSTALLATION $14.08 $0.00 $14.08 Top 10% -38% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $41.40 $13.14 $54.54 +89% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $24.26 $9.76 $34.02 +18% vs market $0.00 $0.00 $0.00 $0.00
FENCE ERECTOR $16.00 $0.00 $16.00 Above median $0.00 $0.00 $0.00 $0.00
GLAZIER $12.02 $2.42 $14.44 Bottom 10% -33% vs market $0.00 $0.00 $0.00 $0.00
HVAC MECHANIC $21.64 $6.46 $28.10 Top 10% +15% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER, REINFORCING $17.11 $0.00 $17.11 -26% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKER: ORNAMENTAL AND STRUCTURAL $32.10 $17.38 $49.48 Bottom 10% +115% vs market $0.00 $0.00 $0.00 $0.00
LABORER: COMMON OR GENERAL $11.40 $0.00 $11.40 -41% vs market $0.00 $0.00 $0.00 $0.00
LABORER: LANDSCAPE $13.75 $0.00 $13.75 -29% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - BRICK $12.00 $0.00 $12.00 -38% vs market $0.00 $0.00 $0.00 $0.00
LABORER: MASON TENDER - CEMENT/CONCRETE $13.00 $1.91 $14.91 Above median -23% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PIPELAYER $12.39 $0.00 $12.39 -36% vs market $0.00 $0.00 $0.00 $0.00
LABORER: PLASTER TENDER $12.00 $0.00 $12.00 Above median -38% vs market $0.00 $0.00 $0.00 $0.00
LESS THAN 100 TON CAPACITY. CRANE EQUIPMENT 3 CU. YD. AND OVER GUY DERRICK WHIRLEY POWER DRIVEN HOLE DIGGER $35.40 $19.05 $54.45 Top 10% $0.00 $0.00 $0.00 $0.00
LESS THAN 200 TON CAPACITY $36.14 $19.05 $55.19 Top 10% $0.00 $0.00 $0.00 $0.00
MILLWRIGHT $29.15 $11.81 $40.96 Bottom 10% +38% vs market $0.00 $0.00 $0.00 $0.00
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $21.25 $4.35 $25.60 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: BULLDOZER $20.64 $2.35 $22.99 Above median $0.00 $0.00 $0.00 $0.00
OPERATOR: GRADER/BLADE $14.28 $1.70 $15.98 $0.00 $0.00 $0.00 $0.00
OPERATOR: LOADER $16.18 $0.00 $16.18 $0.00 $0.00 $0.00 $0.00
OPERATOR: PAVER $13.38 $1.54 $14.92 $0.00 $0.00 $0.00 $0.00
PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING $12.17 $0.00 $12.17 Above median -45% vs market $0.00 $0.00 $0.00 $0.00
PAY CREDIT FOR EMPLOYEE WHO HAS WORKED IN BUSINESS MORE THAN 5 YEARS; 6% FOR LESS THAN 5 YEARS' SERVICE $51.11 $38.44 $89.55 Bottom 10% $0.00 $0.00 $0.00 $0.00
PIPEFITTER: INCLUDING HVAC PIPE INSTALLATION $41.00 $16.03 $57.03 +116% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER $41.00 $16.03 $57.03 Above median +116% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 10 OILER; SEMI- TRAILER TRUCK DRIVER $27.25 $19.05 $46.30 Top 10% +104% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 4 CRANES WITH BOOM INCL. JIB LESS THAN 100 FT AND LESS THAN 3 CU. YD.; OVERHEAD MONORAIL CRANE AND BULLDOZER $34.07 $19.05 $53.12 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR: GROUP 8 FORKLIFT $28.77 $19.05 $47.82 Top 10% +111% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $26.30 $10.34 $36.64 +62% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER $33.38 $16.36 $49.74 +61% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER, EXCLUDES HVAC DUCT INSTALLATION.$ 19.45 6.38 PLASTERER $17.50 $0.00 $17.50 -43% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $39.05 $25.77 $64.82 +146% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: DUMP AND FLATBED TRUCK $11.60 $0.00 $11.60 Top 10% -54% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Grady, OK — Building construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.