Highway Construction — Pembina, North Dakota

WD ND20260001-17895-hwy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for CARPENTER in Pembina, North Dakota (construction type: highway) is $38.70/hr base + $9.00/hr fringe = $47.70/hr total package (WD ND20260001-17895-hwy, Rev. 2).

Scroll down for all 24 trade classifications covered by this determination.

WD Number: ND20260001-17895-hwy
Revision: 2
Construction Type: highway
State: North Dakota (ND)
County: Pembina
Effective: May 17, 2026
Trades covered: 24
Official source: SAM.gov reference ND20260001View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
CARPENTER $38.70 $9.00 $47.70 +70% vs market $0.00 $0.00 $0.00 $0.00
CEMENT MASON/CONCRETE FINISHER $38.70 $9.00 $47.70 Above median +77% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: CABLE SPLICER:: ADAMS, BILLINGS, BOTTINEAU, BOWMAN, BURKE, DIVIDE, DUNN, EMMONS, GOLDEN VALLEY, GRANT, HETTINGER, MCHENRY, MCKENZIE, MCLE $55.35 $24.55 $79.90 Top 10% +152% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: Cass County $37.41 $16.75 $54.16 Top 10% +71% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICIAN:: ADAMS, BILLINGS, BOTTINEAU, BOWMAN, BURKE, DIVIDE, DUNN, EMMONS, GOLDEN VALLEY, GRANT, HETTINGER, MCHENRY, MCKENZIE, MCLEAN $55.35 $24.55 $79.90 Top 10% +152% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN: ELECTRICIAN:: BURLIEGH, MORTON, STARK:.$ 55.35 24.55 ELECTRICIAN: CABLE SPLICER:: BURLIEGH, MORTON, STARK $55.35 $24.55 $79.90 Top 10% +152% vs market $0.00 $0.00 $0.00 $0.00
LABORER: Group 1 $30.90 $3.40 $34.30 Top 10% +48% vs market $0.00 $0.00 $0.00 $0.00
LABORER: Group 2 $31.15 $3.40 $34.55 Top 10% +49% vs market $0.00 $0.00 $0.00 $0.00
LABORER: Group 3 $31.30 $3.40 $34.70 Top 10% +49% vs market $0.00 $0.00 $0.00 $0.00
LABORER: Group 4 $32.05 $3.40 $35.45 Top 10% +53% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: CABLE SPLICER $55.35 $24.55 $79.90 Bottom 10% +71% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: GROUNDMAN $31.32 $19.39 $50.71 Above median +8% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINE EQUIPMENT OPERATOR $47.00 $22.21 $69.21 Top 10% +48% vs market $0.00 $0.00 $0.00 $0.00
LINE CONSTRUCTION: LINEMAN $55.35 $24.55 $79.90 +71% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 1: All Cranes 60 tons and over, Cranes doing piling, sheeting, dragline/clam work, Derrick, Gentry Crane Operator, Heli $36.65 $22.45 $59.10 Top 10% +96% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 2: All Cranes 59 tons and under, Backhoe Operator 3 CY. and over, Creter Crane, Dredge Operator 12' and Over,Equipment $35.25 $22.45 $57.70 Top 10% +91% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 3: Lazer-Screed Operator, Asphalt Paving Machine Operator, Asphalt Plant Operator, Automated Grade Trimmer, Backhoe Ope $35.00 $22.45 $57.45 Top 10% +90% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 4: Articulated/Off Road Hauler, Asphalt Dump Person, Asphalt Paving Screed Operator, Backhoe - up to and including 1/2 $34.85 $22.45 $57.30 Top 10% +90% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 5: Boom Truck- A- Frame or Hydraulic 2 tons up to and including 7 tons, Broom-Self propelled, Concrete Saw, Cure Bridge $34.00 $22.45 $56.45 Top 10% +87% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATOR GROUP 6: Brakeman or Switchman, Dredge or Tugboat Deckhand, Drill Truck Gravel/Testing Operator, Form Trench Digger, Gunite O $33.20 $22.45 $55.65 Top 10% +84% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: Euclid over 20 yds $35.79 $19.28 $55.07 Top 10% +94% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: Single Axle Trucks $33.84 $19.28 $53.12 Top 10% +87% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: Tandem Tri Axle Semi, Low Boy and Off Road Heavy Duty End Dumps 20 yds & under $34.27 $19.28 $53.55 Top 10% +89% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVER: Tandem Tri/Axle Truck $33.96 $19.28 $53.24 Top 10% +88% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Pembina, ND — Highway construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Pembina

Compliance Notes

Full Davis-Bacon compliance guide →

View full revision history for ND20260001-17895-hwy →