Heavy Construction — Warren, New York

WD NY20260039-16076-hvy · Revision 2 · Effective May 17, 2026

Revision history →
Quick Answer

The Davis-Bacon prevailing wage for ASBESTOS WORKERS/INSULATOR in Warren, New York (construction type: heavy) is $41.74/hr base + $27.58/hr fringe = $69.32/hr total package (WD NY20260039-16076-hvy, Rev. 2).

Scroll down for all 69 trade classifications covered by this determination.

WD Number: NY20260039-16076-hvy
Revision: 2
Construction Type: heavy
State: New York (NY)
County: Warren
Effective: May 17, 2026
Trades covered: 69
Official source: SAM.gov reference NY20260039View on SAM.gov →

Prevailing Wage Rates — All Trades

Base hourly rates and fringe benefit requirements for all trade classifications covered by this wage determination. Total package = base + fringe.

Trade Classification Base $/hr Fringe $/hr Total Package H&W Pension Vacation Training
ASBESTOS WORKERS/INSULATOR $41.74 $27.58 $69.32 Above median +127% vs market $0.00 $0.00 $0.00 $0.00
BOILERMAKER $43.34 $27.66 $71.00 +97% vs market $0.00 $0.00 $0.00 $0.00
BRICKLAYER, MARBLE, TILE AND TERRAZZO FINISHERS FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, THANKGIVING DAY (PROVIDED THE EMPLO $29.38 $19.16 $48.54 +30% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $44.28 $24.50 $68.78 Above median +125% vs market $0.00 $0.00 $0.00 $0.00
CARPENTER $36.38 $24.65 $61.03 Above median +99% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN $48.00 $32.09 $80.09 Top 10% +115% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION OVERHEAD AND UNDERGROUND DISTRIBUTION AND MAINTENANCE WORK AND ALL OVERHEAD AND UNDERGROUND TRANSMISSION LINE WORK INCLU $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SUBSTATION: GROUND MAN TRUCK DRIVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENTS' DAY, MEMORIAL DAY, GOOD FRID $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION SWITCHING STRUCTURES; RAILROAD CATENARY INSTALLATION AND MAINTENANCE, THIRD RAIL TYPE UNDERGROUND FLUID OR GAS FILLED TR $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT CABLE SPLICER A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATIO $40.81 $6.99 $47.80 Top 10% +28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT GROUNDMAN A. NEW YEAR'S DAY, PRESIDENT'S DAY, GOOD FRIDAY, DECORATION DA $20.53 $6.39 $26.92 Top 10% -28% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION TELEPHONE, CATV FIBEROPTICS CABLE AND EQUIPMENT INSTALLER REPAIRMAN-TELEDATA LINEMAN/TECHNICIAN-EQUIPMENT OPERATOR A. NE $38.73 $6.93 $45.66 Top 10% +23% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $42.29 $30.66 $72.95 +96% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $52.86 $35.60 $88.46 Top 10% +138% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $47.57 $31.03 $78.60 Above median +111% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN LINE CONSTRUCTION: LIGHTING AND TRAFFIC SIGNAL INCLUDING ANY AND ALL FIBER OPTIC CABLE NECESSARY FOR TRAFFIC SIGNAL SYSTEMS, TRAFFIC MONIT $31.72 $29.87 $61.59 Bottom 10% +65% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER $63.14 $33.82 $96.96 Top 10% +160% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid $64.59 $42.92 $107.51 Top 10% +189% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or ga $35.34 $30.12 $65.46 Top 10% +76% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail t $55.40 $31.78 $87.18 Top 10% +134% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type undergro $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type un $61.56 $36.21 $97.77 Top 10% +163% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or g $49.25 $31.15 $80.40 Top 10% +116% vs market $0.00 $0.00 $0.00 $0.00
ELEVATOR CONSTRUCTOR FOOTNOTE: A.VACATION: 6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR HOURLY $57.73 $38.44 $96.17 +61% vs market $0.00 $0.00 $0.00 $0.00
GLAZIER $37.25 $33.54 $70.79 Above median +145% vs market $0.00 $0.00 $0.00 $0.00
HAZARDOUS MATERIAL HANDLER $41.74 $27.58 $69.32 Above median $0.00 $0.00 $0.00 $0.00
IRONWORKERS $38.50 $25.48 $63.98 Bottom 10% +40% vs market $0.00 $0.00 $0.00 $0.00
IRONWORKERS $38.75 $25.48 $64.23 Bottom 10% +40% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 1 BASIC RATE, FLAGMAN OUTBOARD AND HAND BOATS. HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE $31.27 $27.80 $59.07 +113% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 2 BULL FLOAT, CHAIN SAW, CONCRETE AGGREGATE BIN, CONCRETE BOOTMAN, GIN BUGGY, HAND OR MACHINE VIBRATOR, JACK HAMMER, MASON TENDER, MOR $31.27 $27.80 $59.07 +113% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 3 ALL ROCK OR DRILLING MACHINE OPERATORS ACETYLENE TORCH OPERATOR, ASPHALT RAKER, POWDERMAN. HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAY $31.47 $27.80 $59.27 +114% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 4 BLASTER, FORM SETTERS, STONE OR GRANITE CURB SETTERS. HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDE $31.67 $27.80 $59.47 +114% vs market $0.00 $0.00 $0.00 $0.00
LABORERS: GROUP 5 HAZARDOUS WASTE, ASBESTOS ABATEMENT AND REMOVAL. HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDE $34.27 $27.80 $62.07 +124% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP A LABORERS, MULT-TRADE TENDER, PIPELAYER, SELF-PROPELLED EQUIPMENT OPERATOR A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY $23.68 $21.45 $45.13 +63% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP B CONCRETE OR PLASTER PUMP OPERATOR, BUILDING DEMOLITION AND WRECKING A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEP $23.68 $21.45 $45.13 +63% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP C SAND BLASTER CONSTRUCTION CLEAN UP, DRILLER, WAGONJACK OR WAGON DRILL OPERATOR, METAL AND CRUB FORM SETTER, ASPHALT RAKER $23.68 $21.45 $45.13 +63% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP D ACETYLENE TORCH OPERATOR ON DEMOLITION WORK & CUTTING PIPE A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE D $23.68 $21.45 $45.13 +63% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP E BLASTER A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $23.68 $21.45 $45.13 +63% vs market $0.00 $0.00 $0.00 $0.00
LABORERS:, BUILDING: GROUP F WORKERS IN KILNS, LIQUOR TANKS, BOILERS, ETC., ASBESTOS AND/OR HAZARDOUS WASTE WORKER A. PAID HOLIDAYS: NEW YEAR'S DAY, M $25.18 $21.45 $46.63 +68% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS $48.75 $35.63 $84.38 Top 10% +213% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: LEAD ABATEMENT WORKERS $34.50 $21.69 $56.19 +109% vs market $0.00 $0.00 $0.00 $0.00
PAINTERS: PAINTERS, DRYWALL FINISHERS, SPRAY $33.50 $21.69 $55.19 Top 10% +105% vs market $0.00 $0.00 $0.00 $0.00
PLUMBER AND STEAMFITTER $44.88 $33.60 $78.48 Above median +108% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER, AUTOMATIC FINE GRADER, BACKHOE, BACKHO $57.30 $33.55 $90.85 Top 10% +135% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 2 ASPHALT PAVER, BACKHOE, BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT, BLAST OR ROTARY $56.39 $33.55 $89.94 Top 10% +133% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 3 $53.82 $33.55 $87.37 Top 10% +126% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 4 TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DA $63.30 $33.55 $96.85 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THAN $61.80 $33.55 $95.35 Top 10% +147% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THA $60.30 $33.55 $93.85 Top 10% +143% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP 7 MASTER MECHANIC FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING $58.91 $33.55 $92.46 Top 10% +140% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP A CRANE, HYDRAULIC CRANES, TOWER CRANE, LOCOMOTIVE CRANE, PILEDRIVER, CABLEWAY, DERRICKS, WHIRLIES, DRAGLINE, BOOM TR $55.42 $33.20 $88.62 Top 10% +130% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP A SHOVEL, ALL EXCAVATORS, GRADALLS, POWER ROAD GRADER, ALL CMI EQUIPMENT, FRONT-END RUBBER TIRE LOADER, TRACTOR-MOUNT $54.93 $33.20 $88.13 +128% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP B BACKHOE,, BULLDOZER, PUSHCAT, TRACTOR, TRAXCAVATOR, SCRAPER, LETOURNEAU GRADER, FORM FINE GRADER, ROAD ROLLER, BLAC $53.91 $33.20 $87.11 +126% vs market $0.00 $0.00 $0.00 $0.00
POWER EQUIPMENT OPERATORS: GROUP C FORK LIFT, HIGH LIFT, LULL, OILER, FIREMAN AND HEAVY- DUTY GREASER, BOILERS, AND STEAM GENERATORS, PUMP, VIBRATOR $51.01 $33.20 $84.21 +118% vs market $0.00 $0.00 $0.00 $0.00
ROOFER $38.05 $24.27 $62.32 Above median +105% vs market $0.00 $0.00 $0.00 $0.00
SHEET METAL WORKER A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. IF ANY OF THESE HO $33.73 $33.04 $66.77 +89% vs market $0.00 $0.00 $0.00 $0.00
SPRINKLER FITTER $47.85 $28.94 $76.79 Above median +104% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 $41.52 $31.42 $72.94 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 1 $33.65 $30.79 $64.44 Top 10% +121% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 $41.29 $31.42 $72.71 Top 10% +150% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 2 $33.95 $30.79 $64.74 Top 10% +122% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 3 SEMI-TRAILERS, LOW-BOY TRUCKS ASPHALT DISTRIBUTOR TRUCKS, AGITATOR, MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES, TRUCK MECHANIC, F $41.38 $31.42 $72.80 +150% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 4 SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED, STRADDLE CARRIER, SEL $41.52 $31.42 $72.94 Top 10% +151% vs market $0.00 $0.00 $0.00 $0.00
TRUCK DRIVERS: GROUP 5 OFF-HIGHWAY TANDEM BACK DUMP, TWIN ENGINE EQUIPMENT AND DOUBLE HITCHED EQUIPMENT WHERE NOT SELF-LOADED. FOOTNOTE: A. PAID HOLID $41.69 $31.42 $73.11 +151% vs market $0.00 $0.00 $0.00 $0.00

Crew Labor Cost Estimator

Estimate total federal-contract labor cost using the Warren, NY — Heavy construction prevailing wage rates. Add a row for each trade in your crew, set the number of workers and hours, and optionally add a burden percentage for payroll taxes, workers’ comp, and insurance.

Trade Workers Hours/worker Rate $/hr Subtotal
|
Direct labor subtotal
$0.00
Loaded cost (with burden)
$0.00

This is an estimate only. Burden percentages vary widely by state, employer experience modifier, and benefit plan structure. Davis-Bacon also requires per-trade record-keeping on Form WH-347; this calculator does not replace certified payroll reporting.

Other Construction Types in Warren

Compliance Notes

Full Davis-Bacon compliance guide →